A-E Services for Electron Injector Complex: requirements and submission rules
46 requirements and 1 submission rules found in the solicitation documents for RFP_476957. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- An application with drawings, specifi cations and Engineers Report and Letter of Compliance shall be submitted to the Suffolk County Department of Health for approval.
Requirements
| ID | Requirement |
|---|---|
| R1 | The Conventional Facilities must be designed and constructed to enable the performance of the most advanced lepton-hadron collider ever built. Furthermore, the Conventional Facilities must be constructed on a schedule that enables installation of the accelerator systems in accordance with the overall project schedule.A.9 |
| R2 | These site facilities must provide access for maintenance and replacement activities, supply the necessary utilities including but not necessarily limited to potable water/fire water, sanitary sewer, stormwater, electrical power, and telephone/data.A.9 |
| R3 | The latest edition of the codes, standards, orders, and guides referred to in this section will be followed.A.9 |
| R4 | It is noted that prior to the implementation of new water mains/services, a full set of engineering plans, specifications and engineering report must be approved by BNL Energy and Utilities as well as Suffolk County Department of Health Services via DOH-348 submittal.A.9 |
| R5 | Since site disturbance is over 5,000 SF, compliance with EISA Section 438 is required and will be included in the stormwater evaluations.A.9 |
| R6 | To meet the requirements of the Manual, each site is required to have an infiltration test performed within the disturbance area.A.9 |
| R7 | The drainage systems for each individual site will capture and infiltrate a minimum of 1.5 inch of stormwater runoff over the tributary area without system overflow.A.9 |
| R8 | Per the New York State Stormwater Design Manual, water quantity must be addressed for three separate criteria. This includes channel protection volume (CPv) based on the 1-yr, 24-hr storm event to protect stream channels from erosion, overbank flood control (Qp) and extreme flood control (Qf) being fully managed on-site. |
| R9 | All facilities will be cited to be outside of the existing floodplain.A.9 |
| R10 | Erosion and sedimentation control systems will be installed and utilized for the duration of the construction phase of the project. |
| R11 | Given the scope of the project, a Stormwater Pollution Prevention Plan (SWPPP) that consists of an erosion and sediment control plan and Post-Construction Stormwater management including the design of related water quality and quantity controls/best management practices (BMPs) will be required. |
| R12 | Silt fencing and stabilized construction entrances will be installed prior to the commencement of construction activities. Disturbed areas within the construction site will be stabilized as soon as practical and subsequently maintained with appropriate methods to minimize erosion of exposed earth.A.9 |
| R13 | BNL and the contractor will obtain the services of an independent soils laboratory to conduct in-place compaction tests throughout construction.A.9 |
| R14 | Topsoil will meet the requirements of NYSDOT Topsoil Section 713- 01. Topsoil will be spread to a compacted depth of 4-inches in all disturbed earth areas. |
| R15 | Pavement design construction standards will conform with the New York State, Department of Transportation, and 'Standard Specifications' (latest edition).A.9 |
| R16 | All new road and surface parking lot pavements will be asphalt, concrete, or porous concrete. Pavement in loading areas will be reinforced heavy duty concrete.A.9 |
| R17 | Aggregate base for pavements will be naturally or artificially graded mixture of crushed gravel or crushed stone. The base will be compacted between 95 and 100%. The subgrade under pavements should be moisture conditioned between optimum and plus four percentage points above optimum moisture content and compacted to a minimum 95% of the maximum dry density in accordance with ASTM D 698. |
| R18 | Line paint will be non-reflective, white paint conforming to NYSDOT TT-P-115E.A.9 |
| R19 | Each pump shall be sized for full flow, with float level controls and control panels with level, run and fault alarming. Force main piping leaving the wet well will enter a valve vault where each pump will have dedicated isolation and check valves prior to combining and discharging to the existing piping systems.A.9 |
| R20 | The NYS BC Section 503 requires access to be available within 150 feet of a building that is not protected by sprinklers. Given the configuration of the building as an elongated rectangle, access shall be available from two of the longer sides of the building.A.9 |
| R21 | The EIC buildings will be designed in accordance with all applicable federal laws, codes, and standards. Particular attention will be paid to compliance with radiological requirements of 10 CFR 835 and 851 and OSHA requirements of 29 CFR 1910 and electrical safety requirements of NFPA 70E-2021. |
| R22 | For the design of facilities and equipment and purchase of equipment NFPA 70-2017 or the most recent version is acceptable for use. Designers and vendors must specify which version is being used. |
| R23 | The building energy cost must be equal to or less than 85 percent of the standard reference design building.A.9 |
| R24 | All Buildings will have Class A interior finish and roof per DoE requirements.A.9 |
| R25 | The following requirements are in the Project Specifications and will be the responsibility of the Contractor: Utilize Low-Emitting Materials; Develop and implement an IAQ During Construction Plan. |
| R26 | The following requirements are in the Project Specifications and will be the responsibility of the Contractor: Meet the Resource Conservation and Recovery Act (RCRA) requirements for recycled content; Meet Section 9002 of the Farm Security and Rural Investment Act (FSRIA) requirements for the use of bio-based materials; Develop and implement a Construction Waste Management Plan and divert at least 50% of the construction waste from landfills. |
