RWP - Test Site 2 (TS2) Improvements & Modernization, Aerospace Vehicle Survivability Facility (AVSF): requirements and submission rules
35 requirements and 2 submission rules found in the solicitation documents for FA9101269TS2. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Submission Format: Whitepapers must be submitted in PDF format, limited to 15 pages, excluding ROM and schedule details.
- Submission Deadline: 16 November 2026
Requirements
| ID | Requirement |
|---|---|
| R1 | The Performer's response must focus on demonstrating their technical capability, experience, and methodology to execute this project successfully. |
| R2 | The Performer must show they have the technical expertise, personnel, equipment, and supply chain to design-build the system per the SOO. |
| R3 | The Performer must clearly outline their proposed IP and data rights assertion strategy. |
| R4 | All IP and data rights assertions must reference "Article: Intellectual Property Rights in accordance with part 3 of the AEDC Velocity Consortium Request for Whitepaper" for VAC members. Non-VAC industry partners must clearly state IP and data rights assertions within the white paper. |
| R5 | The Performer is required to provide formal confirmation of the specific prototype rights they will grant to the Government for the designs, "as-built" CAD files, and operational/maintenance documentation. |
| R6 | To be eligible for award, the Performer must meet the statutory requirements of 10 U.S.C. § 4022(d). The Performer's whitepaper must explicitly detail how they satisfy at least one of the following criteria: Criterion 1... Criterion 2... Criterion 3... Criterion 4... |
| R7 | Performers must provide a detailed execution schedule and a Rough Order of Magnitude (ROM) cost estimate for all Base Milestones. |
| R8 | Performers are not required to provide pricing or ROM estimates for the Unpriced/Unfunded Options but are required to provide an estimated schedule and integration plan for these options. |
| R9 | The Performer must demonstrate their compliance with defense cybersecurity standards. |
| R10 | All cybersecurity protocols must reference "Article: Cybersecurity Requirements (CUI and CMMC)". |
| R11 | Performers must explicitly highlight that compliance with these cybersecurity standards flows down to all subcontractors, suppliers, and consortium partners, and remains the sole responsibility of the prime Performer. |
| R12 | The Performer must map their proposed timeline and schedule directly to milestones. |
| R13 | The proposed design must address several critical deficiencies inherent in the current site. Specifically, operations are currently hindered by limited ballistic threat capture capabilities and inadequate fuel containment and recovery systems. Furthermore, the facility experiences extended and inefficient test setup times and is unable to accommodate varied shot line elevations, remaining strictly limited to horizontal configurations. |
| R14 | A new steel test superstructure (approx. 24’ Width x 50’ Length x 50’ Height) shall provide both a ground-level test area and an elevated platform at a height of 20’. |
| R15 | The superstructure shall include an integrated 25-ton bridge crane with a hook clearance of ~ 20’ above the first level platform and the ability to transfer test items from the ground level to anywhere on the elevated platform via removable grating. |
| R16 | In addition, the first level platform shall support a 5-ton monorail. |
| R17 | The design must incorporate a concrete/steel deck roof structure covering the entire crane span. |
| R18 | The contractor shall design and install a steel fuel containment catch pan capable of capturing and containing up to 1,000-gallons of fuel for an individual ballistic test. |
| R19 | The contactor shall design and install a 6,000-gallon fuel recovery tank and provide a portable pump system which transfers fuel from the “catch pan” to the recovery tank. |
| R20 | The contractor shall be responsible for the end-to-end management, engineering, fabrication, installation, and functional verification of the entire system. |
| R21 | Blast analysis is not necessary; however, designing the structure for accidental fires is required. Design should include the best approach for fire design per AISC, ACI, and owner input. |
| R22 | A 40’ long x 4’ high concrete curb is required along the north edge of the test area. |
| R23 | Any proposed design requiring modification to existing infrastructure shall be identified early and will be considered out of scope unless otherwise approved. |
| R24 | The roof shall provide protection to personnel and test articles/equipment from falling debris (weather and adjacent concrete wall). |
| R25 | Test superstructure shall be designed to incorporate removable ballistic protection (bullet catchers, steel plates, etc.). Shields drawings/weights to be provided by owner. |
| R26 | Design shall include wide stair access to the upper platform and ladder access to roof. |
| R27 | Design shall adhere to all personnel and test safety standards. |
| R28 | The bridge crane system must meet all requirements of the Crane Manufacturers Association of America (CMAA) and be certified in accordance with OSHA and ASME standards. |
| R29 | The first level platform to have the higher of a 100,000 lbs. total (blanket) load or code required live load. Grating design drawings, to be incorporated in this project, to be provided by owner. |
| R30 | The system must be compatible with Jet-A, JP-8, and other standard military-grade aviation fuels. |
| R31 | The moveable pump system shall be capable of transferring fuel from the catch pan to the recovery tank at a minimum rate of ~ 180 gallons per minute. |
| R32 | The fuel system must include emergency shut offs and be compliant with all relevant EPA, local, and WPAFB environmental regulations for fuel storage and handling. |
| R33 | The construction and installation plan must minimize disruption to ongoing operations at adjacent AVSF test sites. A phasing plan may be required. |
| R34 | The design must specify all required utility connections, including power (voltage and phase requirements), water, and data acquisition/controls/communication lines. |
| R35 | The contractor shall provide the following deliverables: A fully constructed and operational Test Site 2 (superstructure, elevated platform, fuel pan, fuel recovery tank and pump, concrete retention wall, utility connections, etc.); Comprehensive documentation for operation, safety, and long-term maintenance; Design Reviews including Preliminary Design Reviews (PDR) and Critical Design Reviews (CDR) with government stakeholders; Final “as-built” drawings, including certified equipment drawings for the bridge crane and monorail, in both PDF and native CAD format upon project completion. |
Recent awards in NAICS 236220
The newest federal contract awards in the same industry code from Department of Defense, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2031-02-11 | FEDVET CONSTRUCTIONDepartment of the Army · MIN GUARANTEE | $2,500 |
| 2030-09-28 | STRUCTSURE PROJECTS INCDepartment of the Navy · MEDICAL MACC-MINIMUM GUARANTEE | $0 |
| 2027-11-02 | CCI PRIME CONTRACTORS, LLCDepartment of the Air Force · FY25 MSG CES HANGAR H285 REPAIR MAINTENANCE DOCK | $27.62 million |
| 2027-07-31 | DOYON TECHNICAL SERVICES, LLCDepartment of the Army · PJ00082-25 - PROVIDE AND INSTALL ALL MATERIAL AND LABOR NECESSARY TO DEMO FAILED CMP, AND RE-INSTALL RCP. PJ00018-26 - DESIGN, DEMOLISH, INSTALL, AND COMMISSION A COMPLETE AND OPERATIONAL NEW DRY PIPE | $486,999 |
| 2027-07-17 | CONTI FEDERAL SERVICES, LLCDepartment of the Army · B-21 60 ROW SOUTH ENVIRONMENTAL PROTECTION SHELTERS (EPS) AT ELLSWORTH AIR FORCE BASE (AFB), SOUTH DAKOTA (SD) | $43.99 million |
| 2027-04-28 | MIRADOR ENTERPRISES, INC.Department of the Air Force · THE CONTRACTOR SHALL PROVIDE ALL MATERIALS, EQUIPMENT, AND LABOR NECESSARY TO DESIGN INSTALL EMERGENCY WASH STATIONS, HOLLOMAN AFB, NEW MEXICO. | $79,056 |
Source: USAspending.gov, retrieved 2026-10-25. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.