TenderAxiom

TenderAxiom · Opportunities

TELESCOPE, ELBOW: requirements and submission rules

51 requirements and 15 submission rules found in the solicitation documents for SPRDL1-27-R-A055. Use them as the start of your compliance matrix.

Solicitation number
SPRDL1-27-R-A055
Agency
DEPT OF DEFENSE / DEFENSE LOGISTICS AGENCY / DLA LAND / DLA LAND WARREN MICHIGAN / DLA LAND WARREN
NAICS
333310
Set-aside
Small Business Set Aside - Total
Responses due
30 December 2026 (32 days)
Official notice
View on SAM.gov

Submission rules that can disqualify a bid

  • Sealed offers in original and copies for furnishings the supplies or services in the Schedule will be received at the place specified in item 8, or if hand carried, in the depository located in until local time CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision Number 52.214-7 or 52.215-1.
  • If the response deadline has passed for the solicitation, vendors will need to send any late quotes, if applicable, directly to the Contract Specialist identified on the cover page of this solicitation.
  • The Administering Contracting Officer (ACO) designated by the agency administering the contract, or the Procuring Contracting Officer (PCO) if an ACO was not assigned shall submit the Contractor's request for equipment to US ARMY - ARDEC/RDAR-EIQ- EC, BLDG 92, Picatinny Arsenal, NJ 07806-5000.
  • Vendors must be registered for a sam.gov account through https://login.gov in order to manage searches and track solicitations.
  • All bids and proposals must be submitted via email to the Contract Specialist on record.
  • The Data Custodian MUST be registered for a sam.gov account through https://login.gov.
  • If a Value Engineering Change Proposal(s) (VECPs) clause is included on this contract, VECPs shall be submitted in the same manner as ECPs.
  • ECPs shall be submitted to include all Notice of Revisions (NORs) necessary to completely define the requested change.
  • Pages 2-7 of DD Form 1692 shall be submitted when required to properly explain all the potential logistics and technical impacts of the proposed change.
  • DD Form 1695 NOR or DD Form 1695-1 Tabulated NOR (or equivalents) shall be submitted to completely describe the desired change on each affected document.
  • Supply chain traceability documentation shall include: basic item description, part number; drawing or specification; national stock number, manufacturing source, manufacturing source's Commercial and Government Entity (CAGE) code, and clear identification of the name and location of all supply chain intermediaries between the manufacturer to the contractor to Government acceptance.
  • When conditions (i), (ii), or (iii) above occurs, the Contractor shall notify the Procuring Contracting Officer that a determination can be made concerning the need for the additional first article sample or portion thereof, and instructions provided concerning the submission, inspection, and notification of results.
  • Offeror must specify below the exact name, address, and CAGE of the facility where supplies to be furnished under this contract/purchase order will be available for inspection/acceptance.
  • Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review and approval prior to implementation. c.
  • (b) In order to be eligible to receive an award under this solicitation, the successful Offeror must be registered with the Department of Defense (DOD) System for Award Management (SAM).

