75 requirements and 7 submission rules found in the solicitation documents for W912CH-26-R-A096. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- SECTION SF 30 BLOCK 14 CONTINUATION PAGE SUMMARY OF CHANGES Section A - Solicitation/Contract Form The following changes have been made: INFORMATION FROM TO Response Due Date 30 Oct 2026 13 Nov 2026 Miscellaneous text in this section has been modified from: SOLICITATION: W912CH-26-R-A096 AMENDMENT: 0003 1.
- Section A, Block 9 of the SF 33 (and all corresponding solicitation references) is hereby amended to change the proposal closing deadline: FROM: October 30, 2026, at 3:30 PM Eastern Time.
- Page 4 of 16 3) Provisioning Control Code (PCC) or Use-On-Code (UOC) 4) Technical Manual Code 5) Model Record Data b) Contractor Furnished Information (CFI) - The Contractor shall provide the Government with the Commercial and Government Entity Code (CAGEC) and Part Number (P/N) of the end article/end item in writing at the Logistics Guidance Conference.
- Offerors must acknowledge receipt of this Amendment 0003, in addition to all previous amendments, in their proposal submission.
- The following data items for technical data product(s) shall be developed by the Contractor for the end article and submitted to the Government by the schedule contained in the CDRL.
- 6.6 Prescreening of Part Numbers: The Contractor shall research and prescreen all submitted repair parts (CAGEC and Part Number) and technical characteristics for existing NSNs within the Department of Defense supply system.
- Do not post CUI to web pages that are publicly available or have access limited only by domain/IP restrictions.
Requirements
| ID | Requirement |
|---|---|
| R1 | Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. |
| R2 | If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified. |
| R3 | The Contractor shall test 2 unit(s) of Lot/Item 0011 as specified in this contract.Section I (contract clauses) |
| R4 | At least 10 calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.Section I (contract clauses) |
| R5 | The Contractor shall submit the first article test report within 240 calendar days from the date of this contract to IAW CDRL A002, First Article Test Report marked "FIRST ARTICLE TEST REPORT: Contract No. TBD , Lot /Item No. 0011."Section I (contract clauses) |
| R6 | If the first article is disapproved, the Contractor, upon Government request, shall repeat any or all first article tests. After each request for additional tests, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government.Section I (contract clauses) |
| R7 | The Contractor shall not deviate from this PSOW and associated DD Forms 1423. Deviation from the PSOW shall only occur by the approval and direction of the Contracting Officer (KO).Section I (contract clauses) |
| R8 | Contractor deviation from this PSOW and/or DD Form 1423 must receive prior Government approval. If a deviation is required, the Contractor will present a request, in writing, to the Contracting Officer for an In-Process Review (IPR) to present the details of the request for deviation to the appropriate office.Section I (contract clauses) |
| R9 | The Contractor shall be responsible for the development of the Maintenance Allocation Chart (MAC).Section I (contract clauses) |
| R10 | The Contractor shall be responsible for providing a Provisioning Parts List (PPL) and an Engineering Data for Provisioning (EDFP) to support the provisioning process.Section I (contract clauses) |
| R11 | The Contractor or a Contractor Designated Representative, as directed by this PSOW, shall be a required attendee at all conferences and/or review(s).Section I (contract clauses) |
| R12 | The Contractor shall present a briefing that demonstrates their understanding and how they will comply with the logistical support requirements.Section I (contract clauses) |
| R13 | At the MAC IPR the Contractor shall present the Initial MAC to the Government.Section I (contract clauses) |
| R14 | The Contractor shall have representatives that can support the IPR, present content to the Government, and respond to Government comments and questions about maintenance levels, tasks, repair parts and tools.Section I (contract clauses) |
| R15 | The Contractor shall present a detailed briefing of the theory and principles of operation of the End Item (EI) and/or sub-components, the MAC functional group breakdown, maintenance actions and processes, maintenance times, equipment troubleshooting strategy and logic. The Contractor will provide a top down breakdown engineering drawing tree of the end item to the Government personnel.Section I (contract clauses) |
| R16 | The contracted end item(s), kits, and/or accessories shall be available for Government review during the MAC IPR. The end item shall be set-up as configured for operation during the review.Section I (contract clauses) |
| R17 | If the MAC IPR is held at the Contractor facilities: The Contractor shall provide the following facilities for the IPR: 1) A sheltered, temperature controlled work area that provides protection from the weather. 2) Office space with adequate worktables and chairs. All office space and work areas shall be free of all dusts, fumes, slip, trip, and fall hazards and provide adequate work area to perform required tasks. 3) All work areas should provide adequate protection from the weather and provides for adjustable temperature controls. 4) Connection to the internet as required to perform necessary work functions.Section I (contract clauses) |
