Z1DA--Local | 460-26- 4-5074-0108 | 460-26-999 | Condenser Water Piping Modification | (VA-26-00077929): requirements and submission rules

45 requirements and 15 submission rules found in the solicitation documents for 36C24427B0003. Use them as the start of your compliance matrix.

Solicitation number
36C24427B0003
Agency
VETERANS AFFAIRS, DEPARTMENT OF / VETERANS AFFAIRS, DEPARTMENT OF / 244-NETWORK CONTRACT OFFICE 4 (36C244)
NAICS
236220
Set-aside
Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
Responses due
20 November 2026 (closed)
Official notice
View on SAM.gov

Submission rules that can disqualify a bid

  • VA Form 10101, Contractor Production Report, or a Contractor generated form containing the same type of information shall be signed, dated and submitted by the Contractor superintendent.
  • (g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
  • All offerors shall submit information pertaining to their past safety and environmental record.
  • (2) Costs as shown on this schedule must be true costs and the resident engineer may require the Contractor to submit the original estimate sheets or other information to substantiate the detailed makeup of the schedule.
  • (b)(1) Bidders shall acknowledge receipt of any amendment to this solicitation—
  • (2) Each payroll submitted must be accompanied by a "Statement of Compliance." signed by the Contractor or subcontractor or his or her agent who pays or supervises the payment of the persons employed under the contract and must certify—
  • Documentation of training shall be submitted to the Contracting Officer for review and approval prior to any work being performed.
  • The Offeror shall review the list of excluded parties in the System for Award Management (SAM) at https://www.sam.gov for entities excluded from receiving federal awards for “covered telecommunications equipment or services.”
  • (i) The Offeror shall search in SAM for the phrase “FASCSA order” for any covered article, or any products or services produced or provided by a source, if there is an applicable FASCSA order described in paragraph (e) of FAR 52.240-91, Security Prohibitions and Exclusions.
  • (ii) The Offeror shall review the solicitation for any FASCSA orders that are not in SAM but are effective and apply to the solicitation and resultant contract (see FAR 40.204-1(c)(2)).
  • (2) If a disclosure is required to be submitted to a contracting office, the offeror shall submit the disclosure as follows:
  • (i) If a Department of Defense contracting office, the offeror shall submit the disclosure to the website at https://dibnet.dod.mil.
  • (ii) For all other contracting offices, the Offeror shall submit the disclosure to the Contracting Officer.
  • (a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
  • (c) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.

