Submission rules that can disqualify a bid
- The offeror shall provide a written statement confirming that both proposed forklifts, meeting all Statement of Work requirements, will be available for delivery and commissioning at USCG TRACEN Birmingham-Southern no later than December 1, 2026.
- If temporary physical access to a Government facility is required for delivery, maintenance, training, or fueling, Contractor personnel shall comply with all local installation visitor control procedures, submit to standard security screening, and be escorted by Government personnel as required by local policy.
- 8.0 DELIVERABLES All deliverables shall be submitted to the GTR unless otherwise noted.
- (c) If the offeror deletes or modifies subparagraph (a)(2) above, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
Requirements
| ID | Requirement |
|---|---|
| R1 | Offerors are invited to state an opinion on whether the quantity(ies) of supplies on which bids, proposals or quotes are requested in this solicitation is (are) economically advantageous to the Government. |
| R2 | If different quantities are recommended, a total and a unit price must be quoted for applicable items. |
| R3 | Proposed Equipment Information. The offeror shall identify the manufacturer, make, and model of the proposed 6,000-pound forklift and 12,000-pound forklift. |
| R4 | Equipment Specification Documentation. The offeror shall provide manufacturer specification sheets, product literature, or equivalent documentation showing that each proposed forklift meets all requirements in Sections 2.1.1 and 2.1.2 of the Statement of Work. The documentation shall show, at a minimum, rated capacity, load center, fuel type, mast height, tire type, fork length, side-shift capability, and required safety equipment. |
| R5 | Service and Support Plan. The offeror shall provide a brief plan describing how it will perform the required maintenance, repair, replacement, LPG fuel delivery, and training services. The plan shall confirm the offeror’s ability to meet the timeframes stated in the Statement of Work, including: (1) Preventive maintenance at manufacturer-recommended intervals; (2) Replacement equipment, when required, within four business days after Government notification; (3) On-site LPG fuel replenishment within two business days after Government request; (4) Initial training within five business days after delivery and commissioning; and (5) Additional training, when requested, within 10 business days after Government request. |
| R6 | The offeror represents as part of its offer that— (i) it □ is, □ is not a small business concern; or (ii) It □ is, □ is not a small business joint venture that complies with the requirements of 13 CFR 121.103(h) and 13 CFR 125.8(a) and (b). [ The offeror shall enter the name and unique entity identifier of each party to the joint venture: __.] |
| R7 | The Offeror shall list foreign-made domestic personal protective equipment items. |
| R8 | The Contractor shall insert the substance of this clause in all subcontracts. |
| R9 | Unless otherwise specified, initial training certificates for each Contractor and subcontractor employee shall be provided to the Contracting Officer’s Representative (COR) not later than thirty (30) days after contract award. Subsequent training certificates to satisfy the annual training requirement shall be submitted to the COR via e-mail notification not later than October 31st of each year. |
| R10 | The DHS Rules of Behavior shall be signed before accessing DHS systems and sensitive information. |
| R11 | Unless otherwise specified, the Contractor shall e-mail copies of the signed DHS Rules of Behavior to the COR not later than thirty (30) days after contract award for each employee. |
| R12 | The Contractor shall deliver only domestic personal protective equipment except to the extent that it specified delivery of foreign-made domestic personal protective equipment in the provision of the solicitation entitled “Made in America Certificate – Personal Protective Equipment. |
| R13 | Except as provided in paragraph (c) of this clause, the contractor must submit payment requests electronically using the Invoice Processing Platform (IPP). |
| R14 | If alternate payment procedures are authorized, the contractor must include a copy of the contracting officer's written authorization with each payment request. |
| R15 | The Contractor shall provide two propane-powered forklifts for seven months at U.S. Coast Guard Training Center Birmingham-Southern: • One forklift with a rated lifting capacity of at least 6,000 pounds; and • One forklift with a rated lifting capacity of at least 12,000 pounds. |
| R16 | The Contractor shall deliver the forklifts, confirm they meet the required specifications, and provide the manuals and inspection records at delivery. |
| R17 | The Contractor shall maintain and repair both forklifts during the rental period. |
| R18 | The Contractor shall comply with all applicable Federal, State, and local laws and regulations that pertain to the rental, operation, maintenance, and fueling of industrial forklifts and the handling of liquid propane gas. |
