RM16-1405 BUILDING 592 RENOVATIONS: requirements and submission rules
122 requirements and 15 submission rules found in the solicitation documents for N4008527R0017. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- 1.4.1.1 Shop Drawing 2 copies of the shop drawings, no later than 28 days prior to the start of SECTION 21 13 16 Page 5
- Submit a minimum 1 foot wide by 6 inch deep, full size sample for each type of counter top shown on the project drawings; include the edge profile and backsplash as detailed on the drawings and at least SECTION 06 61 16 Page 6
- 1.4.2.2 Record of Document Submittal to Testing Agency Submit not later than 30 calendar days prior to the work plan submittal due date, a record of transmittal of the following documents to the approved independent testing agency.
- Sequencing for Submittals: The sequencing specified for submittals is the deadline by which the submittal must be initially submitted to the Government.
- Where analysis to determine asbestos content in bulk materials or transmission electron microscopy is required, submit evidence that the laboratory is accredited by the National Institute of Science and Technology (NIST) under National Voluntary SECTION 02 82 00 Page 10
- Submit sampling results to the Contracting Officer and the affected Contractor employees where required by law within three working days, signed by the testing laboratory employee performing air sampling, the employee that analyzed the sample, and the PQP and GC.
- Submit results of air samples, signed by the CP, within 72-hours after the air samples are taken. d.
- A test record of samples of aggregate taken at the same locations must show the results of SECTION 03 30 00 Page 39
- Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-02 Shop Drawings Detail Fabrication Drawings ; G, AE Installation ; G, SD-03 Product Data Solid Polymer ; G SD-04 Samples Material ; G Counter Tops ; G, AE SD-06 Test Reports Test Report Results SD-07 Certificates SECTION 06 61 16 Page 2
- Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES SD-01 Preconstruction Submittals Sample Warranty ; G List of Product Installations ; G SD-02 Shop Drawings Installation Drawings ; G Fabrication Drawings ; G SD-03 Product Data Manufacturer's Catalog Data ; G Finish ; G SECTION 08 41 13 Page 2
- Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-02 Shop Drawings Corner Guards ; G, A/E SD-03 Product Data Corner Guards ; G SD-04 Samples Corner Guards ; G SD-10 Operation and Maintenance Data SECTION 10 26 00 Page 1
- For the purposes of this specification, if a Specialty CEQ Package is required, the same requirements identified for SECTION 12 00 01.00 20 Page 1
- Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-02 Shop Drawings Installation Drawings ; G Detail Drawings ; G, AE SD-03 Product Data Entrance Floor Mats and Frames ; G Adhesives and Concrete Primers ; G SD-04 Samples Entrance Floor Mats and Frames ; G, AE SD-08 Manufacturer's Instructions Manufacturer's Instructions SECTION 12 48 13 Page 1
- 1.4.2 Certification 1.4.2.1 Test Agency Qualifications Submit, no later than 15 calendar days after contract award, information certifying that the test agency is not affiliated with any other company participating in work on this contract.
- Items of the same type and purpose must be identical, SECTION 23 09 00 Page 19
Requirements
| ID | Requirement |
|---|---|
| R1 | At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started. |
| R2 | Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 15 days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work. |
| R3 | Notify the Contracting Officer at least 15 days prior to starting excavation work. |
| R4 | Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. |
| R5 | Permission to interrupt any Activity roads, roads, drive aisles, pedestrian accesses or walkways, entrance gates, or utility service, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption. |
| R6 | All concrete repairs (demolition and new work) on the mezzanine floor in Building 20 must be performed during second shift, which consists of an 8-1/2 hour period between 3:30 pm and 12:00 am, Monday through Friday, excluding Government Holidays. All concrete repairs (demolition and new work) on the mezzanine floor in Building 20 must be phased to progress from east to west. |
| R7 | Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists. |
| R8 | General construction and finish work of the Naval Foundry Propeller Center (NFPC) must be performed by U.S. firms using U.S. citizens. |
| R9 | Submit a SECNAV FORM 5512/1 for all employees or representatives who will be working inside NFPC facilities or secure perimeters to obtain a Contractor's ID badge at least two weeks prior to start of work. All personnel must be US citizens. |
| R10 | No cameras, including cell phone cameras, are allowed inside the NFPC fenced perimeter. Photography by the Contractor is prohibited. Photography from the outside of the NFPC fenced perimeter is also prohibited. |
| R11 | All laptops must be approved for entry by NNSY Code 109, this process takes 7 days for approval which is valid for 1 year. |
| R12 | At no time shall work interfere with normal traffic flow without having an approved traffic control plan. Fire lanes shall be kept open at all times. |
