763-25-700 EHRM Infrastructure Upgrades Construction Dallas CMOP, TX: requirements and submission rules
96 requirements and 15 submission rules found in the solicitation documents for 36C77626B0028_1. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Submit the CQC Plan no later than 30 days after receipt of Notice to Proceed (NTP) proposed to implement the requirements of the FAR Clause 52.246.12 titled “Inspection of Construction”.
- Response to Specification: The Contractor shall submit a point-by- point statement of compliance with each paragraph of the security specification.
- Submit the APP to the Contracting Officer Representative for review for compliance with contract requirements in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 15 calendar days prior to the date of the preconstruction safety conference for acceptance.
- All submittals shall include six copies of adequate descriptive literature, catalog cuts, shop drawings, test reports, certifications, samples, and other data necessary for the Government to ascertain that the proposed materials and equipment comply with drawing and specification requirements.
- Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.
- The Contractor shall submit formal monthly updates to the submittal register in electronic format.
- Provide submittals in electronic format, with the exception of material samples.
- Submit sufficient information to demonstrate compliance with drawings and specifications. b.
- All power-dissipating components shall incorporate safety margins of not less than 25 percent with respect to dissipation ratings, maximum voltages, and current- carrying capacity.
- The Contractor shall submit a qualification proposal to the COTR, within 10 days of bid acceptance.
- Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer.
- After each rerun update, the resulting electronic project schedule data file shall be appropriately identified and submitted to the VA in accordance to the requirements listed in articles 1.4 and 1.7.
- Submit two sets of physical samples showing range of variation, for each required item.
- Certification of their competency/qualification shall be submitted to the Government Designated Authority (GDA) for acceptance prior to the start of that work activity.
- If more than one Competent/Qualified Person is used on the AHA activity, a list of names shall be submitted as an attachment to the AHA.
Requirements
| ID | Requirement |
|---|---|
| R1 | Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the upgrade of the facility infrastructure to support the new Electronic Health Record Modernization System as required by drawings and specifications. |
| R2 | Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer. |
| R3 | Before placement and installation of work subject to tests by testing laboratory retained by the Contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR. |
| R4 | All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. |
| R5 | Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. |
| R6 | No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time. |
| R7 | The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action. |
| R8 | The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. |
| R9 | Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies. |
| R10 | The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. |
| R11 | It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. |
| R12 | Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. |
| R13 | Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified. |
| R14 | Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman. |
| R15 | No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. |
| R16 | Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption. |
| R17 | Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR. |
| R18 | Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. |
| R19 | Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report |
| R20 | The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications. |
| R21 | Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR. |
| R22 | Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan. |
| R23 | Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. |
| R24 | Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. |
| R25 | At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. |
| R26 | As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. |
| R27 | Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified. |
| R28 | Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. |
| R29 | The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. |
| R30 | Notify Contracting Officer in writing, 60 days in advance, of date on which Contractor will be prepared to receive equipment furnished by Government. |
| R31 | The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements (Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). |
| R32 | Within 45 calendar days after receipt of Notice to Proceed, the Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved CPM schedule program. |
| R33 | The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. |
| R34 | The Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the VA. |
| R35 | All submittals are required to be approved prior to the start of the specified work activity. |
| R36 | The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified. All deviations submitted must include a side by side comparison of item being proposed against item specified. |
| R37 | Provide all electronic documents through an electronic FTP file sharing system. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic FTP file sharing system for the construction contract period of performance. |
| R38 | Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site. |