| R19 | Provide one (1) standard counterbalanced industrial forklift with a minimum rated load capacity of 6,000 lbs at a 24-inch load center, powered by LPG, equipped with pneumatic or solid pneumatic tires for indoor and outdoor paved operations, a three-stage mast with a minimum 15-foot lift height, side-shift carriage, 48-inch pallet forks, an OEM-installed overhead guard meeting applicable powered-industrial-truck safety requirements and suitable for the Government’s intended operating environment, seatbelt, backup alarm, strobe beacon, Light-Emitting Diode (LED) work lights, and a mounted Class ABC dry chemical fire extinguisher. |
| R20 | Provide one (1) medium standard counterbalanced industrial forklift with a minimum rated load capacity of 12,000 lbs at a 24-inch load center, powered by LPG, equipped with pneumatic or solid pneumatic tires for indoor and outdoor paved operations, a two-stage or three-stage mast with a minimum 12-foot lift height, side-shift carriage, minimum 48-inch pallet forks, an OEM-installed overhead guard meeting applicable powered-industrial-truck safety requirements and suitable for the Government’s intended operating environment, seatbelt, backup alarm, strobe beacon, LED work lights, and a mounted Class ABC dry chemical fire extinguisher. |
| R21 | Provide one (1) weather-resistant copy of the Original Equipment Manufacturer (OEM) Operator and Maintenance (O&M) Manual and a legible load capacity data plate mounted on each forklift upon delivery. |
| R22 | Conduct a joint initial acceptance inspection and operational load verification review of OEM/load-rating documentation with the GTR upon delivery and provide a signed Pre-Delivery Inspection Report documenting baseline equipment condition, serial numbers, and initial hour-meter readings. |
| R23 | Perform scheduled preventive maintenance (PM) on both forklifts at the intervals specified by the OEM using a self-contained mobile service truck on-site at USCG TRACEN Birmingham-Southern or by transporting the equipment off-site at no additional cost to the Government. If off-site PM is required a comparable temporary replacement shall be provided and will need to be approved by the GTR. |
| R24 | Provide labor, OEM replacement parts, filters, lubricants, tires, hydraulic hoses, lift chains, engine tuning to maintain Carbon Monoxide (CO) exhaust emissions within permissible exposure limits for indoor/outdoor operation, and consumables required to maintain both forklifts in operational condition throughout the Period of Performance. |
| R25 | Contain and remove waste oils, hydraulic fluids, spent filters, oily rags, and maintenance debris generated during on-site service visits from USCG TRACEN Birmingham-Southern prior to departing the installation on the same day in accordance with Section 4.7. |
| R26 | Record each preventive maintenance service, safety inspection, and repair action on a Preventive Maintenance and Repair Service Ticket, and submit a copy of the ticket to the GTR via electronic mail within two (2) business days of service completion. |
| R27 | Respond to GTR notifications of equipment defect, mechanical breakdown, or safety deficiency, and conduct on-site troubleshooting and repair at USCG TRACEN Birmingham-Southern. |
| R28 | Provide, deliver, and offload a replacement forklift meeting the technical specifications of Section 2.1.1 (for the 6,000-lb unit) or Section 2.1.2 (for the 12,000-lb unit) to USCG TRACEN Birmingham-Southern within four (4) business days of GTR notification when a malfunctioning forklift cannot be repaired and returned to full operational status within four (4) business days of notification. |
| R29 | Remove the defective or inoperable forklift from USCG TRACEN Birmingham-Southern at no additional cost to the Government upon delivery of the comparable replacement forklift within two (2) business days. |
| R30 | Upon request from the GTR, the Contractor shall exchange a depleted LPG cylinder installed on either rental forklift with a full LPG cylinder of the correct type and capacity for that forklift. The Contractor shall perform the exchange at USCG TRACEN Birmingham-Southern during normal operating hours, 0800 through 1700 Central Time, Monday through Friday, excluding Federal holidays, within two (2) business days after receipt of the GTR’s request. |
| R31 | The Contractor shall remove each depleted LPG cylinder from the installation during the same visit in which the replacement cylinder is installed. The Contractor shall not leave spare LPG cylinders, depleted LPG cylinders, or bulk LPG storage tanks on Government premises. |
| R32 | For each completed cylinder exchange, the Contractor shall prepare an LPG Fuel Delivery Ticket that identifies, at a minimum: 1. Contract number and CLIN; 2. Date and time of service; 3. Forklift identification number or serial number; 4. Quantity delivered, expressed as the number of completed cylinder exchanges; 5. Cylinder type and capacity; 6. Name of the Contractor employee performing the service; and 7. Name and signature of the GTR or other Government representative acknowledging receipt. The Contractor shall submit the signed LPG Fuel Delivery Ticket with the applicable invoice. |
