SEPA PARKING LOT REPAVING AND REPAIRS: requirements and submission rules
62 requirements and 8 submission rules found in the solicitation documents for 89503511102026. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Deadline for submission of all questions will be December 4, 2026 @12:00 pm Eastern time and Deadline for responses will be December 9, 2026, on Sam.gov
- All proposals must be received by December 15, 2026, no later than 12:00 p.m.
- Bid Submission Deadline: 3pm Eastern Time on December 15, 2026
- The successful Offeror shall submit the executed bonds to the Contracting Officer within ten (10) calendar days after contract award, unless otherwise authorized in writing by the Contracting Officer.
- Contractors must maintain active registration in the System for Award Management (SAM) at www.sam.gov, consistent with applicable FAR requirements, to be eligible for contract award.
- Offeror must be registered in the System for Award Management, SAM, https://www.sam.gov/.
- All offerors who bid on Federal Government Contracts are required to be registered in SAM, keep the registration current, an update annually.
- Please note that this RFP or submitted bids do not constitute a contract, and we reserve the right to accept or reject any or all proposals received.
Requirements
| ID | Requirement |
|---|---|
| R1 | The required work shall be performed in accordance with the attached Performance-Based Statement of Work (PWS), which outlines the project scope, technical specifications, performance requirements, and expected outcomes. |
| R2 | All work shall be completed in accordance with the requirements and specifications identified in the PWS. |
| R3 | Prospective contractors are strongly encouraged, but not required, to participate in a site visit to assess existing conditions, evaluate the scope of work, and obtain a clear understanding of the project requirements before submitting a quotation. |
| R4 | Proposals may be submitted by mail or electronically via email using the mailing address identified on page 5 of the solicitation. |
| R5 | All questions, requests for clarification, or inquiries concerning this solicitation shall be directed to both designated Contracting Officers: Tabitha Rambert, Contracting Officer; Juvonna Mattox, Contracting Officer |
| R6 | Make existing ditches functional at Athens Tech Drive and on northeast side of building at adjacent school property. Remove overgrowth of vegetation (excluding trees) and debris in existing swales and ditches to ensure functional surface drainage to adjacent properties and right-of-way. |
| R7 | Remove debris from existing trench drains and ensure trench drain functionality. |
| R8 | Sweep and Clean: Thoroughly clean the entire parking lot surface using commercial blowers and broom sweepers to remove all dirt, debris, and vegetation in paved areas. |
| R9 | Oil Spot Treatment: Clean and prime oil/grease spots with a designated primer to ensure proper sealant adhesion. |
| R10 | Pressure wash existing curb and gutter and sidewalks. |
| R11 | Sawcut, remove and replace to match existing approximately 12 linear feet of 24-inch concrete curb and gutter affected by water line damage at southeast corner of building. |
| R12 | Sawcut and remove any damaged existing asphalt paving above water line damage including sunken asphalt. Repair any damage to soil base. Install GAB as needed to provide adequate base for asphalt. Apply prime coat. |
| R13 | Install no less than 2” asphalt above repaired base to match existing surface drainage scheme flush with existing asphalt. |
| R14 | Sawcut and remove existing asphalt with alligator cracking Areas to include: Near dumpster approximately 1,000 sf; Between waterline damage and concrete aprons at southeast entrance approximately 1,000 sf; Near generator at northwest corner of building approximately 150 sf; Near deliver entrance at rear of building 50 sf; Near northeast corner of building approximately 750 sf |
| R15 | Repair any damage to soil base. Install GAB as needed to provide adequate base for asphalt. Apply prime coat. |
| R16 | Crack Sealing: Clean cracks larger than 1/8 inch of debris and seal with hot-applied crack sealant not to exceed 5,000 linear feet. |
| R17 | Sealcoating: Apply two coats of high-quality asphalt emulsion seal coat to the entire parking lot asphalt surface approximately 55,000 sf. |
| R18 | Striping and Marking: Restripe all parking stalls, including ADA-compliant spaces, government vehicle spaces, and directional arrows using durable white traffic paint. |
| R19 | Southeastern has a 24-hour Operations Center so building access will be needed at all times during the work. |
| R20 | All travel to and from Southeastern offices will be provided by the contractor. The Government will not separately reimburse the contractor for travel expenses or any other direct costs. |