| R39 | In addition to the detailed requirements included in the provisions of this contract, comply with the most recent edition of USACE EM 385-1-1, comply with 29 CFR 1926, comply with 29 CFR 1910 as incorporated by reference within 29 CFR 1926, comply with ASSP A10.34, and all applicable federal, state, and local laws, ordinances, criteria, rules and regulations. |
| R40 | Work shall not begin until the AHA for the work activity has been accepted by the Resident Engineer, Contracting Officer Representative or Government Designated Authority and discussed with all engaged in the activity, including the Contractor, subcontractor(s), and Government on-site representatives at preparatory and initial control phase meetings. |
| R41 | The Prime Contractor shall provide a Safety oversight team that includes a minimum of one (1) person at each project site, for each shift, to function as the Site Safety and Health Officer (SSHO). The Prime Contractor shall provide a minimum of one “Full-Time” SSHO at each project site, for each shift (with no other duties) that holds as current, a professional safety certification with at least 3 years of dedicated construction safety related experience. |
| R42 | As a minimum the SSHO must have completed the OSHA 30-hour Construction Safety Outreach class within the past five (5) years and: 1. Seven (7) years of construction industry safety related experience. 2. OR have a safety and health degree from an accredited university or college and five (5) years of construction industry safety related experience 3. OR hold as current, a Certified Safety Professional (CSP) or a Construction Health and Safety Technician (CHST) certification and five (3) years of construction industry safety related experience. |
| R43 | All designated CPs shall have completed the OSHA 30-hour Construction Safety course and/or EM 385-1-1 40-hour training within the past 5 years. In addition, all CPs with high hazard work operations (such as operations involving asbestos, electrical, cranes, demolition, work at heights/fall protection, fire safety/life safety, ladder, rigging, scaffolds, and trenches/excavations) shall have a specialized formal course in the hazard recognition and control associated with those high hazard work operations. |
| R44 | All other construction workers shall have the OSHA 10-hour Construction Safety Outreach course within the past 5 years and any necessary safety training to be able to identify hazards within their work environment. |
| R45 | A Certified Safety Professional (CSP) with specialized knowledge in construction safety or a certified Construction Safety and Health Technician (CSHT) shall randomly conduct a monthly site safety inspection. The CSP or CSHT shall be one that is not a part of the immediate site project team. |
| R46 | Notify and provide an initial report to the Facility Safety Officer or Contracting Officer Representative as soon as practical, but no more than two hours after any Moderate or Major Mishap, High Visibility Incidents, or any weight handling and hoisting equipment mishap. No Impact/Near-Miss and Minor Mishaps shall be reported within 24 hours or as soon as practical. |
| R47 | Conduct a mishap investigation for all Mishaps including mishaps resulting in at least $20,000 in damages without injury, to establish the root cause(s) of the mishap... Additionally, complete the VA Form 2162 (or equivalent) and provide the report to the Facility Safety Officer or Contracting Officer Representative within 7 calendar days of the accident. |
| R48 | A summation of all exposure-hours worked by the contractor and associated sub-contractors for each month will be reported to Facility Safety Officer or Contracting Officer Representative no later than the 10th day of the following month. |
| R49 | Contractor shall provide written certification that all contract employees assigned to the work site have had a pre-placement tuberculin screening within 90 days prior to assignment to the worksite and been found have negative TB screening reactions. |
| R50 | Smoking: Smoking is prohibited on all VA property. |
| R51 | All qualified persons performing electrical work under this contract shall be licensed journeyman or master electricians. All apprentice electricians performing under this contract shall be deemed unqualified persons unless they are working under the immediate supervision of a licensed electrician or master electrician. |
| R52 | The fall protection (FP) threshold height requirement is 4ft for ALL WORK in government occupied sites, unless the OSHA 29 CFR 1926 or EM 385-1-1 requirements are more stringent, to include steel erection activities, systems-engineered activities (prefabricated) metal buildings, residential (wood) construction and scaffolding work. |
| R53 | Establish and maintain an effective quality control (QC) system. that complies with the FAR Clause 52.246.12 titled “Inspection of Construction”. |
| R54 | The CQC system Manager is required to be a construction person with a minimum of 10 years in related work. This CQC System manager is on the site at all times during construction and is employed by the General Contractor. |
| R55 | In addition to the above experience and education requirements, the CQC System Manager and Alternate CQC System Manager are required to have completed the Construction Quality Management (CQM) for Construction course. If the CQC System Manager does not have a current specification, obtain the CQM for Contractors course identification within 90 days of award. |
| R56 | At least three phases of control are required to be conducted by the CQC System Manager for each definable feature of the construction work as follows: Preparatory Phase... Initial Phase... Follow-Up Phase... |
| R57 | The Government needs to be notified at least 48 hours or 2 business days in advance of beginning the Preparatory control phase. |
