Tax Software and Support: requirements and submission rules
37 requirements and 13 submission rules found in the solicitation documents for 5000230074. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Submit Volumes I through IV electronically to louis.c.browniii@irs.gov and tanya.r.burnett@irs.gov no later than November 18, 2026, at 4:00 p.m.
- L.5 Volume III — Factor 3: Past Performance The offeror shall submit up to three contract references for performance within the three years preceding the proposal due date.
- Maintain historical SLA performance data for the duration of the contract and provide supporting documentation upon Government request 13.1 SLA Performance Reporting The Contractor shall submit a Monthly SLA Performance Report no later than five (5) business days following the end of each reporting month.
- L.8 Late Proposals FAR 52.215-1(c)(3) governs late proposals, modifications, and withdrawals.
- Recency means performance within the three years preceding the proposal due date; relevance considers similarity in scope, complexity and magnitude.
- The statement shall confirm compatibility with IPv6-only networks and shall be submitted prior to each release.
- Submit Reinvestigation requests within 6 months prior to expiration of current staff-like access
- L.7 Questions and Amendments Proposals responding to the RFP must be e-mailed to louis.c.browniii@irs.gov and tanya.r.burnett@irs.gov on or before 4PM ET November 18, 2026.
- Questions received may or may not be answered, and if answered will be answered through an amendment to the solicitation.
- L.2 Proposal Organization and Submission Offerors shall submit proposals in four separate, independently evaluable volumes: Volume I—Factor 1 Technical Approach; Volume II—Factor 2 Licensing, Middleware Integration & Support Capability; Volume III—Factor 3 Past Performance; and Volume IV—Factor 4 Price.
- Volume I shall address the proposed methods and implementation approach; Volume II shall substantiate existing resources, authorizations, infrastructure, and capacity.
- L.4 Volume II – Factor 2: Licensing, Middleware Integration & Support Capability The offeror shall provide verifiable evidence demonstrating its existing technical capabilities, qualifications, infrastructure, and available resources necessary to perform the requirements of the PWS.
- L.6 Volume IV — Factor 4: Price The offeror shall submit a completed price schedule for the base period and all four option periods, identifying the quantity, unit price, and extended price for each Contract Line Item Number (CLIN).
Requirements
| ID | Requirement |
|---|---|
| R1 | OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30. |
| R2 | CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN 1 COPIES TO ISSUING OFFICE. |
| R3 | All required information shall be electronically submitted in the formats specified in this solicitation. |
| R4 | All supplies and/or services provided must be in compliance with Section 508 of the Rehabilitation Act and provisions and requirements for accessibility contained in this solicitation (and resulting award). |
| R5 | Offers must be authorized sellers/resellers of the required supplies and/or services. |
| R6 | Proposals submittals must include: a. Solicitation number b. Entity UEI Number c. Applicable discounts to the Government d. POC name, address, and telephone number |
| R7 | Completed Provisions/Clauses |
| R8 | Failure to mark required provisions will result in a nonresponsive review and no rating will be given due to offerors failure to mark required responses. |
| R9 | **If there are any End User Language Agreements (EULA) or manufacturer software agreements that require IRS review and approval please submit at the time of your proposal. |
| R10 | The contractor shall identify all asserted restrictions and third-party license terms in its proposal for Government review.Section I (contract clauses) |
| R11 | Contractors must complete the contractor point of contact information below and submit it with their proposal submissions.Section I (contract clauses) |
| R12 | If the Contractor is unable to use the IPP for submitting payment requests starting on October 1, 2012, then a waiver form must be completed and submitted with the contractor's proposal submission for review and approval by the Contracting Officer based on one of the conditions listed in the waiver.Section I (contract clauses) |
| R13 | The contractor shall assign and identify, in its offer, a Contractor Security Representative (CSR) and alternate CSR to all contracts requiring staff-like access to IRS information, information technology and systems, facilities, and/or assets.Section I (contract clauses) |
| R14 | The contractor, by signing its offer, hereby asserts to the best of its knowledge and belief that the security control guideline(s) most suitable and applicable to the immediate contracting action, with due consideration to its proposed approach (and work environment) for fulfilling the Government’s requirements and standards for applicability described herein, is as follows (check only one block): [ ] IRM 10.8.1 [ ] Publication 4812 [ ] Both IRM 10.8.1 and Publication 4812Section I (contract clauses) |
| R15 | If Publication 4812 is selected (alone or in combination with IRM 10.8.1) as the most suitable security control guideline, the contractor must identify, as part of its proposal submissions (or its submissions under any modification to an existing contract incorporating this clause), the most suitable security control level within the following hierarchy of security control levels (from lowest or highest): • Software Application Development or Maintenance (SOFT) • Networked Information Technology Infrastructure (NET)Section I (contract clauses) |
| R16 | The offeror shall provide sufficient detail to permit evaluation against the criteria in Section M.L.1 |
