Bushy Knoll Pit Crush & Stockpile: requirements and submission rules
43 requirements and 2 submission rules found in the solicitation documents for 127EAX27Q0017. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Submittals requiring Forest Service approval shall be submitted according to timelines specified to allow adequate review time.
- Submit a plan of operation according to Section 105.02.
Requirements
| ID | Requirement |
|---|---|
| R1 | The Contractor shall be responsible to obtain all permits as required by Arizona Department of Environmental Quality (ADEQ) for the Contractor’s methods of operation(s).Section C (statement of work) |
| R2 | The Contractor shall furnish labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.Section C (statement of work) |
| R3 | The contractor will remove the overburden, create a staging area, and utilize existing materials for barriers for the safety of the operation within the designated NEPA boundary.Section C (statement of work) |
| R4 | The period of performance for this project is 6/1/26-09/30/27. Contract time is 180 days.Section C (statement of work) |
| R5 | No changes to the specifications, terms, or conditions of this statement of work shall be made without the prior written approval of the Contracting Officer.Section C (statement of work) |
| R6 | The Forest Service Supplemental Specifications (FSSS) shall be incorporated in the FP-24. The applicable specifications for the project will be the FP-24 as modified by the FSSS.Section C (statement of work) |
| R7 | The right to use and process material found in the work excludes the use and processing of material for nongovernment contract work, except for the disposal of waste material. Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material at government-approved agreed to location(s), at no additional cost to government.Section C (statement of work) |
| R8 | If there is evidence that a quantity specific as a contract quantity is incorrect by 15% or more, submit calculations, drawings, or other evidence indicating why the quantity is in error and request in writing that the quantity be adjusted.Section C (statement of work) |
| R9 | Provide a construction schedule showing all major activities start and end dates for completion the period of performance for the contract.Section C (statement of work) |
| R10 | Provide a traffic control supervisor (TCS) with at least 1 year of experience supervising traffic control.Section C (statement of work) |
| R11 | When the roadway is open to public traffic, perform the following: Limit construction-caused delays to public traffic to no more than 30 minutes per passage through the project. Operate equipment in the direction of traffic, where practical. Provide minimum lane widths of 10 feet where practicable. Use barricades, drums, or other approved devices to delineate traffic lanes through areas where the edge of pavement or intended path has been obliterated by construction operations. Notify and coordinate with the oversize load permitting authority for lane width limitations before reducing lane width or closing roadway shoulders. Locate staging areas outside the clear zone or behind approved traffic barriers. Obtain approval of the location and access to staging areas. Store unused traffic control devices at staging areas. Park equipment outside of the clear zone or behind approved traffic barriers. Provide parking areas for employee’s personal vehicles in approved areas. Provide uninterrupted two-way communications between flaggers and between flaggers and pilot cars unless flaggers can see each other and communicate. Citizen band radios are unacceptable. Make communication devices available to the CO as necessary or if requested. Maintain existing guardrails, barriers, and bridge railings until removal is necessary for construction. Use a temporary barrier or appropriate channelizing devices while the guardrails and bridge rails are absent. Install permanent barriers, guardrails, and bridge rails as soon as possible.Section C (statement of work) |
| R12 | Maintain traffic control devices during closure period(s).Section C (statement of work) |