| R13 | The use of Citizen's Band (CB) radio is prohibited. If cell phones, or VHF or walkie-talkie type radio are required for operation, during construction, approval will be on a case by case basis. The Contractor is required to submit the manufacturer and model number, frequency desired, transmitter power and type of antenna to be used, to the Contracting Officer for prior approval. |
| R14 | The us of cellular telephones while operating motor vehicles on Government property is prohibited on NFPC. |
| R15 | The contractor shall submit to the Contracting Office a full report of damage to government property or equipment by contractor employees. Damage reports shall be submitted within 24 hours of the occurrence. |
| R16 | There shall be no public release of information or photographs concerning any aspect of the materials or services relating to this contract or other documents resulting therefrom without the prior written approval of the Contracting Officer. The Contractor shall insert the substance of this paragraph in each subcontract and purchase order. |
| R17 | The Contractor shall give written notice of the proposed outages at least four weeks prior to the desired outage. |
| R18 | Provide positive verification that the existing line conveys to sanitary sewer; verify line is not incorrectly connected to a storm drain. Obtain City of Philadelphia's Sanitary Sewer Connection Permit at least 2 weeks prior to connection. |
| R19 | The Contractor shall not use any heat or spark producing device or perform drilling, grinding, burning, soldering, brazing, welding or otherwise use an open flame without obtaining a burn permit from the NAVFAC Fire Marshal. The contractor will have to schedule and attend a 1 hr fire watch class prior to the issuance of the burn permit. |
| R20 | Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. |
| R21 | Within 30 calendar days of notice of award, prepare and deliver to the Contracting Officer a Earned Value Report (construction Contract) as directed by the Contracting Officer. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. |
| R22 | The complete design and construction Schedule of Prices or Earned Value Report must be submitted and accepted prior to starting construction work. |
| R23 | The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. |
| R24 | Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. |
| R25 | A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release. |
| R26 | Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law. |
| R27 | Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. |
| R28 | Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. |
| R29 | The meeting conference must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. |
| R30 | Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. |
| R31 | Mobilize to the jobsite within 60 calendar days after contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite. |
| R32 | Utilize the Naval Facilities Engineering Systems Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. |
| R33 | Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic submittals, RFIs, daily reports, and other files and will require access to the eCMS. |
| R34 | Before preparation of the Project Baseline Schedule, and prior to the start of work, meet with the Contracting Officer to discuss the proposed schedule and the requirements of this section. |
| R35 | Submit the Baseline NAS within 30 calendar days after contract award. Data date must be set to contract award date and no progress recorded for any activity. |
| R36 | Submit the first look ahead schedule 30 days after contract award and continue to submit weekly until contract completion. |
| R37 | Regardless of whether an invoice is being submitted monthly, or no progress in the schedule occurred, an updated schedule (or with new data date) must be submitted monthly to the Government. The Monthly NAS update must be submitted within first 10 days of the month. |
| R38 | As a condition precedent to the release of retention and making final payment, submit an 'As-Built Schedule,' as the last schedule update showing all activities at 100 percent completion. |
| R39 | Prepare and maintain project schedules using Primavera P6 software in a version compatible with Government's current version. |
| R40 | Within 30 calendar days of contract award, submit to the Contracting Officer for approval an individual who will serve as the Designated Project Scheduler. |
| R41 | The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules, of similar size and complexity to this contract, using Primavera P6. |
| R42 | The Project Network Analysis Schedule (NAS) must be cost-loaded and will provide the basis for progress payments. |
| R43 | Submit a Time Impact Analysis with each cost and time proposal for a proposed change. |
| R44 | Government approved Division 01 preconstruction submittals that are required prior to or commencing with the start of work must be submitted within 30 calendar days of contract award unless specified elsewhere in the specifications. |
| R45 | Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site. |
| R46 | The Contractor's Quality Control Manager must prepare, review and stamp submittals, including those provided by a subcontractor, before submittal to the Government. |
| R47 | Provide information-only submittals to the Contracting Officer a minimum of 14 calendar days prior to the Preparatory Meeting for the associated Definable Feature of Work (DFOW). |