| R18 | The Contractor shall make available representatives responsible for provisioning data and representatives that can discuss technical data or engineering drawings.Section I (contract clauses) |
| R19 | If scheduled at the Contractor facility, the Contractor will provide the following facilities for the IPR: a sheltered and heated work area for the end article, restrooms, and office space with adequate worktables and chairs. The office space and work areas shall be free of all dusts, fumes, slip, trip, and fall hazards, provide adequate work area to perform tasks, protection from the weather, temperature control and internet access.Section I (contract clauses) |
| R20 | The Contractor shall present EDFP, PTD, and/or SPTD to support all sources of supply of each item on the PPL/RPSTL.Section I (contract clauses) |
| R21 | ALL EDFP, PPL, RPSTL, and TM data reviewed at the Government provisioning conference will be corrected or updated by the Contractor with the guidance received at the provisioning conference.Section I (contract clauses) |
| R22 | The Contractor shall provide copies of the MAC, Technical Manual (TM) to include RPSTL, PPL, and EDFP at the Government Provisioning Conference as required in the Government Provisioning Conference Plan.Section I (contract clauses) |
| R23 | The Contractor shall provide representatives responsible for provisioning products and a technical consultant or Field Service Representative (FSR) with expert technical knowledge of the end item.Section I (contract clauses) |
| R24 | The Contractor shall be prepared with necessary personnel, supplies, and equipment to capture text, data fields, and illustration change(s) identified during the provisioning conference for the RPSTL, PPL, and/or EDFP. The Contractor shall prepare a master mark-up of the PPL, RPSTL, and/or EDFP of change(s)/updates identified during the conference. A copy of the master mark-ups shall be delivered to the Government representative at the close of the provisioning conference.Section I (contract clauses) |
| R25 | The Contractor shall make all directed updates and corrections to the RPSTL, PPL, and EDFP per Government guidance and cataloging decisions made at the provisioning conference. Corrected and/or updated data shall be included in the next submission of deliverables to include PPL, EDFP and RPSTL.Section I (contract clauses) |
| R26 | The Contractor shall record the following for each Provisioning List Item Sequence Number (PLISN) on the PPL during the provisioning conference. The Contractor shall provide a copy of this record to the Government at the conclusion of the provisioning conference. 1) PLISN items identified with existing National Stock Number (NSN), Commercial and Government Entity Code (CAGEC), and Part Number. 2) PLISN items reviewed and accepted with acceptable EDFP data. 3) PLISN items reviewed and rejected with insufficient EDFP data and deficiency noted. 4) Nomenclature, CAGEC, Part Number, and Federal Supply Class for each PLISN.Section I (contract clauses) |
| R27 | At the Logistics Guidance Conference the Contractor shall identify to the Government their method or software package in which they will develop and record Logistics Management Information (LMI).Section I (contract clauses) |
| R28 | The Contractor shall furnish data products in clarity that every line, letter, and character of data is clearly legible. All data products shall be submitted in English and only one side of each sheet of paper will be used.Section I (contract clauses) |
| R29 | Contractor delivery of logistics data products (electronic and hardcopy) to the Government will include a transmittal letter that includes contracted item name, contract number, logistics data product, and submission number (Draft, Initial, Second, Final). A Compact Disk (CD) containing logistics data products will be clearly marked and/or tagged with the preceding data. Data products will be sent to the Contracting Officer (KO) for distribution to the appropriate office(s).Section I (contract clauses) |
| R30 | Data products submitted after the initial data product submission shall, in addition to the submittal, include a listing document of all change(s), additions, or removal(s) to the product. This listing in Contractor format shall clearly and completely identify all data that has added, changed or deleted on the data product(s) from the previous submission.Section I (contract clauses) |
| R31 | Data products shall be packed to assure arrival at destination in satisfactory condition. Containers and wrappings shall conform to best commercial shipping practices.Section I (contract clauses) |
| R32 | The Contractor shall prepare the MAC in Two-Level Maintenance (TLM) format in accordance with MIL-STD 40051-2D and AR 750-1. The Contractor shall develop and prepare a MAC in top down breakdown structure.Section I (contract clauses) |
| R33 | Parts that are not subject to maintenance shall not be listed in the MAC.Section I (contract clauses) |
