Solicitation - Residential Reentry Center (RRC) Services, Home Confinement (HC) Services - Collin County Texas: requirements and submission rules
57 requirements and 7 submission rules found in the solicitation documents for 15BRRC27R00000005. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- The authorized negotiator's response is due no later than five calendar days after receipt of the report.
- Subsequent updates shall be submitted to the RRM within 30 days of publication.
- The PREA coordinator must be designated in writing and submitted to the BOP prior to the contract performance date.
- In cases where local and/or state laws or ordinances do not allow for placement of a specific type of referral, the contractor will submit written justification to the RRM who will determine if the justification is in compliance with the technical proposal.
- Shall be submitted on a monthly basis by the 10 th of each month.
- Laboratory-Based Testing/Screening Procedures a) Adulteration: All laboratory-based screening specimens, including special testing requests, submitted by an RRC contractor shall be automatically screened for adulteration, substitution, and dilution using DHHS certified laboratory procedures for measuring specific gravity, creatine, and pH.
- The contractor will submit a completed and signed Request for Contract Staff Background Investigation, Attachment A, (must be typed) for all individuals the contractor has determined are appropriate for employment and any person who will work with federal residents.
Requirements
| ID | Requirement |
|---|---|
| R1 | As part of their evaluation, the BOP requires offerors to identify client references and request their participation in the past performance review process. |
| R2 | At least annually, staff shall review the operations manual and document the review. |
| R3 | The plan shall be submitted to the COR for approval, prior to performance and must contain the following, at a minimum: A. A detailed evacuation plan; B. A detailed shelter-in-place plan, to include provisions for food, water, power, etc.; C. Provisions for maintaining adequate staffing levels; D. A detailed pandemic plan, to include provisions for quarantine/isolation areas, adequate PPE supplies, etc. |
| R4 | The contractor will provide at least 70 percent of the contract requirements by using employees compensated directly by the contractor. Thus, the contractor cannot subcontract more than 30 percent of the contract requirements. |
| R5 | Use of this application and all subsequent versions or additions to the application is mandatory within 30 days of implementation. |
| R6 | The contractor must provide written policy and procedures that offer ongoing, positive communication and partnerships between the facility, major employers who employ RRC residents in the local community, appropriate social service agencies, legal services organizations, elected officials, law enforcement, and citizens. |
| R7 | The program must describe the approach to educating the local community about the goals and mission of the RRC and maintaining the support of the community. The outreach program must also include specific activities that will be conducted on a quarterly basis. |
| R8 | This staff coverage shall provide for the safe and secure supervision of all federal residents. |
| R9 | The contractor must identify key staff by title, educational/experience requirement, and major duties within their technical proposal. |
| R10 | Clearance must be obtained from RRM prior to working with federal residents. |
| R11 | However, in cases where these positions will be shared, the contractor must receive approval by the Contracting Officer. The technical proposal must identify the percentage of time that will be devoted to the federal contract. |
| R12 | The RRM must approve any staff member prior to employment in a key personnel position. |
| R13 | The Case Manager ratio will be a minimum of one for every 30 residents. The ratio must be adequate to perform the tasks associated with the position and commensurate with the resident workload of the population without being utilized to perform duties assigned to other positions. |
| R14 | Housing configurations must also be taken into consideration (e.g., several buildings would require the contractor to determine the number of staff needed to safely and securely supervise the federal residents). |
| R15 | All personnel files must be secured and accessible to senior management staff only; hard copy personnel files must be stored in a locked compartment accessible to senior management staff only. |
