KAUTZ ROAD SUBSTATION CONSTRUCION, UIP SUBPROJECT 2- KRS: requirements and submission rules

16 requirements and 15 submission rules found in the solicitation documents for RFP-383167-CD. Use them as the start of your compliance matrix.

Solicitation number
RFP-383167-CD
Agency
ENERGY, DEPARTMENT OF / ENERGY, DEPARTMENT OF / FERMILAB - DOE CONTRACTOR
NAICS
237130
Set-aside
No Set aside used
Responses due
18 December 2026 (20 days)
Official notice
View on SAM.gov

Submission rules that can disqualify a bid

  • The submittal shall contain the same information pertaining to the original specified product for purposes of comparison.
  • Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
  • BY (Signature in ink)(Print or Type Name) TITLE (Print or Type) REQUEST FOR PROPOSAL NO: 383167-CD Kautz Road Substation Construction, UIP Subproject 2- KRS December 18, 2026, 4:00 p.m./Central Time All proposal to be sent electronically to cdaley@fnal.gov TITLE OF PROJECT: DUE DATE AND TIME: SUBMITTAL LOCATION: THE OFFEROR SHALL SUBMIT THIS COMPLETED FORM WITH THEIR WRITTEN PROPOSAL
  • Submit 10 lb samples of each material to be used.
  • When an application shows completion of an item, submit final waivers no later than the next application submitted after showing completion.
  • The General Contractor shall submit to FermiForward one (1) printed copy and one (1) electronic copy in Adobe portable document format (PDF).
  • Submit Construction schedule no later than 45 days after the Notice of Award.
  • These drawings shall be submitted not later than the approved schedule for shop drawing transmittal, shall contain all required detailed information, and shall be submitted in logical order to facilitate proper review.
  • Submit PDF copies within seven (7) days of end of each training module.
  • Shop drawings and schedules of all trades shall be submitted by the General Contractor, who shall indicate by signed stamp on the drawings, that he has checked the shop drawings and that the work shown is in accordance with the Subcontract requirements and that it has been checked for dimension and relationship with the work of all trades.
  • Quality Control Inspector Qualifications: Along with Quality Control Plan, Contractor shall submit written qualifications for all inspectors to be assigned Quality Control functions for structural steel work, including general inspection, bolting inspection, welding inspection, and non-destructive testing.
  • Provide adequate time margins between device characteristics such that selective operation is achieved.
  • Submit certification signed by the producer certifying that recycled crushed concrete complies with IEPA requirements as “clean” containing no contaminates if any used.
  • Within ten (10) business days after subcontract award, the General contractor shall submit the following to FermiForward for acceptance.
  • These items must be submitted and accepted by FermiForward prior issuance of NTP.

