P1555U Wallace Creek Service Road: requirements and submission rules
19 requirements and 5 submission rules found in the solicitation documents for N4008527R9001. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Failure to submit a required bid bond by the deadline will result in your proposal being removed from consideration.
- Proposal Due Date: 12/1/2026 2:00 PM EST E-Mail Address for Proposals: anna.m.lundquist.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.mil
- P1555U 10/29/2026 Requests for Information (RFIs): RFIs must be submitted by the prime contractor to anna.m.lundquist.civ@us.navy.mil.
- The cut off for RFIs is 11/16/2026 by 3:00 PM EST in order to process all inquiries by the proposal due date.
- The specifications and drawings are posted as attachments on https://sam.gov/. “OFFERORS ARE ADVISED THAT FUNDING MAY NOT BECOME AVAILABLE.
Requirements
| ID | Requirement |
|---|---|
| R1 | ONLY THE FOLLOWING LIST OF CONTRACTORS MAY SUBMIT A PROPOSAL FOR THIS PROJECT: N40085-23-D-0013 Quadrant Construction, Inc. 166 Center Street Jacksonville, NC 28546 (910) 937-0003 POC: Chris Whaley chriswhaley@qcenc.com N40085-23-D-0014 Civil Works Contracting, LLC 190 Raleigh Street Wilmington, NC 28412 (910) 859-8574 POC: Pat Paluso ppaluso@civilworkscontracting.com N40085-23-D-0015 Riza Construction, Inc. 228 Chaparral Trail Jacksonville, NC 28546 (910) 934-0385 POC: Evette Britton evette.britton@rizaconstruction.com |
| R2 | Contract Completion Date: 730 days after award |
| R3 | One person may fill the roles of Superintendent, Quality Control Manager, and Safety and Health Officer, if duly qualified for all three positions as defined in the project specification. |
| R4 | Proposal Acceptance Period: 60 days from receipt of offers |
| R5 | Bid bonds are required based on the dollar values listed below. If required, the bid bond should be 20% of the proposal amount. |
| R6 | Utilize the bond formats at FAR 53.300. |
| R7 | Proposals valued at $35K and greater will require a payment bond only. |
| R8 | Proposals valued at $150K and greater will require a bid bond, a payment bond, and a performance bond. |
| R9 | If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. |
| R10 | If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. |
| R11 | The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer. |
| R12 | If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies. |
| R13 | Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number (ELIN) given hereinafter: |
| R14 | For CLINs 0001A through 0001H, enter unit prices and extended totals in spaces provided. |
| R15 | Failure to enter a price for any CLIN will result in a proposal being rejected. |
| R16 | A firm fixed price is required for CLINs 0001 through 0008. |
| R17 | If CLINs 0002 through 0008 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all items. |
| R18 | Monitoring Well Abandonment Permit: Abandonment must be completed by a licensed NC drilling operator. |
| R19 | Explosive Safety Submission: RESPONSIBLE AGENT: Construction Contractor with qualified UXO competent personnel |
Recent awards in NAICS 237310
The newest federal contract awards in the same industry code from Department of Defense, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-08-12 | STEELCO CHAIN LINK FENCE ERECTING CO., INC.Department of the Army · ROAD GATE PAINTING, ROAD GATE INSTALLATION, REMOVAL AND REPLACEMENT OF GUARDRAILS, BUFFUMVILLE LAKE, CHARLTON, MA | $120,057 |
| 2026-08-10 | DOUBLE A SERVICES INCDepartment of the Army · PAVING REPAIR FREEDOM RAMP STORM DRAINS | $816,041 |
| 2026-08-09 | CLASSIC SITE SOLUTIONS INCDepartment of the Army · PROJECT OFFICE PARKING AND ACCESS ROAD PAVING AND CULVERTS, WEST HILL DAM, UXBRIDGE, MA | $747,419 |
| 2026-08-03 | WILLARD ASPHALT PAVING, INC.Department of the Army · THE PURPOSE OF THIS TASK ORDER IS TO PAINT LINES ON THE RANGE 14 PAD. SEE SOW FOR DETAILS. | $1,396 |
| 2026-08-03 | DURHAM FENCE COMPANY, INC.Department of the Army · GUARDRAIL REPLACEMENT, HODGES VILLAGE DAM, OXFORD, MA | $65,340 |
| 2026-08-01 | WIREGRASS CONSTRUCTION COMPANY, INC.Department of the Army · THIS REQUIREMENT IS FOR A PERFORMANCE-BASED ACQUISITION FOR ASPHALT PAVING, CONSTRUCTION OF HORIZONTAL STRUCTURES, EARTH WORKS, AND STORM DRAINAGE STRUCTURES THAT ARE ON OROWNED BY FORT NOVOSEL. | $421,948 |
Source: USAspending.gov, retrieved 2026-10-30. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.