| R16 | Prior to working with federal residents, all staff must receive training on their respective duties and responsibilities. This training should cover all required training topics as outlined in the SOW and should be a minimum of 40 hours in length. |
| R17 | The training must cover the following: • Discipline procedures for residents; • Demonstrate working knowledge and competency of the discipline procedures by passing the standardized test administered by the COR; • Emergency plans (to include pandemic operations); • Staff integrity and ethics; • Accountability and security procedures; • Life safety and emergency procedures; • Resident, vehicle, locker, and facility searches; • Signs of suicide and suicide precautions (to include review of the RRC’s Suicide Prevention Plan); • Use of force regulations and tactics; • Center Disciplinary Committee report writing; • Universal precautions; • Interpersonal relations and communication skills; • Social and cultural life styles of the resident population; • Basic first aid; • Familiarization with Reentry Resources available nationally and in local area (e.g., housing, employment, social services); • Communication skills; • Individualized Program Planning; • Prevention, identification, and handling of sexual abuse/assault incidents; and • Prison Rape Elimination Act Requirements. |
| R18 | Contractors who have a contract which exceeds five years must ensure all staff receive updated clearances every five years. |
| R19 | All volunteers who provide services in the RRC, at a minimum, must undergo a criminal history check prior to working with federal residents. For a volunteer to provide one-on-one counseling or work with small groups of residents (three or less), the volunteer must undergo a full criminal history check and fingerprinting. |
| R20 | This roster must include the employee’s complete name, title, full or part-time status, and the date they began working with federal residents. |
| R21 | The architectural floor plans, drawn to scale by a computer aided drafting design program (no hand drawn and/or handwritten plan or matrix will be accepted) shall be legible and denote all required elements described below: Room identification indicating what the room is used for and room number to include separate sleeping, bathing, and toilet areas by gender (i.e. office, closet, mechanical, dorm). Furniture layout including maximum allowable beds in sleeping rooms. Beds shall be easily identifiable if the bed is a single or bunk bed. Location and number of sinks, toilets, and showers, • Location and number of washers and dryers, • Means of egress elements shall be easily identified (i.e. ramps, stairs, doors etc.). • The proposal shall be in compliance with all of the requirements of the Architectural Barriers Act (ABA). This includes identifying required floor space clearances for accessible routes, toilets, showers, sleeping rooms, and compliant wash basins areas on the architectural floor plans. • A matrix table showing actual interior square footage of meeting rooms, cafeteria, dayrooms, and sleeping rooms. • A matrix table detailing furniture sizes and calculations to ensure a minimum of 25 continuous square feet of unencumbered space per occupant in the sleeping rooms • Identification of sleeping rooms/dorms to be used for BOP male and female residents and which rooms will NOT accommodate the required 25 continuous square feet of unencumbered space for BOP residents. • If any renovations/additions are planned, provide "as built" architectural drawing(s) and proposed architectural drawings depicting renovations. • The contractor will indicate separate sleeping, bathing, and toilet areas by gender on the architectural floor plans and will have a written plan outlining procedures to maintain separation by gender. • Identified location(s) for quarantine isolation areas in accordance with the pandemic plan. |
| R22 | The contractor must provide, at no cost to the resident, transportation, or public transportation vouchers, for all residents (who lack personal transportation) to seek employment, and participate in recommended program activities until such time as the resident obtains his/her first paycheck from employment, no longer meets the definition of indigent, or is able to provide for their own transportation. Upon arrival at the RRC, all residents must be provided with maps of local public transportation options. |
| R23 | The staff member must be licensed and insured in accordance with state laws. When issuing transportation passes to residents, the contractor must factor in the distance to/from public transportation and travel time into the pass time allotted. |