Requirements

IDRequirement
R1Acknowledge all the amendments received from the Contracting Office by identifying the amendment number and its issue date belowSection A
R2As directed in Section L of this solicitation, interested vendors shall submit a quote or proposal via email to the Contract Specialist listed on the solicitation. The email shall include subject header: Proposal Submission - SPRDL1-XX-X-XXXX (company name) on the solicitation.Section A
R3It is Offeror's responsibility to ensure the proposal/quote is received by the Contract Specialist by the date and time specified on the cover page of this solicitation.Section A
R4Offers in response to this solicitation must be submitted for the total quantity of the items identified in the solicitation. (1) ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION. (2) OFFERS SUBMITTED FOR LESS THAN THE TOTAL QUANTITIES OF ALL THE ITEMS IN THIS SOLICITATION ARE INELIGIBLE FOR AWARD.Section A
R5Offerors shall review all documents carefully to locate this important information and direct any questions or concerns to the Contract Specialist or Contracting Officer.Section A
R6Notify the Contracting Officer immediately if any observed changes, removals, or additions affect your award eligibility, violate or alter existing quote/proposal terms, or could affect Contract performance post-award.Section A
R7Take special care to ensure all fill-in Clauses are populated and remain populated across documents received from the Contracting Office throughout the Solicitation and Award process.Section A
R8The Supply Chain Traceability Documentation referred to in clause CS8001 (DLA WRN) Contractor Retention of Supply Chain Traceability Documentation is required to be submitted at the time of offer submission by all offerors other than the manufacturer of the item. Failure to submit acceptable traceability will constitute an offer that does not meet the terms and conditions of the solicitation and therefore will not be eligible for award.Section A
R9This Procurement is a Total Small Business Set-Aside.Section A
R10A First Article Test Report is required in accordance with the clause entitled 'First Article Approval - Contractor Testing', FAR 52.209-3. First Article Test is required. Waiver may be authorized; see waiver provision in Section L. The First Article Test shall be conducted in accordance with MIL-F 13926 Fire Control Spec, MIL-DTL-48558. Number of First Article test sample(s) that shall be consumed or destroyed in testing: 3Section B
R11First Article Test and Report is Not Separately Priced (NSP) and CLIN 0001 is required to included the full price for FAT.Section B
R12Inspection/Acceptance at origin means that you contact the DCMA to arrange for a MUST Government inspection you ship the supplies called out in this order. Failure to have the BEFORE items inspected and accepted will result in their rejection at the destination. The rejected supplies will be returned to you at your expense.Section B
R13The contractor shall provide DoD unique identification, or a DoD recognized unique identification equivalent.Section B
R14To obtain these TDPs, vendors and Contractors must have a current DD 2345, Militarily Critical Technical Data Agreement on file with Defense Logistics Information Service (DLIS).Section C (statement of work)
R15Upon completion of the purposes for which Government Technical Data has been provided, the Contractor is required to destroy all documents, including all reproductions, duplications, or copies thereof as may have been further distributed by the Contractor. Destruction of this technical data shall be accomplished by: shredding, pulping, burning, or melting any physical copies of the TDP and/or deletion or removal of downloaded TDP files from computer drives and electronic devices, and any copies of those files.Section C (statement of work)
R16The Contractor is responsible for producing the shop or process drawings needed to cover intermediate steps in the manufacturing process.Section C (statement of work)
R17The Contractor is responsible for obtaining all specifications and drawings necessary to manufacture the items being solicited in accordance with the TDP including all incorporated specifications and drawings.Section C (statement of work)
R18The Contractor shall not present any production items for acceptance that incorporate any change to the TDP or other baseline documentation until notified by the Government the ECP has been approved and incorporated in the contract.Section C (statement of work)
R19The Contractor shall not present any production items for acceptance with any nonconformance to the requirements in the TDP or other baseline documentation until notified by the Government the RFV has been approved and incorporated in the contract.Section C (statement of work)
R20the Contractor, by accepting this contract, agrees to furnish only the listed manufacturer's part number(s) for those components of the contract item, except as provided in the narrative entitled NOTICE REGARDING REQUIRED MANUFACTURER'S PART NUMBER. It is further understood and agreed that references to manufacturer's part numbers herein shall be deemed to include all changes or revisions thereto which the approved manufacturer has made effective as of the first date of delivery of any of the items under this contract; provided, that no change or revision that affects the interchangeability... shall be incorporated into the contract item without the prior written approval of the Procuring Contracting Officer.Section C (statement of work)
R21No CIODS shall be used in meeting the requirements of this contract. If the use of CIODS is required in the performance of this contract, please notify the Procuring Contracting Officer immediately in writing.Section C (statement of work)
R22No Class II Ozone Depleting Substances shall be required in the performance of this contract without Government approval. If the use of Class II ODS is required in the performance of this contract, please notify the Procuring Contracting Officer immediately in writing.Section C (statement of work)
R23the Contractor, is confirming it currently has, or will obtain before delivery, and shall retain supply chain traceability documentation, as described in paragraph (2) below, demonstrating the item conforms to the technical requirements, and for part numbered items, is from an approved manufacturer.Section C (statement of work)
R24In addition, the contractor will obtain, retain, and provide to the contracting officer written documentation of all inspections and tests necessary to substantiate that the supplies furnished under this contract conform to contract requirements, including any applicable technical requirements for specified manufacturers' parts.Section C (statement of work)
R25The contractor shall make supply chain traceability documentation available to the contracting officer within three business days upon the contracting officer's request. The contracting officer determines the acceptability and sufficiency of documentation. The contractor shall retain supply chain traceability documentation for ten years after final payment under this contract for audit and other valid government purposes.Section C (statement of work)
