A-E Services for Electron Injector Complex: requirements and submission rules
28 requirements and 1 submission rules found in the solicitation documents for RFP_476957. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- An application with drawings, specifi cations and Engineers Report and Letter of Compliance shall be submitted to the Suffolk County Department of Health for approval.
Requirements
| ID | Requirement |
|---|---|
| R1 | BNL and the contractor will obtain the services of an independent soils laboratory to conduct in-place compaction tests throughout construction.A.9 |
| R2 | For the design of facilities and equipment and purchase of equipment NFPA 70-2017 or the most recent version is acceptable for use. Designers and vendors must specify which version is being used. |
| R3 | The following requirements are in the Project Specifications and will be the responsibility of the Contractor: Utilize Low-Emitting Materials. Develop and implement an IAQ During Construction Plan. |
| R4 | The following requirements are in the Project Specifications and will be the responsibility of the Contractor: Meet the Resource Conservation and Recovery Act (RCRA) requirements for recycled content. Meet Section 9002 of the Farm Security and Rural Investment Act (FSRIA) requirements for the use of bio-based materials. Develop and implement a Construction Waste Management Plan and divert at least 50% of the construction waste from landfills. |
| R5 | All cable tray / rack systems are to be directly supported on slabs-on-grade. Hanging cable tray / rack systems from superstructure of pre-fabricated metal enclosures and pre-engineered metal buildings is strictly prohibited. |
| R6 | All vibration-sensitive equipment identified here must be structurally isolatedA.9 |
| R7 | All motorized equipment must include local isolators to mitigate vibration and protect against structural interference.A.9 |
| R8 | For frost protection, exterior footings must be embedded at least 3.5 feet below the finished grade. Interior footings in heated areas should be at least 1.5 feet below the finished floor slab.A.9 |
| R9 | Micropiles shall have a 9.625-inch diameter, 0.500-inch-thick Grade 50 steel casing, and a full-length #9 Grade 75 threaded bar, grouted to a minimum strength of 4,000 psi. The casing shall extend at least 20 feet below the pile cap, with a minimum 15-foot bond length pressure-grouted to 75 psi.A.9 |
| R10 | Backfill placement and compaction should follow best practices, with hand-operated compactors within 10 feet of the walls to prevent excessive lateral soil pressures.A.9 |
| R11 | Strict excavation and installation procedures must be understood and followed by the Contractor to ensure stability is maintained during all modifications to existing corrugated steel structures.A.9 |
| R12 | It should be clearly noted that penetrations and trenches within the existing IR10 tunnel slab is strictly prohibited, as the slab is a crucial piece of the arch plate system’s stability in resisting thrust forces.A.9 |
| R13 | For all buildings all underslab sanitary waste and vent piping 3 inch and larger will be video inspected after installation and before slab pour to verify installation and make possible repairs prior to final slab pour.A.9 |
| R14 | For all buildings all underslab storm drain piping 3 inch and larger will be video inspected after installation and before slab pour to verify installation and make possible repairs prior to final slab pour.A.9 |
| R15 | The Contractor will furnish and install all devices and circuits and mount the control panel(s). Brookhaven staff will make all final connections of the circuits to the control panel.A.9 |
| R16 | Emergency Responder Communication Enhancement System (ERCES): These systems must meet survivability requirements to ensure it will continue to operate during a fire. The system must have redundant primary power sources and stand-by or back-up power to operate at 100% capacity for at least 12 hours. |
| R17 | All luminaires will have field-replaceable drivers and boards. The replacement of an entire fixture due to component failure is not permitted. |
| R18 | Contractor to provide adequate amount of fiber cable feed into the new facility. |
| R19 | Please make note “No” new telecommunications cable will utilize the tunnel; all communications cabling will be routed in the existing manhole infrastructure. |
| R20 | The work area conduits shall not be filled with multiple cables beyond 40% fill. No work area conduit will be installed below grade. The work area conduits shall be sized to support the initial installation of cable, plus a minimum of 35% growth.A.9 |
| R21 | Access control systems are IT Systems that require complete Certification and Accreditation and must obtain Authority to Operate before connecting to the network. Access control systems shall be cyber secured to national cybersecurity standards (NIST 800 or the ISA 62443 series).A.9 |
| R22 | Electric door locks will be fail secure (apply power to unlock/cut power to lock) and shall utilize 24VDC power... Key cylinders to override the electric lock shall be provided in order to facilitate entry into the building in event of power outages exceeding battery capacity. Door hardware power supplies will be included in the security design and furnished and installed by the security contractor adjacent to iSTAR panels.A.9 |
| R23 | Contractor will furnish and install a four-channel media converter to be mounted in an existing data rack in Building 631 in order to tie the cameras into the existing security network.A.9 |
| R24 | The Contractor will designate commissioning team members for each subcontractor responsible for installation, startup and operation of associated equipment and systems. |
| R25 | Startup reports and Prefunctional Checklists executed by Contractor are utilized to achieve this [verify work is installed in accordance with Contract Documents].A.9 |
| R26 | Functional Tests executed by Contractor and witnessed by the Commissioning Authority are utilized to achieve this [verify and document functional performance].A.9 |
| R27 | Detailed operation and maintenance (O&M) data submittals by Contractor are utilized to achieve this [verify O&M manuals are complete].A.9 |
| R28 | Formal training conducted by Contractor is utilized to achieve this [verify Owner's operating personnel are adequately trained].A.9 |
Recent awards in NAICS 541330
The newest federal contract awards in the same industry code from Department of Energy, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-10-28 | LEONARDO TECHNOLOGIES, INC.Department of Energy · IIJA FUNDING TECHNICAL AND ENGINEERING SUPPORT SERVICES FOR THE OFFICE OF HYDROCARBONS AND GEOTHERMAL ENERGY OFFICE ACTIVITIES INCLUDE PROVIDING SOUND PROFESSIONAL, TECHNICAL, AND PROGRAMMATIC APPROAC | $200,000 |
| 2026-10-26 | MSS SERVICES, INC.Department of Energy · INSPECTION SERVICES FOR YUMA SERVICE CENTER (YSC) SECURITY CAMERA AND ELECTRONIC SECURITY SYSTEM (ESS) INSTALLATION PROJECT | $54,403 |
| 2026-10-19 | MSS SERVICES, INC.Department of Energy · ALCOVA-NORTH CODY INSPECTION SERVICES - WESTERN AREA POWER ADMINISTRATION (WAPA) CONSTRUCTION INSPECTION SERVICES BLANKET PURCHASE AGREEMENT (BPA) - UPPER GREAT PLAINS, ROCKY MOUNTAIN, DESERT SOUTHWES | $37,673 |
| 2026-10-01 | HAZEN AND SAWYER, D.P.C.Federal Energy Regulatory Commission · ENVIRONMENTAL CONSULTING SERVICES | $91,600 |
| 2026-09-29 | KBENSKO CONSULTING, LLCFederal Energy Regulatory Commission · ENGINEERING GEOLOGIST SUBJECT MATTER EXPERT CONSULTING | $97,500 |
| 2026-09-28 | CONVERGE FEDERAL SOLUTIONS JV, LLCDepartment of Energy · NETL PITTSBURGH, PA B920 SWITCHGEAR REPLACEMENT ENGINEERING SERVICES & CONSTRUCTION SUPPORT | $120,652 |
Source: USAspending.gov, retrieved 2026-10-30. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.