| R34 | All item names identified in the MAC functional groups shall be official nomenclature in accordance with RPSTL nomenclature or other source as specified by the acquiring activity.Section I (contract clauses) |
| R35 | The Contractor shall provide a top down breakdown engineering drawing tree of the end item with sufficient detail so that the Government can verify the functional groups and NHA for each item listed on the MACSection I (contract clauses) |
| R36 | The Contractor shall develop and prepare a PPL with all Government selected data elements identified in Appendix B GEIA-STD-0007-A.Section I (contract clauses) |
| R37 | The PPL shall be provided in 80-card column format. LSA036.txt is the required file format for Department of Defense (DOD) provisioning technical documentation.Section I (contract clauses) |
| R38 | The PPL shall contain all the assemblies, subassemblies, parts, materials and components that can be disassembled, reassembled, or replaced. The PPL shall include parts, materials and items required for maintenance and operation of the End Item.Section I (contract clauses) |
| R39 | The Contractor shall identify on the PPL all interchangeable part numbers, drawing numbers, and specification numbers for each item listed in the PPL. All “P” coded items that will be provisioned as a result of the Provisioning Conference will be supported with applicable EDFP to receive an NSN.Section I (contract clauses) |
| R40 | The Contractor shall follow the Government structure of model records, i.e., part numbers, Use on Codes (UOC), and sequence. The Contractor will coordinate with the Government representative and structure the model records as the Government has structured the files within the Provisioning Master Record (PMR) within LMP.Section I (contract clauses) |
| R41 | Other than Model Record PLISN’s, all PPL items shall start with PLISN A010 (Figure 1, Item 1) and each following item incremented by 10. e.g., A010, A020, A030 through A990. After A990 continue with B010, B020 through B990 and continuing with all letters of the alphabet (excluding I and O) as the first position character.Section I (contract clauses) |
| R42 | The Contractor shall use an Approved Item Name (AIN) for all entries in the PPL. The Contractor shall review the H6 Federal Name Directory and select the most appropriate nomenclature for the item.Section I (contract clauses) |
| R43 | Trade names, copyrighted names, proprietary names that would require the use of a product or process of one company shall not be used.Section I (contract clauses) |
| R44 | The Contractor shall update the PPL and RPSTL with the Government approved SMR, CAGEC, Part Number, NSN, and description of the provisioned item.Section I (contract clauses) |
| R45 | Bulk items shall be listed for all items that are source coded “M” (Make). Bulk items are listed in the PPL by the equipment drawing number of location of where the item is to be installed and identified by a unique CAGEC and Part Number. Additional remarks in the description column identify color, size, length, or shape of these items. The stocked bulk item (bulk material the portions are manufactured from) will appear in the PPL at the end of the PLISN structure by the bulk CAGEC and part number. Bulk items shall be listed in a bulk items list at the end of the PPL. Bulk items data will contain the total dimensional quantity of each item used on the end item. i. e., length, square foot.Section I (contract clauses) |
| R46 | Make from Items must have an exclusive unique CAGEC and part number listed on the “A” Card. The unique CAGEC and part number is for the modified, or cut to length part.Section I (contract clauses) |
| R47 | Repair parts that are procured either as bare metal or in different colors (black, green, or tan) from the source of supply shall have a part number that distinctly indicates the color of the repair part, assembly, or sub-assembly. e.g., XXXX-1 for Green and XXXX-2 for Tan. The part number indicated on the EDFP must be recognized as valid by the source of supply. Repair parts and assemblies shall have the color of the part described on the remarks card of the PLISN entry of that item in the PPL and in the RPSTL.Section I (contract clauses) |
| R48 | For each potential "P" source-coded item, the Contractor shall determine a realistic unit price in US dollars. This price shall approximate the actual acquisition unit cost to the US Army at the time of initial procurement and in consideration of the projected procurement quantity. The Contractor shall require that the vendors also provide realistic unit prices with the above rationale.Section I (contract clauses) |
| R49 | The Contractor shall make maximum use of existing Government numbers for all common hardware items. In all cases where they exist, the Contractor shall use American National Standards Institute (ANSI), American Society of Mechanical Engineers (ASME), Military Specifications (MIL-SPEC), Military Standard (MS), Federal Specifications (FED-SPEC), Commercial or other Government standard numbers for items such as, but not limited to, nuts, bolts, washers, wire, rope, screws, lubricants, springs, roll pins, and clevis pins.Section I (contract clauses) |