| R48 | Check the column 'variation' of ENG Form 4025 for submittals that include variations proposed by the Contractor. Set forth in writing the reason for any variations and note such variations on the submittal. |
| R49 | Provide a Monthly Exposure Report by the fifth of each month. This report is a compilation of employee-hours worked each month for all site workers, both Prime and subcontractor. |
| R50 | Complete the checklist monthly and submit with each request for payment voucher. This submission is required monthly even when a payment voucher is not requested. An acceptable score of 90 or greater is required. |
| R51 | Subcontractors on this Contract must have an effective EMR less than or equal to 1.10, as computed by the National Council on Compensation Insurance (NCCI) or if not available, as computed by the state agency's rating bureau in the state where the subcontractor is registered, when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. |
| R52 | Subcontractors on this Contract must have a DART rate, calculated from the most recent, complete calendar year, less than or equal to 3.4 when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier. |
| R53 | Provide a minimum of one Level Two SSHO that meets the requirements of EM 385-1-1 for this project. |
| R54 | The Level Two SSHO must not serve as the Quality Control Manager. The Level Two SSHO must not serve as the Superintendent. |
| R55 | The SSHO must have completed a 40-hour contract safety awareness course based on the content and principles of EM 385-1-1, and instructed in accordance with the guidelines of ANSI/ASSP Z490.1, by a trainer meeting the qualifications of paragraph QUALIFIED TRAINER REQUIREMENTS. If the SSHO does not have a current certification, certification must be obtained within 60 days, maximum, of Contract award. |
| R56 | Submit the APP to the Contracting Officer within 30 calendar days of Contract award and not less than 10 calendar days prior to the date of the preconstruction conference for acceptance. Work cannot proceed without an accepted APP. |
| R57 | Submit the AHA for review at least 5 working days prior to the start of each activity task, or DFOW. |
| R58 | Develop a Standard Lift Plan (SLP) in accordance with EM 385-1-1 and using Standard Pre-Lift Crane Plan/Checklist for each lift planned. Submit SLP to the Contracting Officer for approval within 15 calendar days in advance of planned lift. |
| R59 | It is also mandatory to have a designated FIRE WATCH for any 'Hot Work' done at this activity. The Fire Watch must be trained in accordance with NFPA 51B and remain on-site for a minimum of 1 hour after completion of the task or as specified on the hot work permit. |
| R60 | Submit an IAQ Management Plan within 15 calendar days after Contract award and not less than 10 calendar days before the preconstruction conference. |
| R61 | The Quality Control Manager must maintain a physical presence at the work site at all times and is the primary individual responsible for all quality control. |
| R62 | Submit no later than 30 days after Contract Award, the CQC Plan proposed to implement the requirements FAR 52.246-12 Inspection of Construction. Construction will be permitted to begin only after acceptance of the CQC Plan and other Contract requirements. |
| R63 | The QC Manager must be an individual with a minimum of 10 years combined experience in the following positions: Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction Contracts which included the major trades that are part of this Contract. The individual must have at least 4 years experience as a QC Manager. |
| R64 | The QC Manager must possess at least a Bachelor's degree in engineering, architecture, or construction management, with a current professional engineer registration and a minimum of 10 years construction experience as a Project Superintendent, QC Manager, Project Manager, Project Engineer or Construction Manager on similar size and type construction Contracts which included the major trades that are part of this Contract. |
| R65 | The Special Inspector (SI) must be an independent third party hired directly by the Prime Contractor. The SI must not be a company employee of the Contractor or any subcontractor performing the work to be inspected. |
| R66 | Notify the Contracting Officer at least 2 business days in advance of each preparatory phase meeting. |
| R67 | Notify the Contracting Officer at least 2 business days in advance of each initial phase. |
| R68 | Notify the Contracting Officer at least 14 calendar days prior to the date a final acceptance inspection can be held. |
| R69 | Furnish the original and one copy of these records in report form to the Government by 10:00 AM the next working day after the date covered by the report. |
| R70 | Submit qualifications for each special inspector according to the following certification requirements. The Government will consider alternate equivalent certification upon request. Without written acceptance deviations to the following qualifications are not approved. |
| R71 | Prior to the start of work, submit for Government approval a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. |