R26Military preservation, packing, and marking for the item identified above shall be accomplished in accordance with the specific requirements identified below, all the applicable requirements of, MIL-STD-2073-1 and the Special Packaging Instruction (SPI) contained in the TDP. PRESERVATION: MILITARY LEVEL OF PACKING: B QUANTITY PER UNIT PACKAGE: 001 SPI NUMBER: 13005104, DATED - 11 JAN 23, REV DSection D
R27Shipments of identical items going to the same destination shall be palletized if they have a total cubic displacement of 50 cubic feet or more unless skids or other forklift handling features are included on the containers.Section D
R28All unit packages, intermediate packs, exterior shipping containers, and as applicable, unitized loads shall be marked in accordance with MIL-STD-129 including bar coding and a MSL label.Section D
R29All non-manufactured wood used in packaging shall be heat treated to a core temperature of 56 degrees Celsius for a minimum of 30 minutes.Section D
R30A prototype package is required to validate the sizes and fit requirements of the SPI.Section D
R31When applicable, a Product Safety Data Sheet (SDS) is required to be included with every unit pack and intermediate container and shall be included with the packing list inside the sealed pouch attached to the outside of the package.Section D
R32The Contractor shall hereby indicate the facility to which this Government Furnished Property should be shippedSection E
R33The Contractor shall be responsible for shipping the surface quality standards to the Government for certification at 12-month intervals.Section E
R34Within 30 calendar days after completion of delivery of all items on this contract requiring scratch and digs, the Contractor shall assure that the Government owned standards referenced in paragraph a above are in the same condition as when received. Upon verification by a Government representative that the standards are undamaged. The Contractor shall prepare the standards for delivery in accordance with best commercial practices. The Contractor shall ship the standards with a DD Form 1149 to US ARMY-ARDEC/RDAR-EIQ-EC, BLDG 92, Picatinny Arsenal, NJ 07806-5000.Section E
R35The first article shall be examined and tested in accordance with contract requirements, the item specification(s), Quality Assurance Provisions (QAPs) and all drawings listed in the Technical Data Package.Section E
R36The first article shall be representative of items to be manufactured using the same processes and procedures and at the same facility as contract production. All parts and materials, including packaging and packing, shall be obtained from the same source of supply as will be used during regular production.Section E
R37A First Article Test Report shall be compiled by the Contractor the results of all inspections and tests (including supplier's and vendor's inspection records and certifications, when applicable).Section E
R38When requested, the Contractor shall make available to the Government Inspector the drawings and specifications to which the product was manufactured.Section E
R39Once the Government accepts the first production test item, or accepts the first end item you deliver, (whichever comes first) you must not make design changes to any item or part that is not under Government design control.Section E
R40The Contractor shall comply with the higher-level quality standard(s) listed below. ISO 9001:2015 (21 Oct 2015) or equivalent, Tailored by excluding paragraph(s) 8.3Section E
R41Delivery under this contract must conform to the required schedule specified below, unless acceleration is acceptable.Section F (deliveries)
R42This clause is a mandatory flow-down clause; accordingly, Contractor/Subcontractor must include this clause in subcontracts for work under this solicitation and resulting contract.Section H (special requirements)
R43Contractor(s) awarded a contract with demilitarization requirements shall be responsible for maintaining an inventory system capable of recording, safeguarding and tracking all material, work in process, components associated or related to the performance of the contract for the purpose (not intended to be exclusive) of enabling the Contractor to fulfill its demilitarization obligations under this clause.Section H (special requirements)
R44The Contractor will demilitarization and apply TSCs as required on all contract excess property as dictated by the Government assigned demilitarization code and its definition and the demilitarization and trade security controls matrix in paragraph IX of this clause.Section H (special requirements)
R45Upon award, the Contractor shall designate the personnel with signature authority who can contractually bind the Contractor. Additionally, the Contractor shall provide the Procuring Contracting Officer (PCO) with a list of e-mail addresses for all administrative and technical personnel assigned to this contract.Section I (contract clauses)
R46The Contractor shall test 3 unit(s) of Lot/Item CLIN 0002 as specified in this contract. At least 15 calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.Section I (contract clauses)
R47The Contractor shall submit the first article test report within 15 calendar days from the date of this contract to PCO [insert address of the Government activity to receive the report] marked 'FIRST ARTICLE TEST REPORT: Contract No. N/A, Lot/Item No. N/A.'Section I (contract clauses)
R48By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for- ... Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities.Section I (contract clauses)
R49The Offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract.Section I (contract clauses)
R50The apparently successful offeror agrees to submit, for each item as required prior to award, a Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items. Failure to submit the Safety Data Sheet prior to award may result in the apparently successful offeror being considered nonresponsible and ineligible for award.Section I (contract clauses)
R51The Contractor shall- (1)(i) Have and maintain for the duration of the contract a current CMMC status at the following CMMC level, or higher: CMMC Level 2... for all information systems used in performance of the contract, task order, or delivery order that process, store, or transmit FCI or CUI; and (ii) Consult 32 CFR 170.23 related to the flowdown of the CMMC requirements, and flow down the correct CMMC level to subcontracts and other contractual instruments; (2) Only process, store, or transmit FCI or CUI on contractor information systems that have a CMMC status at the CMMC level required in paragraph (d)(1) of this clause, or higher; (3) Complete on an annual basis, and maintain as current, an affirmation, by the affirming officialSection I (contract clauses)

