Repair Taxiway Alpha & Bravo - North Auxiliary Airfield: requirements and submission rules
60 requirements and 15 submission rules found in the solicitation documents for FA441827R0002. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Update and resubmit data for final approval no later than 30 calendar days SECTION 01 78 00 Page 9
- If provided byt the Government, the contractor shall utilize and manage the Government provided program at no additional cost to the Government.1.5 PREPARATION 1.5.1 Transmittal Form Transmit each submittal, except sample installations and sample panels to office of approving authority.
- Submit all aggregate test results and samples to the Government at least 14 days prior to start of construction.
- The term "status" as indicated below must include due date and whether item has been submitted or was accomplished.
- Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly pay estimate.
- Submit a certification of compliance signed by the manager of the laboratory stating that it meets these requirements to the Government prior to the start of construction.
- Utility outage, and road closure requests shall be submitted to the Contracting Officer for coordination and Government approval at least 21 days prior to the desired outage or closure date.
- Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
- Submit manufacturer's instructions prior to installation.
- Submit one sample of each required item. b.
- Submit one sample panel or provide one sample installation where directed.
- Submit one sample of non-solid materials.
- Include certifications to be submitted with the pertinent drawings at the same time.
- Submit a schedule of the work to the Contracting Officer describing the work to be accomplished; the location of the work, noting distances from the ends of landing areas, taxiways and buildings and other structures as necessary; and dates and hours during which the work is to be accomplished.
- Contractor shall submit a SPCD to the Contracting Officer describing how it will comply with the requirements of the Construction Operational Safety and Phasing Plan (COSPP) and supplying any details that could not be determined before contract award.
Requirements
| ID | Requirement |
|---|---|
| R1 | The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-01 Preconstruction Submittals: Utility Outage Requests; G, Road Closure Requests; G, Air Force Work Clearance Permit; G |
| R2 | Obtain a work clearance/digging permit prior to start of excavation. The Contractor is responsible for marking and verifying all utilities. |
| R3 | Notify the Contracting Officer at least 72 hours prior to starting excavation work. |
| R4 | Contractor shall maintain property control records for material or equipment designated as salvage. |
| R5 | Ensure that all Contractor personnel employed on Joint Base Charleston become familiar with and obey Installation regulations including safety, fire, traffic and security regulations. |
| R6 | Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. |
| R7 | Contractor shall furnish a completed Joint Base Charleston (JB CHS) Worksheet for Base Access form for all personnel requesting badges/passes for Base Sponsor digital signature no later than 7 calendar days in advance of needing a badge/pass. |
| R8 | When Applicants no longer requires access, it is the Prime Contractor's responsibility to ensure all access badges/passes are promptly returned to the issuing VCC. Contractor shall immediately report instances of lost or stolen badges/passes to the Base Sponsor. |
| R9 | Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. |
| R10 | The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services without Government notification and approval. |
| R11 | Prior to submitting a dig permit request, the Contractor shall contact South Carolina Palmetto Utility Protection Services (PUPS) and obtain a PUPS tracking number. |
| R12 | Complete the Air Force - Base Civil Engineering - Dig Permit Request and transmit to the Contracting Officer or the Contracting Officer Representative for routing and approval 14 calendar days prior to the desired outage or closure date. |
| R13 | Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage: a. Comprehensive general liability: $500,000 per occurrence b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage c. Workmen's compensation as required by Federal and State workers'compensation and occupational disease laws. d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers. e. Others as required by State law. |
| R14 | Have at least one qualified superintendent capable of reading, writing, and conversing fluently in the English language, on the job-site during working hours. |
| R15 | Superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size, scope and complexity to this project. |