| R24 | Thermostats shall be programed so the fans are continuously running for sleeping areas for continual air flow. Fresh air and filtration requirements shall also be ensured. Inspections must be completed no more than nine months prior to the Pre-Occupancy Safety Inspection. |
| R25 | Beds and chairs shall accommodate the weight of the resident. |
| R26 | If the dining room cannot accommodate the entire proposed population, the contractor must provide a dining schedule for approval by the RRM. |
| R27 | All contracts providing services to the Federal Government must meet the Architectural Barriers Act of 1968 (ABA), which requires that certain buildings owned, occupied, leased or financed by the Federal Government be designed, constructed or renovated so as to be accessible to, and useable by people with physical disabilities. |
| R28 | The contractor may designate smoking areas outside the contract facility 10 to 25 feet away from all entrances and exits, and must be in compliance with all local restrictions or ordinances. |
| R29 | An adequate number of telephones shall be accessible to all residents, 24 hours a day, 7 days a week. |
| R30 | Any structure used to house federal residents must meet specific fire and safety standards before it can be approved by the BOP. |
| R31 | The certified third-party inspector must, at minimum, possess the most recent NFPA 101 Life Safety Code certification. A copy of the certification and/or licensure of the certified contractor performing the NFPA 101 Life Safety inspection will be attached to the report. |
| R32 | Inspections must be completed no more than nine months prior to the Pre-Occupancy Safety Inspection. |
| R33 | Staff shall immediately notify the fire department by telephone for emergency response teams regardless of fire alarm system configuration or automatic dialer. (911) |
| R34 | Floor evacuation diagrams shall reflect floor arrangement and be properly oriented. |
| R35 | All buildings used to house federal residents must be equipped with an automatic fire detection and alarm system designed, installed, tested, and maintained in accordance with the NFPA. The system design must incorporate hard-wired smoke detectors in all sleeping rooms, corridors, and common areas. The alarm system must be hard-wired into an annunciator panel and located at a central control point under 24-hour staff supervision. |
| R36 | Buildings used to house federal residents must be equipped with an adequate number of portable fire extinguishers that are sized, located, installed, tested, and maintained in accordance with NFPA. At least one extinguisher must be provided on each level of the building. |
| R37 | Mattress must be of proper size and fit for the beds/bunks they are being used for. All mattresses mattress pads, and pillows throughout the facility will meet the Flammability Standard DOC-FF-472, Federal Flammability Standard 16 CFR §1632 or 16 CFR 1633 and BOP policy. The contractor will maintain documented compliance of this requirement. Damaged, torn, cracked, or ripped mattresses, mattress pads, or pillows must be replaced. |
| R38 | These emergency lights shall be tested on a monthly basis for a minimum of thirty seconds (logged, visual test, not exceeding 30 days between tests) and on an annual basis for an hour and a half with a final reading of at least 0.06 foot candle (logged, functional test). The contractor must maintain a log documenting the testing of emergency lights. |
| R39 | The outside of the electrical panel box must contain either a numeric or alpha indicator near the top of the panel to identify the different boxes in a room. |
| R40 | Permissible, temporary extension cords must have surge protectors. |
| R41 | Wiring and receptacles must be grounded. |
| R42 | Damaged plate covers, switches, and outlets must be replaced. |
| R43 | An Electrical Maintenance Program (EPM) shall be established. The EMP shall establish procedures and intervals for the servicing, inspection, and testing of the requirements of Chapter 6. |
| R44 | All secondary containers in the RRC shall have a label with the following information: Product Identifier (Name of the Chemical); Signal words (Danger or Warning or None, depending on the Hazards of the Chemical); Pictograms (Nine different pictures that Display Specific Hazards); Hazard Statements (Physical, Health or Environment Hazards); Precautionary Statements (General, Prevention, Response, Storage & Disposal); and Company Information (Manufacturer and/ or Distributor Information). |
| R45 | Control and accountability of pesticides and rodenticides are mandatory. |