| R13 | In areas outside the excavation, embankment, and slope rounding limits, cut stumps to maximum stump height shown in table below. Fall and buck the merchantable material at lengths longer than the minimum lengths listed, or in multiples thereof (i.e. 8 ft, 16 ft, 24 ft, 32 ft), not to exceed 16 feet in length to allow for transportation of the material. Merchantable timber shall be decked at designated location(s).Section C (statement of work) |
| R14 | Merchantable timber is Government property. Dispose of clearing and grubbing debris according to Subsection 203.07.Section C (statement of work) |
| R15 | Dispose of unsuitable and excess material according to the specified method(s) as follows: (a) Windrowing Construction Slash... (b) Scattering... (c) Chipping... (d) Debris Mat... (e) Decking. Remove brush from designated log deck areas. Limb and top logs. Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than 10 feet and decked in designated log deck location. Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c). Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil. (f) Removal to designated locations... (g) Piling...Section C (statement of work) |
| R16 | For projects in National Forest Service lands, comply with Forest Service Manual (FSM) 7190, Explosives and Blasting Materials.Section C (statement of work) |
| R17 | Notify the owners of nearby utilities at least 24 hours before blasting.Section C (statement of work) |
| R18 | Limit blasting induced vibrations in saturated soils or on steep slopes as designated or as directed by the CO.Section C (statement of work) |
| R19 | Test blast at all new sources, when rock type changes, and when blast layout changes due to slope or other changes.Section C (statement of work) |
| R20 | Use explosives and detonators within the manufacturer’s recommended shelf life.Section C (statement of work) |
| R21 | Mitigate uncontrolled gas pressure loss during blasting and excessive blast noise by using appropriate (as determined by CO) stemming materials and practices.Section C (statement of work) |
| R22 | Delete Subsection 703.09(e) Chip Seal Aggregate and Replace with the following: (e) Los Angeles abrasion, AASHTO T 96 30 percent maximum.Section C (statement of work) |
| R23 | General. Provide hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming to the following: Gradation Table 703-1; Los Angeles abrasion, AASHTO T 96 35 % maximum; Soundness of aggregate using sodium sulfate AASHTO T 104, 5 cycles: Coarse aggregate 12 % loss maximum, Fine aggregate 12 % loss maximum; Durability index (coarse), AASHTO T 210 35 minimum; Durability index (fine), AASHTO T 210 35 minimum; Fractured faces, AASHTO T 335 (one or more) 75 % minimum; Without organic matter and lumps or balls of clay; Liquid limit, AASHTO R 58 and T 89, Method A 35 maximum. Statistical procedures do not apply.Section C (statement of work) |
| R24 | Surface Course Gradation R3-G and Plasticity Index Limits: 1 inch (100% passing), 3/4 inch (97 - 100%), 3/8 inch (66 - 87%), No. 4 (43 - 66%), No. 16 (23 - 44%), No. 40 (14 - 31%), No. 200 (7 - 19%), Plasticity index (PI)* 4 - 10. *Imported bentonite can be added to meet the specification. If less than 4 PI then add 2% bentonite by weight. |
| R25 | IF FEDERALLY THREATENED/ENDANGERED SPECIES, FOREST SERVICE SENSITIVE SPECIES, OR BALD OR GOLDEN EAGLES ARE NESTING WITHIN THE VICINITY OF 0.5 MILES OF THE PROJECT AREA, THEN SEASONAL RESTRICTIONS TO OPERATIONS ARE EFFECTIVE DURING THE BREEDING SEASON (MARCH 1 TO SEPTEMBER 1) TO PREVENT DISTURBANCE OF THE AFFECTED SPECIES.Section C (statement of work) |
| R26 | CONTRACTOR SHALL COMPLETE A TOPOGRAPHIC SURVEY OF SITE PRIOR TO DURING AND POST OPERATIONS. SURVEY IS REQUIRED FOR MEASURMENT AND PAYMENT. THE SURVEY SHALL BE PERFORMED BY A LICENSED AND INSURED COMPANY AND PAID UNDER LINE ITEM 154 IN THE SCHEDULE OF ITEMS.Section C (statement of work) |
| R27 | THE CONTRACTOR IS RESPONSIBLE FOR OBTAINING ALL NECESSARY PERMITS FOR THIS TYPE OF CONSTRUCTION, INCLUDING ANY ASSOCIATED FEES. ADEQ AIR QUALITY PERMIT AND NOI (INCLUDING A SWPPP AND EROSION CONTROL PLAN) ARE REQUIRED.Section C (statement of work) |
| R28 | THE BOTTOM OF THE PIT SHALL SLOPE A MINIMUM OF 1% TO PROVIDE POSITIVE DRAINAGE. ALL EXISTING SLOPES AND ANY NEW SLOPES CREATED DURING OPERATIONS SHALL BE LAID AT A MAXIMUM 2:1 SLOPE.Section C (statement of work) |
| R29 | STOCKPILE SIDE SLOPES SHALL BE NO FLATTER THAN 1V:1.5H AND SHALL BE STOCKPILED IN ACCORDANCE WITH FP-24 SECTION 314.05.Section C (statement of work) |