Requirements

IDRequirement
R1RESPONSE DATE/TIME/ZONE | 11-20-2026 10:00 EASTERN TIME, NEW YORK, USA
R2FOR THE PURPOSE OF THIS SOLICITATION THE AWARD WILL BE MADE TO THE LOWEST PROPOSED, RESPONSIVE, AND RESPONSIBLE BIDDER WHOSE BID IS IN CONFORMANCE WITH THIS SOLICITATION.A.3
R3Construction Completion by: 30 days after NTPSection C (statement of work)
R4The Contractor shall provide all labor, transportation, materials, equipment, and supervision to modify the chiller plant Condenser Water Piping System as required at the Wilmington VA Healthcare System, located at 1601 Kirkwood HWY, Wilmington, Delaware 19805.Section L (instructions to offerors)
R5The project consists of: Freeze condenser water piping. Furnish and Install TWO 10 inch Butterfly Valves. Furnish and Install TWO 10 inch vertical check valves. Open Pump #2 and inspect internals. Re-install Pump #2 casing. Start Up and balancing both condenser water pumps.
R6All work to be performed in accordance with manufacturer's recommendations and guidelines.
R7All Federal and State Safety and Environmental guidelines shall be followed.Section C (statement of work)
R8Work will be conducted after normal business hours (7 am to 4pm) or on a Saturday (7am to 5pm).Section C (statement of work)
R9Prime Contractor to plan all phasing of work in coordination with Hospital staff in order to minimize down-time to areas affected by the project.Section C (statement of work)
R10Construction Waste Management, Specification 01 74 19 is to be included.Section C (statement of work)
R11Consolidate all necessary submittals by specification section on an excel spreadsheet. Checklist to be utilized to track/ monitor submittal process.Section C (statement of work)
R12Contractor will submit picture of affected area before, during, and after construction or testing.Section C (statement of work)
R13Contractor and Subcontractor to following specifications: 01 00 00 General Requirements, 01 42 19 Reference Standards, 01 74 19 Construction Waste Management, 23 05 11 Common Work Results For HVAC, 23 05 93 Test, Adjusting and balancing for HVACSection C (statement of work)
R14The Contractor shall make sure that subcontractor and employees have proper documentation to authorize personnel to work in the United States of America. The Contractor shall maintain the personnel, organization and administrative control necessary to ensure that the work delivered meets the contract specifications and requirements.Section C (statement of work)
R15The Contractor is required that all subcontractor or employees have been screen by the VAMC Wilmington Healthcare System. All personnel are required to wear a VA government furnished badge. All contractor and subcontractor are required to wear a government and company furnish badge while performing services under this contract. The badge will contain a personal picture, name of employee, and Contractor's name. Badges shall be worn on the outer garment attached to the outer shirt or jacket pocket by a button or clip or worn around the neck secured by an appropriate identification card lanyard.Section C (statement of work)
R16Government issued identification badge remains the property of the Government and shall be returned to the issuing office or other designated Government personnel upon transfer of Contractor employees from the contract.Section C (statement of work)
R17The contractor shall ensure that employee or subcontractor have valid driver license when driving a vehicle on property.Section C (statement of work)
R18The Contractor must protect against the destruction and/or misplacement of all information produced under this contract, unless directed under local policy to destroy. This includes both hard and soft copies of data.Section C (statement of work)
R19The Contractor shall not release any information (including photographs, files, public announcements, statements, denials, or confirmations) on any part of the subject matter of this contract or any phase of any program hereunder without the prior written approval of the COR.Section C (statement of work)
R20Contractor personnel are not authorized to carry or possess personal weapons to include, but not limited to, firearms and knives with a blade length in excess of three inches, while assigned under this contract.Section C (statement of work)
R21The Contractor shall comply with all applicable federal, state and local laws and ensure performance is secure while protecting material, equipment, and supplies from damage and loss. The Contractor shall ensure that employees or subcontractor have the proper PPE for the job.Section C (statement of work)
R22Contractor shall provide a supervisor who speaks English on site at all time.Section C (statement of work)
R23Appropriate safety equipment shall be furnished by the Contractor to contractor personnel or subcontractor and shall be used as prescribed by OSHA Standards.Section C (statement of work)
R24Upon request, resume shall be provided to the Contracting Office prior to clearance approval, for review and acceptance by the COR.Section C (statement of work)
R25The Contractor shall immediately report all damages to the COR and shall provide the Contracting Officer (CO) and COR, a written report, within 24 hrs. The report shall include: What occurred, who was involved, when it occurred (Time/Date), where did it occurred, why it occurred, how it occurred, and the proposed means to repair or replace.Section C (statement of work)
R26Contractor is to maintain free and unobstructed access to facility emergency services and for fire, police and other emergency response forces in accordance with NFPA 241.Section C (statement of work)
R27All keys provided the Contractor or any subcontractor for use during the project shall be returned to the COR at completion of the work or upon request. No keys shall be reproduced by the Contractor or any subcontractor.Section L (instructions to offerors)
R28Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker's compensation insurance rating bureau.Section L (instructions to offerors)
R29As required by the statutory requirement pertaining to the Veterans Benefits Act of 2003 (15 U.S.C. 657f) and in accordance with FAR 6.206, this procurement will be set-aside for Veteran Owned Small Business (VOSB) concerns. Only VOSB concerns who are verified in the Vendor Information Page (VETBIZ) and registered in System for Award Management (SAM.gov) will be eligible to submit proposals.Section L (instructions to offerors)
R30Prior to any excavating, contractor shall be required to make sure that the location of all underground utilities in excavation sites is accurately designated. Contractor shall be responsible for all costs related to identification of underground utilities. Contractor shall provide a comprehensive report on all underground utilities, which must include survey ground marks laid out and an illustration of jobsite showing underground utilities. The Utility Location & Coordination Uniform Color Code shall be used for the ground marks and illustrations.Section L (instructions to offerors)
R31The Contractor shall be responsible for the correct title classification of workers and compliance with all applicable wage and hour laws.Section L (instructions to offerors)
R32Contractors shall meet at 1601 Kirkwood Hwy, Wilmington, DE 19805 Building 10 at 11:30am on 10/28/2026Section L (instructions to offerors)
R33Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB.Section L (instructions to offerors)
R34The Contractor will not engage in any racially discriminatory DEI activities; The Contractor will furnish all information and reports, including providing access to books, records, and accounts, as required by the Contracting Officer, for purposes of ascertaining compliance with this clause... The Contractor must include the substance of this clause, including this paragraph (c), in subcontracts at any tier, including those for commercial products and commercial services, except those where the place of delivery or performance is outside the United States.Section L (instructions to offerors)
R35All laborers and mechanics employed or working upon the site of the work will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account... the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of LaborSection L (instructions to offerors)
R36Within 14 days after award of the contract, the Contractor must deliver to the Contracting Officer a completed Standard Form (SF) 1413 Statement and Acknowledgment, for each subcontract for construction within the United States, including the subcontractor's signed and dated acknowledgment that the clauses set forth in paragraph (b) of this clause have been included in the subcontract.Section L (instructions to offerors)
R37The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.Section L (instructions to offerors)
R38Within five days after the work commences on the contract or another period of time determined by the Contracting Officer, the Contractor shall prepare and submit to the Contracting Officer for approval a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the work (including acquiring materials, plant, and equipment).Section L (instructions to offerors)
R39The Contractor shall not make reference in its commercial advertising to Department of Veterans Affairs contracts in a manner that states or implies the Department of Veterans Affairs approves or endorses the Contractor's products or services or considers the Contractor's products or services superior to other products or services.Section L (instructions to offerors)
R40In order for a concern to submit an offer and be eligible for the award of an SDVOSB set-aside or sole source contract, the concern must qualify as a small business concern under the size standard corresponding to the NAICS code assigned to the contract and be listed as an SDVOSB participant in the SBA certification database as set forth in 13 CFR 128. Offers received from entities that are not certified SDVOSBs and listed in the SBA certification database at the time of offer shall not be considered.Section L (instructions to offerors)
R41In the case of a contract for general construction, the SDVOSB prime contractor will not pay more than 85% of the amount paid by the government to the prime for contract performance, excluding the cost of materials, to firms that are not certified SDVOSBs listed in the SBA certification database.Section L (instructions to offerors)
R42The formal certification must be completed, signed and returned with the offeror's bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.Section L (instructions to offerors)
R43The Contractor shall submit a schedule of cost to the Contracting Officer for approval within 30 calendar days after date of receipt of notice to proceed. Such schedule will be signed and submitted in triplicate.Section L (instructions to offerors)
R44Except as provided in paragraph (e) of this clause, the contractor shall submit payment requests in electronic form.Section L (instructions to offerors)
R45Six complete composite drawings or six complete sets of separate reproducible drawings shall be received by the Government not less than 20 days prior to the scheduled start of the work in the area illustrated by the drawings, for the purpose of showing the Contractor's planned methods of installation.Section L (instructions to offerors)