| R50 | Common hardware shall have the dimensional characteristics described on the remarks card of the PLISN entry of that item in the PPL.Section I (contract clauses) |
| R51 | The Contractor shall identify any item on the PPL that is a Long Lead Time Item (LLTI). The LLTI related to the complexity of design, complicated manufacturing process, or limited production capability causes extended production or procurement lead time. This would preclude delivery in time to meet the operational need date (fielding date) if not ordered in advance of scheduled provisioning shall be identified in the Provisioning List Category Code field.Section I (contract clauses) |
| R52 | COEI shall be listed in the PPL. All repairable COEI that is listed separately in the MAC shall be listed in the MAC in its normal Top-Down Breakdown place. Non-repairable COEI that is not listed separately and has a Work Package associated with it (replace only) shall also be listed in the PPL in its normal place. All other COEI that is not repairable or have a Work Package associated with it and not separately listed on the MAC shall be listed after the Bulk material and shall be “B” indentured with the NHA as the Model Record (S).Section I (contract clauses) |
| R53 | BII shall be listed in the PPL after all non-repairable COEI is listed. BII is to be “B” indentured with the NHA as the Model Record (S).Section I (contract clauses) |
| R54 | AAL shall be listed in the PPL after BII Items. AAL shall be “B” indentured with the NHA as the Model Records.Section I (contract clauses) |
| R55 | Expendable Durable Items shall be listed in the PPL after AAL Items. Expendable Durable Items will be B indentured with the NHA as the Model Records.Section I (contract clauses) |
| R56 | Special Tools and TMDE shall be listed in the PPL after Expendable Durable Items. Special Tools and TMDE will be B indentured with the NHA as the Model Records.Section I (contract clauses) |
| R57 | The PPL shall contain all data fields selected from GEIA- STD-0007-A, Appendix B to this PSOW, before being accepted by the Government.Section I (contract clauses) |
| R58 | The Contractor shall develop and prepare EDFP for all items listed in PPL that do not have a current NSN assigned.Section I (contract clauses) |
| R59 | SPTD shall be provided for all “P” coded items listed in the RPSTL without a NSN. SPTD shall clearly indicate the physical characteristic(s) and/or specification(s) of the item or assembly. e.g., color, type of paint, dimensions, radius, thickness, dimensions, inlet/outlet dimensions, pressure range, length, width, height, shape, surface treatment, thread size, thread type, type of materiel, wall thickness, amperage, voltage.Section I (contract clauses) |
| R60 | At a minimum, the technical documentation shall provide the following; SPTD shall clearly and completely identify and describe the item and who, Commercial and Government Entity Code (CAGEC), either manufactures the item or from whom the item was purchased, and cost of the item. The Contractor shall provide Original Equipment Manufacturer (OEM) data for all items on the PPL.Section I (contract clauses) |
| R61 | These items shall have a unique and separate drawing that indicates what modification was performed on the provisioned item and the Contractor’s CAGEC and Contractor unique part number. The EDFP shall include the necessary information to identify the item prior to its alteration including the original part number and the name and CAGEC of the source of the original part.Section I (contract clauses) |
| R62 | The Contractor shall supply a minimum of three (3) sources. Where did this come from for any item only available from a Supplier/Distributor.Section I (contract clauses) |
| R63 | The contractor shall submit EDFP for all items that do not have a current NSN assignment.Section I (contract clauses) |
| R64 | Provisioning Technical Data shall be clearly annotated with the Provisioning Contract Control Number (PCCN), Provisioning Control Code (PCC), Provisioning Line Item Sequence Number (PLISN), Commercial and Government Entity Code (CAGEC) and Manufacturer’s Part Number. Technical data and EDFP shall match the data/drawing to the PLISN on the PPL for all items.Section I (contract clauses) |
| R65 | The Contractor shall provide a top down generation breakdown engineering drawing tree of the end item so that the Government can verify the NHA for each item listed on the PPL and associated EDFP. The drawing tree shall clearly show what functional group the assembly, subassembly and/or part is a part of and the NHA.Section I (contract clauses) |
| R66 | The Contractor shall conduct a physical audit of PTD and SPTD against the Government approved end item configuration to assure that each item identified on PTD and SPTD is accurately depicted at the time of submission of PTD and SPTD. The configuration audit results shall be included in a letter included with the EDFP submission that states certification of the PTD/SPTD against the end article and the results of the audit.Section I (contract clauses) |
| R67 | When handling CUI material, all personnel are to comply with these requirements and follow their company policy and/or applicable Non-Disclosure Agreement (NDA) concerning the protection of proprietary information in situations not clearly stated herein.Section I (contract clauses) |