Requirements

IDRequirement
R1Please enter your total firm fixed price in words and numbers: (Dollars)($ )Firm Fixed Price
R2This Offer may be accepted for a period of One Hundred Twenty (120) calendar days after the opening date unless the offeror specifies a longer acceptance period than FFDG’s minimum requirement.
R3The Subcontractor Annual Representations & Certifications (SARC) is made a part of this subcontract.
R4ENCLOSED IS BID GUARANTEE, CONSISTING OF: IN THE AMOUNT OF
R5All offering entities are directed to enter pricing for the lump sum, fixed price proposed for the entire specified project on the “Total Proposal” Price line above. (Pricing breakdown will be used for evaluation purposes)
R6Offerors are to indicate on each Alternate whether their pricing would be an ADD or a DEDUCT to/from the Base Bid Amount above:
R7Submittals with General Contractor’s proposal: 1. Construction Environmental Safety and Health Certification, which includes acknowledgement regarding Worker Safety 10 CFR 851; (See Article 1.8); 2. Experience Modification Rating (EMR) Rates and Occupational Safety Health Administration (OSHA) 300 log for last three years. Reference the Fermilab Subcontractor Safety Information Questionnaire; 3. General Contractor’s ES&H Program (if required by Article 1.9); and 4. If required by Section 01 00 10 , Resume’ of the General Contractor’s Safety Representative.
R8Corporate Quality Assurance Plan: The General Contractor shall furnish with the bid or proposal a copy of their corporate Quality Assurance Plan. Failure to submit such a document could constitute a non-responsive bid or proposal. See Appendix A for Corporate Quality Assurance Plan guidance.
R9Only firms regularly engaged in the construction and installation of medium voltage cable installations and terminations and who have their systems in satisfactory use in similar service for at least ten (10) years shall be considered acceptable Subcontractors.
R10The following documentation shall be provided by the manufacturer as a part of the proposal: 1. Preliminary outline drawings. 2. A complete list of exceptions to the specification listed by specification paragraph number or a written statement indicating complete compliance with the specification. 3. Description of the manufacturer’s warranty.
R11The following documentation shall be provided by the manufacturer as a part of the proposal: 1. Preliminary outline drawings. 2. Fully completed Harmonic Filter Resistor Proposal Data Sheets (Section 3.8). 3. A complete list of exceptions to the specification listed by specification paragraph number or a written statement indicating complete compliance with the specification. Exceptions to this specification may result in the proposal being disqualified. 4. Description of the manufacturer’s warranty.
R12The following documentation shall be provided by the manufacturer as a part of the proposal: 1. Preliminary outline drawings. 2. Preliminary one-line diagrams and fuse loss protection schematics. 3. Method by which simulations/calculations will be accomplished. 4. A complete list of exceptions to the specification listed by specification paragraph number or a written statement indicating complete compliance with the specification. 5. Fully completed Capacitor Bank Proposal Data Sheets (Section 3.10). 6. Description of the manufacturer’s warranty.
R13Vendors must complete this form and attach it to their quotation. [APPENDIX B – SCHEDULE OF TECHNICAL REQUIREMENTS 345kV MOTOR OPERATED HORIZONTAL BREAK DISCONNECT SWITCH]
R14Fabricator Qualifications: A qualified fabricator that participates in the AISC Quality Certification Program and is designated an AISC-Certified Plant, Category STD. The fabricator shall have a minimum of 5 years experience in similar types of fabrication.
R15Installer Qualifications: A qualified installer who participates in the AISC Quality Certification Program and is designated an AISC-Certified Erector, Category ACSE. The erector shall have a minimum of 5 years experience in similar types of erection.
R16Base bids on indicated number of drilled piers and, for each pier, the design length from top elevation to bottom of shaft, extended through the bell, if applicable, and the diameter of shaft and bell.

Recent awards in NAICS 237130

The newest federal contract awards in the same industry code from Department of Energy, since 1 October 2024. Use them to see who wins this kind of work and at what value.

StartAwardee and buyerAward value
2026-09-24FOUR TRIBES CIVIL CONSTRUCTION LLCDepartment of Energy · EO 14398, KESWICK SUBSTATION AND REDDING MAINTENANCE FACILITY CABLE AND WAVEGUIDE BRIDGE PROJECT$373,652
2026-09-23SITE WORK SOLUTIONSDepartment of Energy · WESTERN AREA POWER ADMINISTRATION (WAPA) REQUIREMENT TO REPAIR TWO (2) AUTOMATED SLIDING ENTRY GATES AT THE SIERRA NEVADA REGION (SNR) HEADQUARTERS FACILITY LOCATED IN FOLSOM, CA. WORK SHALL BE PERFOR$94,600
2026-09-23COMPLETE CONCRETE, INC.Department of Energy · CHEYENNE AREA COMM BUILDING ELECTRICAL REPAIRS$563,692
2026-09-16COMPLETE CONCRETE, INC.Department of Energy · MIDLAND REPEATER - EROSION AND FENCE REPAIR PROJECT, SOUTH DAKOTA$78,748
2026-09-16ADDISON CONSTRUCTION CODepartment of Energy · THE STEGALL SUBSTATION STAGE 07 PHASE 01 PROJECT TO REPLACE END OF LIFE EQUIPMENT AND INSTALLS A NEW CONTROL BUILDING.$441,986
2026-09-09COMPLETE CONCRETE, INC.Department of Energy · ALCOVA-NORTH CODY BREAKER FOUNDATIONS REPLACEMENT$148,709

Source: USAspending.gov, retrieved 2026-11-03. Award value is the obligated amount reported by the agency.

Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.

Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.

Bidding? Get a reminder 5 days before it is due

One email, with what to check before you submit. Nothing else.

Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.

Get new solicitations that match your business, free

Enter NAICS codes, keywords or both. No email when nothing matches. Unsubscribe in one click.