Recent awards in NAICS 236220

The newest federal contract awards in the same industry code from Department of Veterans Affairs, since 1 October 2024. Use them to see who wins this kind of work and at what value.

StartAwardee and buyerAward value
2026-12-08LC FLUHARTY CONSTRUCTION LLCDepartment of Veterans Affairs · PROJECT 541-19-101 RENOVATE OPERATING ROOM - VAMC CLEVELAND EO 14398$14.85 million
2026-11-30HIRT ELECTRIC, LLCDepartment of Veterans Affairs · HQ GUIDANCE - COMMERCIAL CLAUSES FOR OPEN MARKET CONSTRUCTION & A/E$244,400
2026-11-23U.S. VET GENERAL CONTRACTING, LLCDepartment of Veterans Affairs · TASK ORDER #13 FOR 3YR PMI UNDER THE CONSTRUCTION MULTIPLE AWARD TASK ORDER CONTRACT (MATOC) FOR THE WM S. MIDDLETON VA HOSPITAL, MADISON WISCONSIN.$2.15 million
2026-11-16BRICAN, INC.Department of Veterans Affairs · 631-26-010 ABATE AND UPGRADE BUILDING 1 COMMON AREA.$2.55 million
2026-11-13PARAMOUNT CONSTRUCTION GROUP, LLCDepartment of Veterans Affairs · 586-25-101 | DB SITE PREP IR$4.88 million
2026-11-04KMK CONSTRUCTION, INCDepartment of Veterans Affairs · 631-18-002 UPGRADE ELECTRICAL PHASE 2 PART 3:$10.34 million

Source: USAspending.gov, retrieved 2026-10-24. Award value is the obligated amount reported by the agency.

Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.

Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.

Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.

Get new solicitations that match your business, free

Enter NAICS codes, keywords or both. No email when nothing matches. Unsubscribe in one click.