RF Roof Replacement Project: requirements and submission rules
27 requirements and 0 submission rules found in the solicitation documents for RFP27-005JR. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- None detected automatically: read the instructions to offerors.
Requirements
| ID | Requirement |
|---|---|
| R1 | Please include the following document s with your proposal: (1) A Schedule of V alues (2) A progress schedule based on a notice -to-proceed date of 05 Jan 2027 |
| R2 | Acceptance of Sample Subcontract terms and conditions. Please initial the applicable statement below in the space provided ( initial one statement only ) |
| R3 | The Offeror agrees that this proposal will remain valid for 90 days from the closing date specified for this RFP. |
| R4 | PPPL will determine the responsiveness of each proposal on a pass/fail basis. A proposal will be considered to be “responsive” if it is in compliance with all the requirements of the RFP. |
| R5 | PPPL reserves the right to consider any proposal “nonresponsive” and reject in total or in part, with or without prior discussion with the Offeror, if the proposal (a) is not submitted in the format specified in the RFP or does not include all of the information requested by PPPL; (b) is not in accordance with the instructions contained in the RFP; or (c) contains material irregularities of any kind. |
| R6 | PPPL will determine if an Offeror is a “responsible” prospective subcontractor, as the term is used in the Federal Acquisition Regulations (FAR) Subpart 9.1. Offerors determined not to be a responsible prospective subcontractor will not be eligible for award. |
| R7 | Therefore, Offerors’ initial proposal should contain the Offeror’s best terms and complete response from a price, schedule, quality, and technical standpoint. |
| R8 | The Offeror shall provide a description of methods the offeror uses in managing construction on similar projects, including lower -tier subcontractor coordination. This should include organizational resources and experience in utilizing industry standard construction management software. |
| R9 | A consolidated list to include the name, position title, description of project responsibilities, full-time percentage, and resume for the following key personnel: (i) Project Manager (ii) Construction Superintendent (iii) Certified Safety Professional |
| R10 | Proposed key personnel must have experience successfully managing and supervising the construction of two (2) or more projects similar in scope or complexity to the RF Roof Replacement Project within the past ten (10) years. |
| R11 | Responsive Offerors shall list at least two (2) prior projects with references completed within the past ten (10) years that are of similar type, size, scope, and complexity to that described in the RFP. |
| R12 | Offerors shall include the following information about each project: a) Project title b) Contract amount at start and completion c) Description of work and location (project type, scope, size, etc.) d) Name, address, and telephone number of Owner or Owner’s Representative and Architect of Record e) A discussion of experienced delays and cost growth f) Any significant aspects worth noting |
| R13 | Three-year average EMR of 1.00 or less and a total recordable and DART case rate at or below 85% BLS TRC/DART Rate for heavy construction. |
| R14 | Submit copy of OSHA Forms 300 and 300A for 2024 – 2026 |
| R15 | Submit explanation and/or supplemental data for periods that are out of tolerance. |
| R16 | Demonstrate that the Offeror’s 2024 – 2026 Insurance Experience Modification Rating averages equal to or less than 1.0 over a three-year period. |
| R17 | Provide backup documentation from an independent source, such as the insurance carrier, to verify ratings. |
| R18 | Joint ventures or teams shall submit the above information for each corporate entity in the joint venture or team. |
| R19 | The Offeror must submit their corporate ES&H Program (and discuss its application on the RF Roof Replacement Project) and Part 1 of the Construction Environmental Safety and Health Plan (Div. 1 Spec Section 013100), that includes acknowledgement regarding Worker Safety 10 CFR 851. Identify current and past projects that were certified under the OSHA Voluntary Protection Program. |
| R20 | The Offeror’s corporate quality program description shall be submitted along with the completed PQA Supplier Quality Survey. |
| R21 | Date Bond Executed (Must be same or later than date of contract) |
| R22 | Insert the full legal name and business address of the Principal in the space designated "Principal" on the face of the form. An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved. |
| R23 | Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. |
| R24 | When multiple corporate sureties are involved, their names and addresses shall appear in the spaces (Surety A, Surety B, etc.) headed "Corporate Surety(ies)." In the space designated "Surety(ies)" on the face of the form, insert only the letter identifier corresponding to each of the sureties. Moreover, when co-surety arrangements exist, the parties may allocate their respective limitations of liability under the bonds, provided that the sum total of their liability equals 100% of the bond penal sum. |
| R25 | When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety shall accompany the bond. |
| R26 | Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the words "Corporate Seal", and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals. |
| R27 | Type the name and title of each person signing this bond in the space provided. |
Recent awards in NAICS 238160
The newest federal contract awards in the same industry code from Department of Energy, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-08-31 | SALTER COREYDepartment of Energy · REPLACE THE EXISTING ROOFING AT ELKTON REPEATER SOUTH DAKOTA AND SPALDING REPEATER IN NEBRASKA | $23,777 |
| 2025-10-14 | NATIVE SOURCE ENTERPRISES, LLCDepartment of Energy · INSTALL ROOFING PAVERS AT THE CLARK REPEATER SITE | $12,500 |
| 2025-07-28 | NATIVE SOURCE ENTERPRISES, LLCDepartment of Energy · REPLACE ROOFING AT THE HIGHMORE REPEATER | $22,950 |
| 2025-07-01 | BRN GROUP LLCDepartment of Energy · SIOUX FALLS SUBSTATION, ROOF REPLACEMENT, WAREHOUSE, OFFICE, AND VEHICLE STORAGE BUILDING, SD | $74,388 |
| 2025-03-10 | ELEVATION CONSTRUCTION OF TEXAS LLCDepartment of Energy · SIOUX FALLS SUBSTATION, ROOF REPLACEMENT, WAREHOUSE, OFFICE, AND VEHICLE STORAGE BUILDING, SD | $0 |
| 2024-09-24 | TRI-STATE ROOFING CONTRACTORS, LLCDepartment of Energy · ROOF REPAIRS AND PREVENTATIVE MAINTENANCE | $27,589 |
Source: USAspending.gov, retrieved 2026-11-06. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.