| R58 | The Government needs to be notified at least 48 hours or 2 business days in advance of beginning the initial phase for definable features of work. |
| R59 | Notify the Contracting Officer through the Resident Engineer office at least 14 days prior to the Final Acceptance Inspection and include the Contractor’s assurance that all specific items previously identified to the Contractor as being unacceptable, along with all remaining work performed under the contract, will be complete and acceptable by the date schedule for the Final Acceptance Inspection. |
| R60 | Furnish the original and one copy of these records in report form to the Government daily with 1 week after the date covered by the report, except that reports need not be submitted for days on which no work is performed. As a minimum, prepare and submit on report for every 7 days of no work and on the last day of a no work period. |
| R61 | Contractor shall develop and implement procedures to recycle construction and demolition waste to a minimum of 50 percent. |
| R62 | Prepare and submit to the COR a written demolition debris management plan. The plan shall include, but not be limited to, the following information: 1. Procedures to be used for debris management. 2. Techniques to be used to minimize waste generation. 3. Analysis of the estimated job site waste to be generated... 4. Detailed description of the Means/Methods to be used for material handling. |
| R63 | With each application for progress payment, submit a summary of construction and demolition debris diversion and disposal including beginning and ending dates of period covered. |
| R64 | Within 30 days after Preconstruction Meeting provide a narrative plan for complying with requirements stipulated within this section. Sustainability Action Plan must: a. Make reference to sustainable construction submittals defined by this section. b. Address all items listed under PERFORMANCE CRITERIA. c. Indicate individual(s) responsible for implementing the plan. |
| R65 | Within 30 days after Preconstruction Meeting provide a preliminary Low Pollutant-Emitting Materials Tracking Spreadsheet. |
| R66 | Not more than 30 days after Preconstruction Meeting provide a Construction IAQ Management Plan as an electronic file |
| R67 | Concurrent with each Application for Payment, submit a Sustainable Construction Progress Report to confirm adherence with Sustainability Action Plan. |
| R68 | Within 14 days after Substantial Completion provide the following: 1. Final version of Low Pollutant-Emitting Materials Tracking Spreadsheet. 2. Manufacturer’s cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for filtration media installed at return air grilles during construction... 3. Manufacturer’s cut sheets and product data highlighting the Minimum Efficiency Reporting Value (MERV) for final filtration media in air handling units. 4. Minimum 18 construction photographs... 5. Flush-out Documentation... |
| R69 | Within 30 days of contract award, the Contractor shall designate a specific individual as the Commissioning Manager (CxM) to manage and lead the commissioning effort on behalf of the Contractor. |
| R70 | Within 30 days of contract award, the Contractor shall ensure that each subcontractor designates specific individuals as Commissioning Representatives (CXR) to be responsible for commissioning related tasks. |
| R71 | The Contractor shall provide a minimum of 7 days’ notice to the Commissioning Agent and the VA regarding the completion schedule for the Pre-Functional Checklists and startup of all equipment and systems. |
| R72 | The Contractor shall submit the following information to the VA and the Commissioning Agent: 1. Instruction Program: Submit two copies of outline of instructional program for demonstration and training, including a schedule of proposed dates, times, length of instruction time, and instructors' names for each training module... At completion of training, submit two complete training manuals for VA's use. 2. Qualification Data... 3. Attendance Record... 4. Evaluations... 5. Demonstration and Training Recording... 6. Transcript... |
| R73 | Conductor ampacities specified or shown on the drawings are based on copper conductors, with the conduit and raceways sized per NEC. Aluminum conductors are prohibited. |
| R74 | The manufacturer shall regularly and currently produce, as one of the manufacturer's principal products, the materials and equipment specified for this project, and shall have manufactured the materials and equipment for at least three years. |
| R75 | Manufacturer's materials and equipment shall have been in satisfactory operation, on three installations of similar size and type as this project, for at least three years. |
| R76 | There shall be a permanent service organization maintained or trained by the manufacturer which will render satisfactory service to this installation within eight hours of receipt of notification that service is needed. Submit name and address of service organizations. |
| R77 | The Contractor shall notify the Government through the COR a minimum of thirty (30) days prior to the manufacturer’s performing of the factory tests. When factory tests are successful, contractor shall furnish four (4) copies of the equipment manufacturer’s certified test reports to the COR fourteen (14) days prior to shipment of the equipment, and not more than ninety (90) days after completion of the factory tests. |
| R78 | Grounding system resistance to ground shall not exceed 5 ohms. Make any modifications or additions to the grounding electrode system necessary for compliance without additional cost to the Government. Final tests shall ensure that this requirement is met. |