| R21 | The Contractor shall comply with Department of Energy (DOE) Safety and Security Orders and Directives, including, but not limited to, the safety requirements defined in all applicable Federal, State and local laws, regulations and ordinances. When questionable, the most stringent shall apply. |
| R22 | Contractor personnel shall comply with all applicable provisions of the State Labor and Industries Safety and Health Regulations, U.S. Department of Labor, Occupational Safety and Health Administration (OSHA) Standards 29 CFR 1910 and 29 CFR 1926, Environmental Protection Agency (EPA) Title 40 CFR 170 (Worker Protection Standard) and other applicable Federal, State, and location regulations. |
| R23 | Job-related injuries/illnesses to Contractor employees shall be reported to the Technical Representative. |
| R24 | The contractor shall implement appropriate safety measures, including barricades, warning signage, traffic control, and restricted access to active construction areas, to protect government personnel, visitors, and property. This includes the use of 811 and taking all reasonable steps necessary to make certain that all active, abandoned, or unknown utilities are identified. |
| R25 | The contractor shall comply with all applicable Federal, State, and local laws, regulations, ordinances and codes governing performance of their services on Southeastern premises in Elberton, Georgia, and any other locations specified under the contract. |
| R26 | The contractor shall comply with all applicable Federal, State and local safety and health laws, regulations and ordinances, and national standards including 29 CFR 1910. |
| R27 | Site Accessibility: Contractor access, equipment staging, material storage, and construction activities shall be limited to Government-authorized locations. The contractor shall coordinate any required parking lot closures with the designated Government representative. |
| R28 | Environmental Compliance: The contractor shall comply with applicable federal, state, and local environmental requirements, including proper handling and disposal of removed asphalt, construction debris, and other waste materials. |
| R29 | Please include a building-entry and parking solution for the entire project duration and provide a clear project timeline. Southeastern’s 24-hour operations center must remain accessible at all times. |
| R30 | The Contractor shall maintain the required insurance throughout the contract performance period. Insurance requirements are separate from, and do not replace, any required bid guarantee or performance and payment bonds. |
| R31 | The Contractor and all applicable subcontractors shall comply with the prevailing wage rates and fringe benefits established by the U.S. Department of Labor for the geographic location and classification of construction covered by this requirement. |
| R32 | The Contractor shall: Pay all covered laborers and mechanics no less than the applicable prevailing wages and fringe benefits. |
| R33 | The Contractor shall: Submit weekly certified payroll records and required statements of compliance in accordance with FAR 52.222-8. |
| R34 | The Contractor shall: Ensure applicable subcontractors comply with all required labor standards. |
| R35 | The Contractor shall: Maintain payroll and employment records as required by the contract. |
| R36 | The Contractor shall: Comply with the applicable labor standards clauses incorporated into the solicitation and resulting contract. |
| R37 | In accordance with FAR 28.102 and FAR 52.228-15, the successful Offeror shall furnish performance and payment bonds for any resulting construction contract exceeding $150,000. The Performance Bond (Standard Form 25) shall be in the amount of 100 percent of the awarded contract price. The Payment Bond (Standard Form 25A) shall be in the amount of 100 percent of the contract price awarded. |
| R38 | The bonds shall be supported by acceptable sureties or other security in accordance with FAR Part 28. |
| R39 | Offerors shall account for all applicable wage and fringe benefit requirements when preparing their quotations. |
| R40 | The bid guarantee must equal at least 20% of the offer price and must be submitted with the offer. |
| R41 | The Contractor shall provide a total firm-fixed price for all labor, equipment, materials, supervision, transportation, disposal, and incidental work necessary to complete the parking lot asphalt repair and repaving project. |
| R42 | The Contractor shall notify the Contracting Officer when all asphalt repair and repaving work has been completed. |
| R43 | Following completion and Government acceptance of all required work, the Contractor shall submit a final invoice to the contracting offer via email to: Tabitha.Rambert@sepa.doe.gov |