| R68 | All documents containing CUI will carry the CUI markings in accordance with DoDI 5200.48. Discontinue all use of legacy or other markings not permitted or included in either the CUI Registry or DoDI 5200.48.Section I (contract clauses) |
| R69 | In accordance with (IAW) DoDI 5200.48, Controlled Unclassified Information (CUI), July 2023, all contractors supporting this contract who receive, store, or generate CUI are required to take the DoD Mandatory CUI training available on the Security Awareness Hub at : https://securityawareness.usalearning.gov/cui/index.html. Per DoDI 5200.48 and pursuant to all contractual requirements, DoD contractors require initial CUI training and annual CUI refresher training.Section I (contract clauses) |
| R70 | All personnel supporting this contract shall sign a CUI Non-disclosure Agreement prior to gaining access to the information. Personnel no longer requiring access to CUI must dispose (see “Disposal” below) or surrender any in their possession and terminate future access to it.Section I (contract clauses) |
| R71 | During working hours, take reasonable steps to minimize risk of access to CUI by unauthorized personnel. After working hours, when not in physical possession of the owner, all CUI (whether hardcopy or optical media (e.g., DVDs, CDs) that contain CUI) must be afforded a reasonable degree of physical protection to prevent theft of program information (e.g., store CUI information in locked desks or file cabinets, locked rooms, cable lock laptops, storing in a trunk, storing out of site or similar means). Do not display CUI in public places (e.g., airports, airplanes, restaurants).Section I (contract clauses) |
| R72 | Electronic storing and processing of CUI shall be in accordance with DFARS 252.204-7012 Safeguarding Controlled Defense Information and Cyber Incident Reporting. Do not process CUI on public computers (e.g., those available for use by the general public in kiosks, hotel business centers), public wireless networks or computers that do not have access control. Personally owned computers and personally owned devices are not authorized to process CUI. Portable electronic devices (e.g., smartphones, laptop computers, tablets), non-portable computers, and removable media (e.g., external hard drives, flash drives, USB drives; not including optical media) must be physically and electronically protected as described in this instruction, DFARS 252.204-7012 and DoDI 8582.01.Section I (contract clauses) |
| R73 | All transmission and/or dissemination of CUI (i.e., email and file transfers) must use NIST/NIAP-approved cryptographic products/algorithms, e.g., DoD-approved Public Key Infrastructure Certification or DoD Safe Exchange at https://safe.apps.mil/. These are available at http://iase.disa.mil/pki/eca or http://csrc.nist.gov/groups/STM/cmvp/documents/140-1/140val-all.htm. This encryption requirement includes communications that contain passcodes to teleconferences or web conferences where there is a reasonable expectation that CUI may be discussed. When encryption is not available, a government collaborative suite (aka Integrated Digital Environment [IDE]) must be used to transmit CUI.Section I (contract clauses) |
| R74 | The contractor shall ensure any covered defense information provided by the Government under this contract is destroyed or sanitized from contractor-owned media and reported in accordance with (IAW) National Institute of Standards and Technology (NIST) Special Publication (SP) 800-88, Revision 1: Guidelines for Media Sanitization (December 2014) (NIST SP 800-88, rev 1), destruction methods, or any destruction method approved for Classified National Security Information (32 CFR 2001.47) unless the CUI category's authority mandates other destruction methods (CUI Specified categories).Section I (contract clauses) |
| R75 | Report any loss of CUI to the Government Security Manager. Initial reports shall be made as expeditiously as possible in all cases within 72 hours of discovery.Section I (contract clauses) |
Recent awards in NAICS 332311
The newest federal contract awards in the same industry code from Department of Defense, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-10-01 | UH STRUCTURES INCDepartment of the Army · FY26 PN26101C DH-ACP-GRDBLDGS (X2) FY26 OMA FUNDS ARE PROVIDED TO ACC/410CSB/RCO-MIAMI TO ACQUIRE TWO (2) PRE-FABRICATED UL752 LEVEL 3 BALLISTIC ACCESS CONTROL POINT GUARD BLDGS, TO INCLUDE DELIVERY A | $285,078 |
| 2026-08-28 | MILL CREEK LLCDepartment of the Army · RELOCATABLE FACILITY | $22.43 million |
| 2026-08-17 | TOYO TRUST TOKKI CO.,LTD.Department of the Navy · PIER SHACK MOVE FROM DD2 TO INDIA PIER 1 FOR THE RUSHMORE AVAILABILITY. | $29,606 |
| 2026-08-14 | MACCAFERRI, INC.Defense Logistics Agency · 8512306344!WALL,PROTECTIVE,RAP | $4,845 |
| 2026-08-12 | ZDAAS LLCDepartment of the Air Force · VCC GUARD BOOTH | $35,512 |
| 2026-07-28 | AAR MANUFACTURING, INC.Department of the Air Force · 19 AMXS REQUIRES AN EXPANDABLE INTERNAL SLINGABLE UNIT. | $83,957 |
Source: USAspending.gov, retrieved 2026-11-24. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.