24 requirements and 9 submission rules found in the solicitation documents for 19JM3727Q0002. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- (b) These schedules shall include the time by which shop drawings, product data, samples and other submittals required by the contr act will be submitted for approval.
- CONTRACTOR'S SUBMISSION OF CONSTRUCTION SCHEDULES (a) The time for submission of the schedules referenced in FAR 52.236 -15, "Schedules for Construction Contracts", paragraph (a), is hereby modified to reflect the due date for submission as five (5) days calendar days after receipt of an executed contract".
- The Contractor shall submit both the information and the guarantee or warranty to the Government in sufficient time to permit the Government to meet any time limit specified in the guarantee or warranty, but not later than completion and acceptance of all work under this contract.
- (b) All offerors must submit the information required in paragraphs (d) through (f) of this provision in order to comply with debt collection requirements of 31 U.S.C.
- The SSHP shall be submitted at least 20 working days prior to commencing any activity at the site.
- G.4.3 The Contractor shall submit proper documentation and evidence satisfactory to the Contracting Officer of compliance with this clause.
- (3) The offeror shall provide proof of SAM registration to include the SAM UEI number (4) Be able to demonstrate prior construction experience with suitable references.
- FAR Clause # Title Date Change ________________________ Any changes provided by the offeror are applicable to this solicitation only, and do not result in an update to the representations and certifications posted on SAM.
- The Offeror shall review the list of excluded parties in the System for Award Management (SAM) ( https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services".
Requirements
| ID | Requirement |
|---|---|
| R1 | OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 |
| R2 | The Contractor shall not include a line for VAT on Invoices as the U.S. Embassy has a tax exemption certificate with the host government.A.1 |
| R3 | The Contractor is responsible for reviewing and understanding all drawings, specifications, and requirements prior to bidding and starting work. If the Contractor identifies any errors, omissions, or inconsistencies in the drawings or documents, the Contractor shall immediately notify the Contracting Officer’s Representative (COR) in writing.Section B |
| R4 | Contractor must present appropriate licenses or permits in their bidding package.Section B |
| R5 | The Offeror shall include Defense Base Act (DBA) insurance premium costs covering employees.Section J |
| R6 | Be able to understand written and spoken English.Section J |
| R7 | Have an established business with a permanent address and telephone listing in Jamaica or plans to establish an office within 30 days of contract award.Section J |
| R8 | Have the necessary personnel, equipment and financial resources available to perform the work.Section J |
| R9 | Have all licenses and permits required by local law.Section J |
| R10 | Meet all local insurance requirements.Section J |
| R11 | Have the ability to obtain or to post adequate performance security, such as bonds, irrevocable letters of credit or guarantees issued by a reputable financial institution.Section J |
| R12 | Have no adverse criminal recordSection J |
| R13 | Have no political or business affiliation which could be considered contrary to the interests of the United States.Section J |
| R14 | The Offeror/Quoter shall identify and explain/justify any deviations, exceptions, or conditional assumptions taken with respect to any of the instructions or requirements of this request for quotation in the appropriate volume of the offer.Section J |
| R15 | Present the performance schedule in the form of a "bar chart" indicating when the various portions of the work will be commenced and completed within the required schedule. This bar chart shall be in sufficient detail to clearly show each segregable portion of work and its planned commencement and completion date.Section J |
| R16 | Proposed Work Information - Provide the following: (1) A list of the names addresses and telephone numbers of the owners, partners, and principal officers of the Offeror. (2) The name and address of the Offeror's field superintendent for this project. (3) A list of the names, addresses, and telephone numbers of subcontractors and principal materials suppliers to be used on the project, indicating what portions of the work will be performed by themSection J |
| R17 | Experience and Past Performance - List all contracts and subcontracts your company has held over the past three years for the same or similar work. Provide the following information for each contract and subcontract: (1) Customer's name, address, and telephone numbers of customer's lead contract and technical personnel. (2) Contract number and type. (3) Date of the contract award place(s) of performance, and completion dates; Contract dollar value. (4) Brief description of the work, including responsibilities; and (5) Any litigation currently in process or occurring within last 5 years.Section J |
| R18 | Offeror interested in attending must email kingstonquotes@state.gov with the caption ‘TRENCHING - SITE VISIT’. To ensure access you are required to be approved prior to the visit. You are to provide the full names of the attendees, the vehicle information to include make, model, color and plate number of the vehicle being driven. The email must be sent no later than Wednesday, November 04, 2026 by 2 pm.Section J |
| R19 | All attendees must take along a valid picture ID (driver’s license or passport). The following items will not be allowed on site: firearms and or any other form of weapons, electronic devices, cameras and umbrellas.Section J |
| R20 | The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this sectionSection L (instructions to offerors) |
| R21 | The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.Section L (instructions to offerors) |
| R22 | Representations. (1) The Offeror represents that it [ ] does, [ ] does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument. (2) After conducting a reasonable inquiry for purposes of this representation, the Offeror represents that it [ ] does, [ ] does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.Section L (instructions to offerors) |
| R23 | Representation. The Offeror represents that. (1) It □ is, □ is not an inverted domestic corporation; and (2) It □ is, □ is not a subsidiary of an inverted domestic corporation.Section L (instructions to offerors) |
| R24 | By submission of its offer, the offeror certifies that it does not conduct any restricted business operations in Sudan.L.6 |
Recent awards in NAICS 238910
The newest federal contract awards in the same industry code from Department of State, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2026-10-20 | MISCELLANEOUS FOREIGN AWARDEESDepartment of State · ESO-LCP AS PART OF UPCOMING TSU PROJECT | $25,946 |
| 2026-09-22 | MISCELLANEOUS FOREIGN AWARDEESDepartment of State · GENERATOR CONCRETE PAD (BUKIEN RESIDENCE) | $19,930 |
| 2026-08-27 | MISCELLANEOUS FOREIGN AWARDEESDepartment of State · TSU - TRENCHING WORKS AT THE EMBASSY | $95,712 |
| 2026-07-28 | MISCELLANEOUS FOREIGN AWARDEESDepartment of State · DELISH KITCHEN RETAIL FAIR PROMOTION | $35,719 |
| 2026-07-23 | MISCELLANEOUS FOREIGN AWARDEESDepartment of State · FABEX KANSAI 2026 | $46,091 |
| 2026-07-22 | MISCELLANEOUS FOREIGN AWARDEESDepartment of State · FOOD STYLE KYUSHU - SITE MANAGEMENT | $17,742 |
Source: USAspending.gov, retrieved 2026-10-29. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.