Recent awards in NAICS 333310

The newest federal contract awards in the same industry code from Department of Defense, since 1 October 2024. Use them to see who wins this kind of work and at what value.

StartAwardee and buyerAward value
2026-08-19NAUTIC-SPORT, INC.Defense Logistics Agency · 8512317381!CREEPER,MECHANIC'S$1,980
2026-08-19SILVER EAGLE MANUFACTURING CODefense Logistics Agency · 8512317068!CAP,FILLER OPENING$530
2026-08-19AFCON PRODUCTS, INC.Defense Logistics Agency · 8512311726!FILLER NECK,VEHICUL$3,864
2026-08-18DIGIS CORPORATIONDefense Logistics Agency · VIDEO MOUNT$28,916
2026-08-17LARKOS PACKING AND DISTRIBUTION INC.Defense Logistics Agency · 8512313913!INSTALLATION KIT,FI$562
2026-08-17LARKOS PACKING AND DISTRIBUTION INC.Defense Logistics Agency · 8512313625!INSTALLATION KIT,FI$8,088

Source: USAspending.gov, retrieved 2026-11-24. Award value is the obligated amount reported by the agency.

Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.

Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.

Bidding? Get a reminder 5 days before it is due

One email, with what to check before you submit. Nothing else.

Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.

Get new solicitations that match your business, free

Enter NAICS codes, keywords or both. No email when nothing matches. Unsubscribe in one click.