| R79 | Resistance of the grounding electrode system shall be measured using a four-terminal fall-of-potential method as defined in IEEE 81. Ground resistance measurements shall be made before the electrical distribution system is energized or connected to the electric utility company ground system, and shall be made in normally dry conditions not fewer than 48 hours after the last rainfall. |
| R80 | Install a printed schedule of circuits in each panelboard after approval by the COR. Schedules shall reflect final load descriptions, room numbers, and room names connected to each circuit breaker. Schedules shall be printed on the panelboard directory cards and be installed in the appropriate panelboards |
| R81 | Two weeks prior to the final inspection, furnish one complete set of spare fuses for each fused disconnect switch installed on the project. Deliver the spare fuses to the COR. |
| R82 | Provide the services of a factory-trained technician for one 2-hour training period for instructing personnel in the maintenance and operation of the SPD, on the date requested by the COR. |
| R83 | All facility backbone structured cabling shall be redundant and follow diverse path routing. |
| R84 | Copper (UTP) backbone cables shall meet the Category 6A performance requirements. Category 6A connectors are required. |
| R85 | Splicing of copper (UTP) cabling is prohibited. |
| R86 | Construction Clad Aluminum (CCA) cable is not permitted. |
| R87 | The Contractor or security sub-contractor shall be a licensed security Contractor with a minimum of five (5) years experience installing and servicing systems of similar scope and complexity. The Contractor shall be an authorized regional representative of the Security Management System’s (PACS) manufacturer. The Contractor shall provide four (4) current references from clients with systems of similar scope and complexity which became operational in the past three (3) years. |
| R88 | The Contractor shall provide proof project superintendent with BICSI Certified Commercial Installer Level 1, Level 2, or Technician to provide oversight of the project. |
| R89 | Cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry Consulting Service International. The staff member shall provide consistent oversight of the project cabling throughout design, layout, installation, termination and testing. |
| R90 | The Contractor shall have a local service facility. The facility shall be located within 60 miles of the project site. The local facility shall include sufficient spare parts inventory to support the service requirements associated with this contract. The facility shall also include appropriate diagnostic equipment to perform diagnostic procedures. |
| R91 | The Contractor shall, as a condition precedent to the final payment, execute a written guarantee (warranty) to the COR certifying all contract requirements have been completed according to the final specifications... The Contractor shall provide quarterly inspections during the warranty period. The contractor shall provide written documentation to the COR on conditions and findings of the system and device(s). In addition, the contractor shall provide written documentation of test results and stating what was done to correct any deficiencies. The first inspection shall occur 90 calendar days after the acceptance date. The last inspection shall occur 30 calendar days prior to the end of the warranty. |
| R92 | For catastrophic system failures, the Contractor shall provide same day four (4) hour service response with a defect correction time not to exceed eight (8) hours from arrival on site. Catastrophic system failures are defined as any system failure that the Owner determines will place the facility(s) at increased risk. For non-catastrophic failures, the Contractor within eight (8) hours with a defect correction time not to exceed 24 hours from notification. |
| R93 | The Contractor shall assemble the Security Test System at the Contractors local project within 50-miles of the project site, and perform tests to demonstrate the performance of the system complies with the contract requirements in accordance with the approved pre-delivery test procedures. |
| R94 | The Contractor shall test all security systems and equipment, and provide written proof of a 100% operational system before a date is established for the system acceptance test. |
| R95 | Phase I (Testing): The test shall be conducted 24 hours per day for 15 consecutive calendar days, including holidays, and the system shall operate as specified... Phase III (Testing): The test shall be conducted 24 hours per day for 15 consecutive calendar days, including holidays, and the system shall operate as specified. |
| R96 | Provide services of manufacturer’s technical representative for four hours to instruct VA personnel in operation and maintenance of units. |
Recent awards in NAICS 236220
The newest federal contract awards in the same industry code from Department of Veterans Affairs, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2027-02-15 | MONUMENT CONSTRUCTION SERVICES, LLCDepartment of Veterans Affairs · 402-26-REPAVE SOUTHGATE ROAD AT TOGUS VAMC. | $734,500 |
| 2027-02-05 | KOALA ROOFING LLCDepartment of Veterans Affairs · REPLACE ROOF POLICE BUILDING MARTINEZ CA VAMC | $124,659 |
| 2026-12-14 | ARMCORP CONSTRUCTION INCDepartment of Veterans Affairs · RENOVATE 6S FOR INPATIENT MENTAL HEALTH | $8.76 million |
| 2026-12-08 | LC FLUHARTY CONSTRUCTION LLCDepartment of Veterans Affairs · PROJECT 541-19-101 RENOVATE OPERATING ROOM - VAMC CLEVELAND EO 14398 | $14.85 million |
| 2026-12-01 | MONUMENT CONSTRUCTION SERVICES, LLCDepartment of Veterans Affairs · 523A4-27-003 EXTERIOR SITE IMPROVEMENTS | $318,296 |
| 2026-11-30 | KMK CONSTRUCTION, INCDepartment of Veterans Affairs · 631-26-012 TRANSFORMER REPLACEMENT. | $1.48 million |
Source: USAspending.gov, retrieved 2026-11-18. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.