| R72 | Prior to testing, submit to the Contracting Officer certification issued by the State or local regulatory agency attesting that the backflow tester has successfully completed a certification course sponsored by the regulatory agency. Tester must not be affiliated with a company participating in other phases of this Contract. |
| R73 | All computers used on this project must be scanned using the installed software at least once per day. |
| R74 | The passwords and passphrases for all computers must be changed from their default values. Passwords must be a minimum of eight characters with a minimum of one uppercase letter, one lowercase letter, one number and one special character. |
| R75 | Provide a single submittal containing completed Contractor Computer Cybersecurity Compliance Statements for each company using contractor owned computers. |
| R76 | Provide standalone Wi-Fi network for authorized Government personnel. Network access must be available throughout the jobsite and for the entire Contract period. |
| R77 | The Environmental Manager and other staff, must complete applicable ECATTS training modules (installation specific or general) prior to starting respective portions of on-site work under this Contract. |
| R78 | Submit copies of regulatory notifications to the Contracting Officer at least at least 20 working days prior days prior to commencement of work activities. |
| R79 | Appoint in writing an Environmental Manager for the project site. The Environmental Manager is directly responsible for coordinating contractor compliance with federal, state, local, and installation requirements. |
| R80 | Submit the EPP within 30 days after Contractor award and not less than 10 days before the preconstruction meeting. |
| R81 | Monthly, submit a solid waste disposal report to the Contracting Officer. |
| R82 | Submit a project-specific Stormwater Pollution Prevention Plan (SWPPP) to the Contracting Officer for approval, within 30 days of Contract Award and prior to the commencement of work. |
| R83 | Divert a minimum of 60 percent by weight of the project construction waste and demolition debris/waste from the landfill or incinerator. |
| R84 | Submit Construction Waste Management Plan within 15 calendar days after contract award. |
| R85 | Provide Final Construction Waste Diversion Report 60 days prior to the Beneficial Occupancy Date (BOD). |
| R86 | At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. |
| R87 | Submit As-Built Drawings 30 days prior to Beneficial Occupancy Date (BOD). |
| R88 | Prepare and provide Record Drawings and Source Documents in accordance with FC 1-300-09N. Provide four copies of Record Drawings and Documents on separate CDs or DVDs 30 days after BOD. |
| R89 | Submit final approved project shop drawings 30 days after transfer of the completed facility. |
| R90 | Near the completion of Project, but a minimum of 60 days prior to final acceptance of the work, complete, update draft DD FORM 1354, and submit an accounting of all installed property with Interim DD FORM 1354. |
| R91 | Submit a written training plan to the Contracting Officer for approval at least 60 calendar days prior to the scheduled training. |
| R92 | Submit the Progress submittal when construction is approximately 50 percent complete, to the Contracting Officer for approval. Provide Operation and Maintenance Manual Files (Bookmarked PDF). |
| R93 | Submit the 100 percent submittal of the Operation and Maintenance Prefinal Submittal to the Contracting Officer for approval within 90 calendar days of the Beneficial Occupancy Date (BOD). |
| R94 | Field verify that at least 5 Subsystems under each of the Mastersystems are accurate, for a total of 25 Subsystems. |
| R95 | Submit the GIS Data Release Form prior to the start of data collection efforts and again 4 weeks prior to data delivery to ensure that GIS data has been created and will be delivered utilizing the most up to date SDSFIE schema. |
| R96 | Prior to any spatial and non-spatial development, provide the Government with a technical approach document for review and approval. |
| R97 | To ensure specifications compliance and quality, provide a preliminary GIS deliverable for review when 25 percent of the data has been collected and updated. |
| R98 | Prepare a Demolition Plan and submit proposed demolition, and removal procedures for approval before work is started. |
| R99 | Notify the Contracting Officer in writing 10 working days prior to the commencement of work in accordance with 40 CFR 61, Subpart M. |
| R100 | Before exposure to airborne asbestos fibers, provide workers with a comprehensive medical examination as required by 29 CFR 1926.1101 or other pertinent State or local directives. This requirement must have been satisfied within the 12 months prior to the start of work on this contract. |
| R101 | Submit a copy of the asbestos contractor's license issued by the State of Pennsylvania and City of Philadelphia. |
| R102 | Submit a detailed plan of the safety precautions such as lockout, tagout, tryout, fall protection, and confined space entry procedures and equipment and work procedures to be used in the removal and demolition of materials containing asbestos. The plan, not to be combined with other hazard abatement plans, must be prepared, signed, and sealed by the PQP. |
| R103 | Provide a local exhaust system that creates a negative pressure of at least 0.02 inches of water relative to the pressure external to the enclosure and operate it continuously, 24-hours a day, until the temporary enclosure of the asbestos control area is removed. |