| R33 | The Contractor shall monitor cumulative invoiced amounts under the LPG NTE CLIN and shall notify the Contracting Officer and GTR in writing when cumulative invoiced amounts reach seventy-five percent (75%) of the NTE ceiling. |
| R34 | The Contractor shall not perform services that would cause the cumulative amount billed under the LPG CLIN to exceed the NTE ceiling unless authorized by a written contract modification signed by the Contracting Officer. |
| R35 | The Contractor shall furnish a current daily pre-operation inspection checklist for each forklift upon delivery. |
| R36 | Conduct one (1) initial on-site basic operating and safety training session for designated USCG personnel within five (5) business days following the delivery and commissioning of the two forklifts, scheduled in coordination with the GTR. |
| R37 | Conduct up to one (1) additional on-site basic operating and safety training sessions at the request of the GTR, scheduled within ten (10) business days of each GTR request. |
| R38 | Instruct trainees on both the 6,000-lb and 12,000-lb forklifts during each session, covering equipment controls, instrumentation, daily pre-operation inspection checklists, rated load capacity data plates, load stability and center-of-gravity principles, mast and side-shift operation, LPG fuel cylinder safety, indoor Carbon Monoxide ventilation precautions, and emergency shutdown procedures. |
| R39 | Provide a signed Training Attendance Roster and Training Completion Summary to the GTR within two (2) business days after each completed training session, documenting the training date, instructor name, topics covered, and names of USCG personnel in attendance. |
| R40 | Remove and transport both forklifts from USCG TRACEN Birmingham-Southern within five (5) business days after contract expiration using self-contained transport equipment without using Government lifting equipment or loading docks. |
| R41 | The Contractor shall provide qualified personnel to perform all requirements specified in this SOW. |
| R42 | The Contractor shall ensure that the services required under this SOW (equipment delivery, preventive maintenance, unscheduled repairs, equipment replacement, LPG fueling, and training) are performed within the stated timeframes. If a scheduled service visit cannot be completed as planned, the Contractor shall provide e-mail notification to the GTR as soon as practicable and shall complete the required service at the earliest opportunity. |
| R43 | Contractor personnel shall clearly always identify themselves as contractors. This includes wearing visible corporate identification badges while at Government facilities, identifying themselves as contractors during telephone conversations and in meetings, and including a contractor designation (e.g., “[Contractor Company Name]”) in all email signatures and electronic communications. |
| R44 | Contractor employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, and “off limits” areas) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees always present a professional appearance and that their conduct does not reflect discredit on the United States or the Department of Homeland Security. |
| R45 | The Contractor shall coordinate installation access with the Government Technical Representative (GTR). |
| R46 | The Contractor shall provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications). |
| R47 | The Contractor shall contain and remove all waste oils, hydraulic fluids, spent filters, oily rags, and maintenance debris generated during on-site service visits from the installation on the same day. The Contractor shall leave no residual materials on-site and shall comply with all applicable Federal, State, and local environmental regulations. |
| R48 | The Contractor shall furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 5.0. |
| R49 | The Contractor shall correct the rejected deliverable and return it per delivery instructions within the timeframe agreed with the GTR. |
| R50 | Unless otherwise specified in the Deliverables table or agreed in writing, the GTR will have five (5) business days to review deliverables and provide comments. The Contractor shall have five (5) business days to make corrections and redeliver. |
Recent awards in NAICS 532490
The newest federal contract awards in the same industry code from Department of Homeland Security, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-12-01 | SMITHS DETECTION INC.Office of Procurement Operations · LEASE OF X-RAY MACHINES | $0 |
| 2026-11-01 | BSE PERFORMANCE, LLCU.S. Coast Guard · 500K-750K BTU DIESEL FLAMELESS HEATER RENTALS | $12,277 |
| 2026-11-01 | SMITHS DETECTION INC.Office of Procurement Operations · X-RAY LEASING, REGION 10, BUILDING ID4335 IN BOISE, ID | $9,173 |
| 2026-10-12 | J. H. NORTON COMPANY, INC.U.S. Coast Guard · EQUIPMENT RENTAL- DUST COLLECTOR, AIR COMPRESSOR, AND BLAST POT | $53,006 |
| 2026-10-01 | SMITHS DETECTION INC.Office of Procurement Operations · LEASE OF TWO (2) NEW REPLACEMENT X-RAY MACHINES (AR2086) | $18,345 |
| 2026-10-01 | SMITHS DETECTION INC.Office of Procurement Operations · LEASE OF X-RAY MACHINES | $29,138 |
Source: USAspending.gov, retrieved 2026-11-01. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.