| R16 | Approval of the project superintendent is required prior to the start of construction. Provide a resume for the proposed superintendent describing their experience with references and qualifications to the contracting officer for approval. |
| R17 | After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the contract and safety program, preparation of the schedule of prices, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the 'Interim DD Form 1354' Submittal. |
| R18 | Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. |
| R19 | The Baseline Project Schedule shall be submitted for approval within 30 calendar days after the Notice to Proceed (NTP) has been acknowledged. |
| R20 | The Contractor shall use the critical path method (CPM) and the Precedence Diagram Method (PDM) to schedule and control project activities. |
| R21 | Prior to commencement of work, submit the Initial Contract Progress Report (AF IMT 3065). |
| R22 | Prior to commencement of work, submit the Initial Contract Progress Schedule (AF IMT 3064). |
| R23 | Three hard copies and one electronic file of the 3-Week Look Ahead Schedule shall be delivered to the Contracting Officer no later than 9 a.m. each Monday and reviewed during the CQC Coordination Meetings. |
| R24 | Submit a Time Impact Analysis (TIA) with each cost and time proposal for a proposed change clearly illustrating the influence of each change or delay on the Contract Completion Date (CCD) or milestones. |
| R25 | Prior to commencement of work, submit the following to the Contracting Officer: Existing Conditions Survey, Construction Operations Plan, Safety Plan, Heavy Equipment and Vehicle List. |
| R26 | Provide a minimum of 2 aviation red or high intensity white obstruction lights on temporary structures (including cranes) over 100 feet above ground level. |
| R27 | Obtain an approved BCE Work Clearance Request, AF Form 103, prior to the start of excavation, digging work, or work that disrupts aircraft or vehicular traffic flow, base utility services, fire and intrusion alarm system, or routine activities of the Activity. |
| R28 | During work within the landing area, have an operator (who speaks fluent English) available for radio contact with the tower at all times. Radio frequency must be approved by the tower. |
| R29 | Prior to being allowed any access to the site, the Contractor shall prepare, submit and receive approval of a Safety Plan Compliance Document. |
| R30 | Forms must be submitted to the FAA a minimum of 45 days before the start of construction. (FAA Form 7460-1, FAA Form 7460-2). |
| R31 | The SSHO must meets the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one (1) person at each project site to function as the Site Safety and Health Officer (SSHO). |
| R32 | Submit the APP to the Contracting Officer 15 calendar days prior to the date of the preconstruction conference for acceptance. |
| R33 | Prepare and sign weight handling critical lift plans for lifts over 75 percent of the capacity of the crane or hoist... Submit 15 calendar days prior to on-site work... |
| R34 | Submit the AHA for review at least 15 calendar days prior to the start of each phase. |
| R35 | Notify the Contracting Officer as soon as practical, but no more than four hours, after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility Accidents, property damage equal to or greater than $2,000, or any weight handling equipment accident. |
| R36 | Provide at least two 20 pound 4A:20 BC rated extinguishers for normal 'Hot Work'. All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal. It is also mandatory to have a designated FIRE WATCH for any 'Hot Work' done at this activity. |
| R37 | Apply for utility outages at least 28 days in advance. As a minimum, the request must include the location of the outage, utilities being affected, duration of outage and any necessary sketches. |
| R38 | All underground utilities in the work area must be positively identified by a third party, independent, private utility locating company in addition to any station locating service and coordinated with the station utility department. |
| R39 | Submit a QC plan within 15 calendar days after receipt of Notice of Award. |
| R40 | Acceptance of the QC plan is required prior to the start of construction. |
| R41 | Provide a QC Manager at the work site to implement and manage the QC program. The QC Manager may not perform the duties of project superintendent. |
| R42 | QC Manager: An individual with a minimum of 10 years combined experience as a superintendent, inspector, QC Manager, project manager, or construction manager on similar size and type construction contracts which included the major trades that are part of this contract. |
| R43 | In addition to the above experience and education requirements, the QC Manager shall have completed the course Construction Quality Management for Contractors and will have a current certificate. |
| R44 | Construction materials testing laboratories must be accredited by a laboratory accreditation authority and will be required to submit a copy of the Certificate of Accreditation and Scope of Accreditation. |