| R17 | Pricing assumptions affecting technical performance shall be identified consistently in the applicable volumes.L.2 |
| R18 | Volume I Technical Approach: PDF, 12-pt Times New Roman, 1" margins, Page Limit 25 |
| R19 | Volume II Licensing, Middleware Integration & Support Capability: PDF, 12-pt Times New Roman, 1" margins, Page Limit 25 |
| R20 | Volume III Past Performance: PDF, Page Limit 10 |
| R21 | Volume IV Price: completed CLIN pricing table/schedule (Base + Option Periods), Excel + PDF, No Page Limit |
| R22 | The offeror shall describe its proposed technical approach, methodologies, implementation schedule, dependencies, risks, and mitigation strategies for satisfying the requirements of the Performance Work Statement (PWS).L.3 |
| R23 | The offeror shall describe its proposed approach to provisioning and administering 130 Tax Analyzer Enterprise licenses and up to 20 additional surge licenses, including entitlement tracking, fulfillment lead times, license administration, and continuity of service.L.3.1 |
| R24 | The offeror shall describe its proposed approach to provisioning and administering 150 Tax Planner licenses and up to 20 additional surge licenses, including entitlement tracking, renewal arrangements, and continuity of service.L.3.1 |
| R25 | The offeror shall describe its proposed approach to meeting the individual and corporate tax computation, audit support, scenario analysis, offline functionality, IRS forms, and XML/e-file import requirements identified in PWS Sections 4.1.1 through 4.1.7.L.3.3 |
| R26 | The offeror shall describe its proposed approach to providing Tier 1 through Tier 3 technical support, and Tier 4 escalation when applicable, including help desk operations, staffing, escalation procedures, ticketing, and response and resolution targets identified in PWS Sections 4.2 and 4.3.L.3.4 |
| R27 | The offeror shall describe its proposed approach to maintaining and supporting the IMS Tax Engine Middleware, including e-file processing, IRS system interfaces, XML import/export, patches, version compatibility, integration testing, and change coordination under PWS Section 4.5.L.3.5 |
| R28 | The offeror shall describe its proposed approach to delivering one annual 40-hour in-person Tax Analyzer training session and one annual 40-hour in-person Tax Planner training session, each accommodating up to 25 participants, together with four quarterly one-hour virtual training sessions per product annually. The offeror shall address training curricula, instructor qualifications, scheduling, training materials, and Section 508 accessibility requirements consistent with PWS Section 4.6.L.3.6 |
| R29 | The offeror shall describe its proposed approach to ensuring uninterrupted IRS operations during transition-in and transition-out, including implementation schedules, dependencies, integration testing, risk mitigation, knowledge transfer, and any proposed interim continuity solution consistent with the PWS and Acquisition Plan.L.3.7 |
| R30 | The offeror shall provide evidence of its Original Equipment Manufacturer (OEM) status or authorized reseller arrangements, existing licensing infrastructure, entitlement management capabilities, and capacity to fulfill the required Tax Analyzer and Tax Planner licenses, including authorized surge quantities.L.4.1 |
| R31 | The offeror shall provide product documentation, technical specifications, or other verifiable evidence demonstrating that the proposed software possesses the functional capabilities required by the PWS, including applicable tax computations, audit support, offline functionality, and data import/export capabilities.L.4.2 |
| R32 | The offeror shall provide evidence of existing help desk infrastructure, qualified technical support personnel, ticketing systems, escalation resources, and support capacity necessary to meet the PWS service-level requirements.L.4.3 |
| R33 | The offeror shall provide evidence of available middleware engineering expertise, integration and testing tools, qualified technical personnel, and applicable third-party arrangements necessary to support the IMS Tax Engine Middleware.L.4.4 |
| R34 | The offeror shall provide evidence of available qualified instructors, training platforms, facilities or delivery arrangements, and accessible training materials sufficient to support the PWS training requirements.L.4.5 |
| R35 | For evaluation purposes, offerors shall price the full quantity of 20 Tax Analyzer surge licenses and 20 Tax Planner surge licenses for the base period and each of the four option periods.L.6 |
| R36 | All no-additional-charge training CLINs shall be priced at $0.00, with associated costs included in the applicable firm-fixed-price CLINs.L.6 |
| R37 | Offerors shall identify all pricing assumptions and provide sufficient supporting information to permit evaluation of price reasonableness. Offerors shall not add unauthorized CLINs.L.6 |
Recent awards in NAICS 513210
The newest federal contract awards in the same industry code from Department of the Treasury, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-10-27 | CAS SEVERN, INCBureau of Engraving and Printing · VMWARE LICENSES FOR BEP VIDEO MANAGEMENT SYSTEM | $242,876 |
| 2026-09-30 | IMPRES TECHNOLOGY SOLUTIONS, INCBureau of Engraving and Printing · DATAPATH LICENSES FOR BUREAU OF ENGRAVING AND PRINTING DC AND TX FACILITIES | $11,348 |
| 2026-09-30 | AMPED SOFTWARE USA INCInternal Revenue Service · SOFTWARE LICENSE AND TRAINING | $19,800 |
| 2026-09-30 | ORBITAX LLCInternal Revenue Service · ORBITAX TAX MODELING SOFTWARE AND SUPPORT | $450,000 |
| 2026-09-30 | QINTEL LLCInternal Revenue Service · QINTEL PLATFORM BLUE SUBSCRIPTION | $1.75 million |
| 2026-09-30 | DIGITAL AUDIO CORPInternal Revenue Service · FAUXDIO AUDIO AUTHENTICATION SOFTWARE LICENSES | $40,800 |
Source: USAspending.gov, retrieved 2026-10-25. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.