| R30 | ALL AGGREGATE PRODUCED SHALL MEET THE REQUIREMENTS UNDER FSSS SECTION 703.05 FOR SURFACE COURSE AGGREGATE. GRADATION OF STOCKPILE SHALL BE "R3-G" PER FOREST SERVICE SUPPLEMENTAL SPECIFICATION TABLE 703-1.Section C (statement of work) |
| R31 | AGGREGATE SHALL HAVE A MAXIMUM OF 10% FLAT AND ELONGATED PARTICLES. IF APPARENT FLAT AND ELONGATED PARTICLES ARE OBSERVED IN THE MATERIAL. THE CONTRACTOR SHALL HAVE THE MATERIAL TESTED FOR FLAT AND ELONGATED PARTICLES AT THE REQUEST OF THE COR PER ASTM D4791 (1:3 RATIO, PLUS 3/8" SIEVE, CALCULATED BY MASS, WEIGHTED AVERAGE) AT THE CONTRACTOR'S EXPENSE.Section C (statement of work) |
| R32 | CLEARING AND GRUBBING MAY BE REQUIRED IF ADDITIONAL EXPANSION FOR THE PIT DEVELOPMENT IS NECESSARY. ALL REFUSE FROM THIS OPERATION SHALL BE PILED IN LOCATIONS DESIGNATED BY THE COR.Section C (statement of work) |
| R33 | MERCHANTABLE TIMBER AS DEFINED BY THE UTILIZATION STANDARDS SHALL BE HANDLED ACCORDING TO FSSS SECTION 201 AND ALL APPLICABLE SUPPLEMENTS AND DECKED IN LOCATIONS DESIGNATED BY THE COR.Section C (statement of work) |
| R34 | THE CONTRACTOR WILL COMPLY WITH FP-24 SECTION 205, ROCK BLASTING, DURING BLASTING OPERATIONS.Section C (statement of work) |
| R35 | THE CONTRACTOR SHALL PLAN FOR 10 FT DEEP ENTRY FOR INITIAL DRILLING (MIN). THE PROPOSED FOOTPRINT CAN BE MODIFIED AS NECESSARY TO ACCOMMODATE THIS DEPTH.Section C (statement of work) |
| R36 | ALL EXISTING OVERSIZED BOULDERS SHALL BE UTILIZED FOR A VEHICLE BARRIER AND/OR AGGREGATE PRODUCTION PRIOR TO ANY ROCK BLASTING/ROCK EXCAVATION AND/OR PIT EXPANSION WITH APPROVAL FROM THE COR. THE VEHICLE BARRIER SHALL BE PLACED AT ENTRANCE LOCATIONS OF THE PROJECT SITE DESIGNATED BY THE COR. SPACE BETWEEN THE OVERSIZED BARRIER MATERIAL SHALL NOT EXCEED 36 INCHES.Section C (statement of work) |
| R37 | ALL ADDITIONAL OVERSIZED MATERIAL THAT IS NOT USED TO CREATE A VEHICLE BARRIER, REGARDLESS OF SIZE, SHALL BE REDUCED TO A MAXIMUM SIZE OF 2'X2'X2' THROUGHOUT THE PROJECT SITE.Section C (statement of work) |
| R38 | PROTECT IN PLACE ALL EXISTING EQUIPMENT ON SITE, INCLUDING THE GATE AT THE JUNCTION OF COC-211 AND NFSR 211D.Section C (statement of work) |
| R39 | ONE 50 GALLON SPILL KIT OR TWO 30 GALLON SPILL KITS MUST BE LOCATED ON-SITE DURING USE OF HEAVY EQUIPMENT.Section C (statement of work) |
| R40 | ACCESS ROAD SHALL BE CONSTRUCTED USING THE STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS (FP-24 U.S. CUSTOMARY UNITS) AS WELL AS APPLICABLE SUPPLEMENTAL SPECIFICATIONS. |
| R41 | THE SITE TOPOGRAPHIC SURVEY DATA SHALL BE DELIVERED TO THE GOVERNMENT IN THE FOLLOWING FORM: AUTOCAD 2022 SURFACE FILE, OR OTHER FORMAT APPROVED BY THE COR, CLEARLY STATING THE ANALYZED VOLUME OF THE STOCKPILE AND VISUALLY REPRESENTATIVE OF THE STOCKPILE THAT WAS ANALYZED. |
| R42 | MAINTAIN EXISTING DITCH FLOW LINES TO ENSURE POSITIVE DRAINAGE AWAY FROM THE EXISTING INTERSECTING ROAD. |
| R43 | ROLLING DIP NOTES: 1.THE CROSS SLOPE OF THE ROADBED SHALL BE MAINTAINED THROUGH THE DIP. 2.THE DRAIN LINE SHALL BE SKEWED OFF OF THE ROADBED TO ALLOW POSITIVE DRAINAGE, UNLESS OTHERWISE FLAGGED. 3.FOR DIPS ON AGGREGATE SURFACE ROADS, ADD DEPTH OF COMPACTED SURFACE TO DIMENSION (H). 4.ALL DITCHES ASSOCIATED WITH DRAINAGE DIP STRUCTURES SHALL BE MAINTAINED WITHIN THE PROJECT SITE. 5.DIRECTION OF EXISTING WATER FLOW SHALL BE MAINTAINED. |
Recent awards in NAICS 212321
The newest federal contract awards in the same industry code from Department of Agriculture, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2027-06-01 | AMERICAN CLASSIC CONSTRUCTION INC.Forest Service · GAOA BLOOMINGTON LAKE TRAILHEAD GRAVEL CTNF | $34,978 |
| 2026-10-12 | BRINK BROTHERS INC.Forest Service · GRAVEL IN SUPPORT OF WILDLAND FIRE SUPPRESSION ACTIVITY | $28,750 |
| 2026-10-01 | LARRANAGA TRUCKING INCForest Service · 09 - CON - GAOA, GRAVEL FOR CAMPGROUNDS | $104,160 |
| 2026-08-29 | GPC CONSOLIDATED REPORTINGForest Service · GRAVEL | $67,345 |
| 2026-07-27 | PITLIK & WICK, INCForest Service · GRAVEL CRUSHING IDIQ | $88,150 |
| 2026-07-01 | GOLAT & ENGEL CUSTOM GRAVEL CRUSHING INCForest Service · GRAVEL CRUSHING, CNNF | $208,872 |
Source: USAspending.gov, retrieved 2026-11-20. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.