| R104 | The CP must be a Certified Industrial Hygienist (CIH) certified by the American Board of Industrial Hygiene or a Certified Safety Professional (CSP) certified by the Board of Certified Safety Professionals or a licensed lead-based paint abatement Supervisor/Project Designer in the Commonwealth of Pennsylvania and City of Philadelphia. |
| R105 | The plan must be developed and signed by a certified Lead Project Designer in the State of Commonwealth of Pennsylvania and City of Philadelphia. |
| R106 | Submit a job-specific plan within 20 calendar days after award of contract of the work procedures to be used in the removal, packaging, and storage of PCB-containing lighting ballasts and associated mercury-containing lamps. |
| R107 | Submit a PCB and lamp Disposal Plan within 45 calendar days after award of contract, complying with the applicable requirements of federal, state, and local PCB and Universal waste regulations |
| R108 | Sixty days minimum prior to concrete placement, submit a mix design for each strength and type of concrete. |
| R109 | Submit shop drawings for formwork, shoring, reshoring, and backshoring, signed and sealed by a licensed design engineer. |
| R110 | Each worker engaged in the installation of post-installed anchors must have satisfactorily completed an applicable certification program or equivalent instruction program through the manufacturer or manufacturer's representative for all anchoring products they will install. |
| R111 | Fabricate work in an AISC Certified Fabrication Plant, Category BU. Erect work by an AISC Certified Erector, Category CSE. |
| R112 | Submit design calculations for steel connections signed and sealed by a registered professional engineer. |
| R113 | Offerors must propose a HAR for the FF&E not to exceed 5 percent. Do not include costs associated with INTERIOR DESIGN SERVICES in the HAR. |
| R114 | All FF&E must be installed by the manufacturer's dealer of record and not by the Contractor. |
| R115 | Provide a FF&E Schedule and Schedule Updates Submittal for all FF&E and Specialty CEQ services and deliverables to the NAVFAC Construction Manager, Interior Designer and Contracting Officer 7 business days after the PRECON. |
| R116 | Provide the Final FF&E Package Submittal 9 months prior to BOD, following the receipt of review comments on the Pre-Final FF&E Package Submittal and as determined by the approved FF&E schedule developed and incorporated into the Contractor's Schedule. |
| R117 | The QFPE must affix their professional engineering stamp with signature to the shop drawings, calculations, and material data sheets, indicating approval prior to submitting the shop drawings to the DFPE. |
| R118 | The sprinkler system designer must be certified as a Level III Technician by National Institute for Certification in Engineering Technologies (NICET) in the Water-Based Systems Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7. |
| R119 | The Contractor shall engage a Professional Engineer licensed in the Commonwealth of Pennsylvania to provide a complete delegated engineering design for the dust collection, ductwork, and explosion protection systems. |
| R120 | The System Analyzer must perform the power system studies. The System Analyzer must be a registered professional electrical engineer with a minimum of 3 years of experience with power system studies. |
| R121 | Testing, inspection, calibration, and adjustments must be performed by an engineering technician, certified by NETA (Level III) or the National Institute for Certification in Engineering Technologies (NICET) with a minimum of 5 years' experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices. |
| R122 | A NICET Level III fire alarm technician must supervise the installation of the fire alarm system. The fire alarm technicians supervising the installation of equipment must be factory trained in the installation, adjustment, testing, and operation of the equipment specified herein and on the drawings. |
Recent awards in NAICS 236220
The newest federal contract awards in the same industry code from Department of Defense, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2031-02-11 | FEDVET CONSTRUCTIONDepartment of the Army · MIN GUARANTEE | $2,500 |
| 2030-09-28 | STRUCTSURE PROJECTS INCDepartment of the Navy · MEDICAL MACC-MINIMUM GUARANTEE | $0 |
| 2027-11-02 | CCI PRIME CONTRACTORS, LLCDepartment of the Air Force · FY25 MSG CES HANGAR H285 REPAIR MAINTENANCE DOCK | $27.62 million |
| 2027-07-31 | DOYON TECHNICAL SERVICES, LLCDepartment of the Army · PJ00082-25 - PROVIDE AND INSTALL ALL MATERIAL AND LABOR NECESSARY TO DEMO FAILED CMP, AND RE-INSTALL RCP. PJ00018-26 - DESIGN, DEMOLISH, INSTALL, AND COMMISSION A COMPLETE AND OPERATIONAL NEW DRY PIPE | $486,999 |
| 2027-07-17 | CONTI FEDERAL SERVICES, LLCDepartment of the Army · B-21 60 ROW SOUTH ENVIRONMENTAL PROTECTION SHELTERS (EPS) AT ELLSWORTH AIR FORCE BASE (AFB), SOUTH DAKOTA (SD) | $43.99 million |
| 2027-04-28 | MIRADOR ENTERPRISES, INC.Department of the Air Force · THE CONTRACTOR SHALL PROVIDE ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY TO DESIGN INSTALL EMERGENCY WASH STATIONS, HOLLOMAN AFB, NEW MEXICO. | $79,056 |
Source: USAspending.gov, retrieved 2026-10-29. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.