| R45 | Prior to the start of work, submit a site plan showing the locations and dimensions of temporary facilities (including layouts and details, equipment and material storage area (onsite and offsite), and access and haul routes, avenues of ingress/egress to the fenced area and details of the fence installation. |
| R46 | Provide the Government Resident Engineer with an office, approximately 200 square feet in floor area, located where directed and providing space heat, electric light and power, and toilet facilities consisting of one lavatory and one water closet complete with connections to water and sewer service. |
| R47 | Using the attached AFFIRMATIVE PROCUREMENT REPORTING FORM, the contractor shall consolidate and provide this information to the contracting officer in a signed monthly report. |
| R48 | Fourteen days after the environmental protection meeting, submit the proposed Environmental Protection Plan for further discussion, review, and approval. Commencement of work shall not begin until the environmental protection plan has been approved. |
| R49 | Submit truck and material haul routes along with a plan for controlling dirt, debris, and dust on base roadways. |
| R50 | Within 30 days after contract award and prior to performing any demolition work, submit a Waste Management Plan for review and approval. |
| R51 | At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. |
| R52 | Submit the final record PDF and CAD drawings package for the entire project within 20 days of substantial completion of all phases of work. |
| R53 | Near the completion of Project, but a minimum of 60 days prior to final acceptance of the work, complete, update draft DD FORM 1354 and submit an accounting of all installed property with Interim DD FORM 1354. |
| R54 | The Contractor shall attend a one day airfield electrical workshop on base in advance of the electrical work. The workshop will be scheduled by the Government. The workshop shall be attended by the Contractor's QC Manager, electrical superintendants, electrical foremen and electricians. |
| R55 | Submit certification containing the names and the qualifications of persons recommended to perform the splicing and termination of medium-voltage cables approved for installation under this contract. The certification shall indicate that any person recommended to perform actual splicing and termination has been adequately trained in the proper techniques and has had at least 3 recent years of experience in splicing and terminating the same or similar types of cables approved for installation. |
| R56 | Submit a Shoring and Sheeting plan for approval 15 days prior to starting work. Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of excavations. |
| R57 | Hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. |
| R58 | Prior to any work being completed, submit a Paint Removal Process Plan for approval by the Contracting Officer. |
| R59 | Prior to full production, place a test section for each JMF used. |
| R60 | Submit documentation of qualifications in resume format a minimum of 14 days before pavement marking work is to be performed showing personnel who will be performing the work have experience working on airfields, operating mobile self-powered marking, cleaning, and paint removal equipment and performing these tasks. Provide certification for pavement marking machine operator and Foreman demonstrating experience successfully completing a minimum of two airfield pavement marking projects of similar size and scope. |
Recent awards in NAICS 237310
The newest federal contract awards in the same industry code from Department of Defense, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-08-12 | STEELCO CHAIN LINK FENCE ERECTING CO., INC.Department of the Army · ROAD GATE PAINTING, ROAD GATE INSTALLATION, REMOVAL AND REPLACEMENT OF GUARDRAILS, BUFFUMVILLE LAKE, CHARLTON, MA | $120,057 |
| 2026-08-10 | DOUBLE A SERVICES INCDepartment of the Army · PAVING REPAIR FREEDOM RAMP STORM DRAINS | $816,041 |
| 2026-08-09 | CLASSIC SITE SOLUTIONS INCDepartment of the Army · PROJECT OFFICE PARKING AND ACCESS ROAD PAVING AND CULVERTS, WEST HILL DAM, UXBRIDGE, MA | $747,419 |
| 2026-08-03 | WILLARD ASPHALT PAVING, INC.Department of the Army · THE PURPOSE OF THIS TASK ORDER IS TO PAINT LINES ON THE RANGE 14 PAD. SEE SOW FOR DETAILS. | $1,396 |
| 2026-08-03 | DURHAM FENCE COMPANY, INC.Department of the Army · GUARDRAIL REPLACEMENT, HODGES VILLAGE DAM, OXFORD, MA | $65,340 |
| 2026-08-01 | WIREGRASS CONSTRUCTION COMPANY, INC.Department of the Army · THIS REQUIREMENT IS FOR A PERFORMANCE-BASED ACQUISITION FOR ASPHALT PAVING, CONSTRUCTION OF HORIZONTAL STRUCTURES, EARTH WORKS, AND STORM DRAINAGE STRUCTURES THAT ARE ON OROWNED BY FORT NOVOSEL. | $421,948 |
Source: USAspending.gov, retrieved 2026-10-31. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.