| R46 | If the contractor subcontracts an outside pest control company to perform pest control services for the facility, the pest control company must provide SDS forms for all pesticides to be applied at the facility. In addition, after the application, the pest control company must inform the RRC in writing regarding what pesticide was applied and the amount used. |
| R47 | If the placement date is within the next 30 days, the contractor must respond within two working days. If the placement date is more than 30 days from the date the referral is received, the contractor must respond within five working days. If the requested acceptance date is not granted, a written justification must be provided to the RRM. |
| R48 | If the reporting date differs from the date in the referral packet, the contractor must obtain concurrence from the RRM before notifying the referring source of the acceptance. |
| R49 | If after screening the resident is determined to be at risk of victimization or abusiveness, the RRM must be contacted to refer the resident for Community Treatment Services. |
| R50 | Notifications must include full name, register number, and the time/date of arrival/transfer/release. All releases will also include the complete release address. |
| R51 | In these cases, the contractor must verify the reason and notify the RRM immediately that the resident has arrived and reason he/she did not arrive by the designated time. |
| R52 | Staff must execute the certified Orders, and return one to the RRM and one to the U.S. Marshal (USM) of the sentencing district. |
| R53 | Each resident must sign the BOP form Community Based Program Agreement. |
| R54 | Strict accountability of DNA numbers must be maintained to ensure that proper/assigned numbers are provided with the correct resident DNA sample. |
| R55 | The contractor shall utilize electronic monitoring equipment to ensure accountability of all inmates on home confinement. |
| R56 | Contractors must develop procedures and policies that allow for the possession and routine use of cell phones, to include smartphones by residents. Such policies and procedures must take into account residents’ important needs to interact with potential employers, educators, family, friends, and other members of the community. Contractors must allow for residents to retain and utilize their cell phone devices at all times, absent court order to the contrary. |
| R57 | The laboratory must comply with all specifications contained herein and all applicable local, state, and federal law, as indicated in 42 CFR Part 493, Laboratory Requirements, to engage in urine drug testing for federal residents. |
Recent awards in NAICS 623990
The newest federal contract awards in the same industry code from Department of Justice, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2027-04-01 | DISMAS CHARITIES INCFederal Prison System / Bureau of Prisons · TO PROVIDE RESIDENTIAL REENTRY CENTER (RRC) SERVICES AND HOME CONFINEMENT (HC) SERVICES LOCATED IN ROANOKE, VIRGINIA. HOME CONFINEMENT RADIUS IS WITHIN 100 MILES OF THE RRC FACILITY. | $1.98 million |
| 2027-03-01 | CORECIVIC, INC.Federal Prison System / Bureau of Prisons · TO PROVIDE RESIDENTIAL REENTRY CENTER (RRC) SERVICES AND HOME CONFINEMENT (HC) SERVICES LOCATED IN SAN DIEGO COUNTY, CALIFORNIA. HOME CONFINEMENT RADIUS IS WITHIN 100 MILES OF THE RRC FACILITY. | $16.02 million |
| 2027-03-01 | CITY OF FAITH PRISON MINISTRIESFederal Prison System / Bureau of Prisons · TO PROVIDE RESIDENTIAL REENTRY CENTER (RRC) SERVICES AND HOME CONFINEMENT (HC) SERVICES LOCATED IN TULSA COUNTY, OKLAHOMA. HOME CONFINEMENT RADIUS IS WITHIN 100 MILES OF THE RRC FACILITY. CDA-6ZA CITY | $1.42 million |
| 2027-02-01 | DISMAS CHARITIES INCFederal Prison System / Bureau of Prisons · TO PROVIDED RESIDENTIAL REENTRY CENTER LOCATED WITHIN ONE OF THE FOLLOWING KENTUCKY COUNTIES: CLAY, JACKSON, LAUREL, OWSLEY, PERRY, LESLIE, KNOX. HOME CONFINEMENT RADIUS: WITHIN 200 MILES OF THE FACIL | $1.21 million |
| 2027-02-01 | TURNING POINT OF CENTRAL CALIFORNIA INCFederal Prison System / Bureau of Prisons · RESIDENTIAL REENTRY CENTER (RRC) SERVICES LOCATED WITHIN THE EASTERN DISTRICT OF CALIFORNIA. HOME CONFINEMENT RADIUS IS WITHIN 100-MILE OF THE RRC FACILITY. OBLIGATE FUNDS. | $1.31 million |
| 2027-02-01 | RENEWAL INCFederal Prison System / Bureau of Prisons · RESIDENTIAL REENTRY CENTER (RRC) SERVICES LOCATED WITHIN ALLEGHENY COUNTY, PENNSYLVANIA. HOME CONFINEMENT RADIUS WITHIN 150 MILES OF THE RRC FACILITY IN REF RFP 15BRRC25R00000013. | $1.88 million |
Source: USAspending.gov, retrieved 2026-11-13. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.