| R44 | Final payment shall be made in accordance with FAR 52.232-5 and FAR 52.232-27, including applicable requirements for a proper invoice and release of claims. |
| R45 | Technical Approach: Technical capability of the Technical Approach offered to meet the Government requirement; the approach must include Contractor’s understanding of asphalt removal, base preparation, paving, compaction, drainage, and pavement markings. A logical sequence of tasks that you will perform to accomplish the requirements including specific methods, technologies, processes, tools, and resources to deliver the required results. Identify and describe the specific techniques and steps that will be applied during the accomplishment of all tasks of this project. Please include a roadmap for execution, including timelines, teams’ roles, and technical solutions. |
| R46 | Past Performance-Relevant Experience: Evidence of successfully performing similar asphalt paving or parking lot rehabilitation projects (i.e. size, scope and complexity). |
| R47 | Any scope changes require review, formal documentation and approval by the Contracting Officer |
| R48 | Each contractor shall submit a complete proposal containing the following information: Detailed Price Quotation: A comprehensive price breakdown identifying the total firm-fixed price and associated costs necessary to complete the project, including labor, materials, equipment, mobilization, site preparation, and other applicable expenses. |
| R49 | Technical Approach/Project Plan: A description of the contractor’s proposed methodology for performing the required work, including the anticipated project schedule, equipment, staffing, quality control measures, and approach to meeting the performance requirements. |
| R50 | Past Performance: Information demonstrating the contractor’s experience successfully completing projects of similar scope, size, and complexity, including relevant project references (including contract numbers, point of contacts with telephone numbers and other relevant information). Please submit a minimum of three references with your proposal package. |
| R51 | Additional Supporting Information: Any other relevant documentation the contractor believes demonstrates its qualifications, technical capabilities, and ability to successfully perform the required services. |
| R52 | The Contractor shall, at its own expense, obtain and maintain insurance coverage throughout the performance of this contract in accordance with FAR 52.228-5, Insurance—Work on a Government Installation. |
| R53 | Prior to commencement of work, the Contractor shall furnish a Certificate of Insurance demonstrating the required coverage and evidence of any required policy endorsements. |
| R54 | Title your submission “SEPA Parking Lot Repaving and Repairs” |
| R55 | Please include the solicitation number in the subject line: 89503511102026 |
| R56 | Include offeror name, address, telephone number, and email address |
| R57 | “Remit to:” address, if different than mailing address |
| R58 | Project Schedule: A proposed schedule demonstrating the ability to complete the work within the required performance period. |
| R59 | Quality Control: Procedures for ensuring workmanship, material quality, required testing, and compliance with contract specifications. |
| R60 | GSA Contract Number (if applicable) and/or SAM UEI Number |
| R61 | When submitting the bid please include the offeror Unique Entity ID and your preferred NAICS Code. |
| R62 | Please email any questions that you may have to both Contracting Officer listed above. |
Recent awards in NAICS 238990
The newest federal contract awards in the same industry code from Department of Energy, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-08-25 | MAYOINTHEMIX LLCDepartment of Energy · RAPID CITY MAINTENANCE FACILITY SECURITY FENCE RESTORATION | $30,655 |
| 2026-06-01 | FEDERAL BUILDERS LLCDepartment of Energy · BISMARCK DISTRICT OFFICE CRAWLSPACE REMEDIATION | $34,475 |
| 2025-03-24 | BOWEN DOOR SERVICE LLCDepartment of Energy · ROTO-GATE DOOR REPLACEMENTS WITH STOREFRONT DOORS | $27,016 |
| 2024-07-17 | MEADOWLARK ASPHALT MAINTENANCE LLCDepartment of Energy · ASPHALT CRACK SEALING AT BISMARCK O&M SERVICE CENTER | $15,792 |
| 2024-06-27 | PANHANDLE CLEANING & RESTORATION, INCDepartment of Energy · NETL MORGANTOWN, WV BUILDING 3 EMERGENCY FLOODING REMEDIATION | $67,878 |
| 2024-05-20 | TITAN CRANE & RIGGING INCDepartment of Energy · THIS IS A STANDALONE PURCHASE ORDER FOR BEALE CRANE RENTAL & OPERATOR SERVICE IAW WITH THE ATTACHED STATEMENT OF WORK. | $0 |
Source: USAspending.gov, retrieved 2026-11-11. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.