| R27 | All cable tray / rack systems are to be directly supported on slabs-on-grade. Hanging cable tray / rack systems from superstructure of pre-fabricated metal enclosures and pre-engineered metal buildings is strictly prohibited. |
| R28 | all vibration-sensitive equipment identified here must be structurally isolatedA.9 |
| R29 | Seismic restraints are required only for architectural components critical to life safety (e.g., egress stairs) or those containing hazardous materials (such as flammable or toxic substances). Non-structural mechanical, electrical, and plumbing (MEP) components are exempt from these requirements. All motorized equipment must include local isolators to mitigate vibration and protect against structural interference. |
| R30 | For frost protection, exterior footings must be embedded at least 3.5 feet below the finished grade. Interior footings in heated areas should be at least 1.5 feet below the finished floor slab.A.9 |
| R31 | Micropiles shall have a 9.625-inch diameter, 0.500-inch-thick Grade 50 steel casing, and a full-length #9 Grade 75 threaded bar, grouted to a minimum strength of 4,000 psi. The casing shall extend at least 20 feet below the pile cap, with a minimum 15-foot bond length pressure-grouted to 75 psi.A.9 |
| R32 | Permanent retaining walls shall be designed without reliance on temporary shoring for lateral support. Walls exceeding 6 feet in height must resist seismic loads, and tiered retaining walls spaced at a horizontal distance greater than the height of the lower wall may be considered structurally independent. Lateral stresses from temporary or long-term surcharges must be included in the design.A.9 |
| R33 | Strict excavation and installation procedures must be understood and followed by the Contractor to ensure stability is maintained during all modifications to existing corrugated steel structures.A.9 |
| R34 | It should be clearly noted that penetrations and trenches within the existing IR10 tunnel slab is strictly prohibited, as the slab is a crucial piece of the arch plate system's stability in resisting thrust forces.A.9 |
| R35 | All motor operated equipment, including mounted upon slab-on-grade, is provided with vibration isolation and flexible duct/pipe connections, based upon criteria described within Section 5 Structural, to prevent transmission of vibration or noise to the building and utilities. |
| R36 | For all buildings all underslab sanitary waste and vent piping 3 inch and larger will be video inspected after installation and before slab pour to verify installation and make possible repairs prior to final slab pour.A.9 |
| R37 | For all buildings all underslab storm drain piping 3 inch and larger will be video inspected after installation and before slab pour to verify installation and make possible repairs prior to final slab pour.A.9 |
| R38 | Automatic sprinkler protection shall be provided in accordance with NFPA 13 per BNL request and DOE-STD-1066 - D.2. The Substation – Building 638A will not be equipped with sprinklers.A.9 |
| R39 | The Contractor will furnish and install all devices and circuits and mount the control panel(s). Brookhaven staff will make all final connections of the circuits to the control panel.A.9 |
| R40 | Emergency Responder Communication Enhancement System (ERCES) two-way radio communication enhancement systems will be provided in new buildings (as indicated on contract drawings)... These systems must meet survivability requirements to ensure it will continue to operate during a fire. The system must have redundant primary power sources and stand-by or back-up power to operate at 100% capacity for at least 12 hours. |
| R41 | All luminaires will have field-replaceable drivers and boards. The replacement of an entire fixture due to component failure is not permitted. |
| R42 | Contractor to provide adequate amount of fiber cable feed into the new facility. BNL utilizes Corning CCH products for terminations which when using LC connectors can provide the required connections per rack space. Please make note 'No' new telecommunications cable will utilize the tunnel; all communications cabling will be routed in the existing manhole infrastructure. |
| R43 | Access control systems are IT Systems that require complete Certification and Accreditation and must obtain Authority to Operate before connecting to the network. Access control systems shall be cyber secured to national cybersecurity standards (NIST 800 or the ISA 62443 series).A.9 |
| R44 | Contractor will furnish and install a four-channel media converter to be mounted in an existing data rack in Building 631 in order to tie the cameras into the existing security network.A.9 |
| R45 | The Contractor will designate commissioning team members for each subcontractor responsible for installation, startup and operation of associated equipment and systems. |
| R46 | Commissioning, including Functional Tests, O&M documentation review, and training, is to occur after startup and initial checkout and be completed before Substantial Completion.A.9 |
Recent awards in NAICS 541330
The newest federal contract awards in the same industry code from Department of Energy, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-10-19 | MSS SERVICES, INC.Department of Energy · ALCOVA-NORTH CODY INSPECTION SERVICES - WESTERN AREA POWER ADMINISTRATION (WAPA) CONSTRUCTION INSPECTION SERVICES BLANKET PURCHASE AGREEMENT (BPA) - UPPER GREAT PLAINS, ROCKY MOUNTAIN, DESERT SOUTHWES | $37,673 |
| 2026-10-01 | HAZEN AND SAWYER, D.P.C.Federal Energy Regulatory Commission · ENVIRONMENTAL CONSULTING SERVICES | $91,600 |
| 2026-09-29 | KBENSKO CONSULTING, LLCFederal Energy Regulatory Commission · ENGINEERING GEOLOGIST SUBJECT MATTER EXPERT CONSULTING | $97,500 |
| 2026-09-28 | CONVERGE FEDERAL SOLUTIONS JV, LLCDepartment of Energy · NETL PITTSBURGH, PA B920 SWITCHGEAR REPLACEMENT ENGINEERING SERVICES & CONSTRUCTION SUPPORT | $120,652 |
| 2026-09-24 | MSS SERVICES, INC.Department of Energy · EO 14398, BPA CALL FOR CONSTRUCTION INSPECTION SERVICES FOR KE AND RMF WAVEGUIDE CONSTRUCTION | $35,028 |
| 2026-09-16 | BURNS & MCDONNELL ENGINEERING COMPANY, INC.Department of Energy · A-E TITLE I, II, AND III ENGINEERING SERVICES - 2026 RMR AND UGP LIDAR PROJECT | $1.51 million |
Source: USAspending.gov, retrieved 2026-10-24. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.