20 requirements and 9 submission rules found in the solicitation documents for 12445127B0005. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.
- Questions Questions shall be submitted via email to cynthia.granderson@usda.gov and are due no later than December 18, 2026, at 12:00 PM Eastern Time.
- Please RSVP so we don¿t leave you behind BID Submittal Deadline: January 6, 2027 @ 1000EST.
- ACKNOWLEDGEMEN T OF AMENDMENTS OFFER (Must be fully completed by offeror) (The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) AMENDMENT NO.
- Bidders MUST be registered in the System for Award Management (SAM) prior to award of contract.
- Submit Product Data before Shop Drawings, and before or concurrent with Samples.
- Bids submitted in response to this solicitation shall be furnished as specified below: The bids must include the following: a.
- Submit Product Data in PDF electronic file.
- Submit Shop Drawings in PDF Electronic Format.
Requirements
| ID | Requirement |
|---|---|
| R1 | The contractor SHALL BID ALL LINES. |
| R2 | Therefore, to be considered responsive, contractors must submit pricing for all items. |
| R3 | Offers providing less than 90 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . |
| R4 | All Prospective Bidders are to attend a mandatory pre-bid meeting. |
| R5 | The bids must include the following: a. Acknowledgement of solicitation amendments (if any). This can be accomplished by submitting the signed SF-30(s). |
| R6 | The bids must include the following: ... b. Scanned copy of fully executed Bid Guarantee (Standard Form 24 and Power of Attorney) |
| R7 | The bids must include the following: ... c. Schedule B completed (Package Attachment 1- Schedule of Items- Format- Adobe PDF |
| R8 | BID Submittal Deadline: January 6, 2027 @ 1000EST. All bids shall be received by 1000EST and emailed to cynthia.grandersooN@usda.gov subject line: 12445127B0005 BID_Co. Name |
| R9 | An authorized person shall sign the bond. Any person signing in a representative capacity (e.g., an attorney-in-fact) must furnish evidence of authority if that representative is not a member of the firm, partnership, or joint venture, or an officer of the corporation involved. |
| R10 | Corporations executing the bond as sureties must appear on the Department of the Treasury's list of approved sureties and must act within the limitations listed therein. |
| R11 | When individual sureties are involved, a completed Affidavit of Individual Surety (Standard Form 28) for each individual surety, shall accompany the bond. |
| R12 | Corporations executing the bond shall affix their corporate seals. Individuals shall execute the bond opposite the word 'Corporate Seal'; and shall affix an adhesive seal if executed in Maine, New Hampshire, or any other jurisdiction requiring adhesive seals. |
| R13 | Type the name and title of each person signing this bond in the space provided. |
| R14 | All work MUST be completed during the evenings with the sealcoating and line painting only taking place on Friday, Saturday, or Sunday. All work must be scheduled with the CO and COR. |
| R15 | all waste material must be removed from the site daily. |
| R16 | A schedule is to be presented to COR and CO within 10 business days of Award. |
| R17 | Notify COR a minimum of two week prior to beginning work. |
| R18 | Notify the COR in writing at least 10 calendar days before moving any construction equipment onto National Forest lands. |
| R19 | Traffic Control and Phasing Plan: Submit a detailed plan showing proposed sequence of operations, closing dates per phase, detour routes for vehicles and pedestrians, and locations of signs, barricades, and flaggers at least 14 days prior to commencing work. |
| R20 | The COR must inspect and approve the prepared surface immediately prior to any crack seal or seal coat application. |
Recent awards in NAICS 237310
The newest federal contract awards in the same industry code from Department of Agriculture, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2027-07-15 | PRICE CONTRACTING INCForest Service · REPLACE AGING TIMBER BRIDGE WITH NEW STEEL BRIDGE WHICH INCLUDES GSR ABUTMENTS. | $545,292 |
| 2027-07-07 | YRU CONTRACTING INCForest Service · BORAH TRAILHEAD/CAMPGROUND RENOVATION - SALMON CHALLIS NATIONAL FOREST | $332,737 |
| 2027-06-15 | TK3, LLCForest Service · TURPIN MEADOW ROAD AGGREGATE FURNISH AND INSTALL | $147,400 |
| 2027-06-15 | BATTLE RIDGE BUILDERS, LLCForest Service · GAOA WARM SPRINGS TRAIL BRIDGE REPLACEMENT BITTERROOT NF | $112,999 |
| 2027-06-01 | ISLAND ENTERPRISES INCForest Service · GAOA 0CL STARRIGAVAN RECREATION AREA DEFERRED MAINTENANCE | $665,300 |
| 2027-06-01 | CUTTING EDGE CONTRACTORS INCForest Service · HTNF PAVEMENT AND REPAIR PROJECT | $298,825 |
Source: USAspending.gov, retrieved 2026-11-20. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.