21 requirements and 4 submission rules found in the solicitation documents for 1240LT27Q0027. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- Submit additional information if required by Contracting Officer.
- Certificates of training for all personnel who will be performing the work under this contract shall be submitted to the U.S.
- The Contractor shall submit to the U.S.
- The contractor shall submit a work plan to the Contracting Officer for approval describing removal techniques and plans.
Requirements
| ID | Requirement |
|---|---|
| R1 | This acquisition is set-aside for small business concerns. The applicable North American Industry Classification Standard Code is 237110 The small business size standard is $45 This acquisition is a Total Small Business Set-Aside. |
| R2 | Therefore, to be considered responsive, contractors must submit pricing for all items. |
| R3 | The quoter shall provide pricing as requested in the Schedule of Items on page 2 of this Request for Quote. Failure to propose pricing for all individual line items may result in a quotation being excluded from further consideration. |
| R4 | The quoter's submission shall demonstrate a clear understanding of the requirements and sufficient experience, personnel, resources, and scheduling capability to successfully complete the work. At a minimum, the quoter shall provide the following: 1. Relevant Experience Provide information for at least two (2) projects completed within the past five (5) years that are similar in size, scope, and complexity to the requirements of this solicitation. Projects should demonstrate experience performing HVAC installation, replacement, renovation, or similar mechanical work. For each project, provide: • Project name and location; • Customer/owner; • Brief description of the work performed; • Approximate contract value; • Date of completion; and • Customer point of contact, including telephone number and/or email address. |
| R5 | 2. Ability to Meet the Required Schedule Provide a brief description of how the quoter intends to accomplish the work within the performance period identified in the SOW. The response shall identify, at a minimum: • Anticipated staffing and key personnel; • Major equipment and/or subcontractors anticipated for performance; • Availability and anticipated lead times for major HVAC equipment and materials; and • Any known scheduling constraints that could affect timely completion. |
| R6 | 3. Exceptions or Limitations Identify and provide a detailed explanation of any requirement contained in the SOW that the quoter cannot successfully accomplish. If there are no exceptions or limitations, the quoter shall affirmatively state that it can perform all requirements of the SOW. |
| R7 | The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers. |
| R8 | The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. |
| R9 | The Contractor shall submit the following payment protections: Payment Bond (b) The amount of the payment protection shall be 100 percent of the contract price. (c) The submission of the payment protection is required within 15 days of contract award. |
| R10 | The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause. |
| R11 | Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including- (A) A description of the foreign and domestic construction materials; (B) Unit of measure; (C) Quantity; (D) Price; (E) Time of delivery or availability; (F) Location of the construction project; (G) Name and address of the proposed supplier; and (H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause. |
| R12 | 1. Workers' Compensation and Employer's Liability. The contractor must comply with applicable Federal and State workman’s compensation and occupational disease statutes. If these diseases are not covered, they must be included under the employer's liability section of the policy, unless contract operations are commingled with the contractor's commercial operations. Employer's liability coverage of at least $100,000 is required, except in States with exclusive or monopolistic funds that prohibit private carriers from providing workers' compensation. |
| R13 | 2. General Liability. The contractor must have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence. |
| R14 | 3. Property Liability (Remove if not required): The contractor must have property damage liability insurance required in the amount of $250,000 per occurrence. |
| R15 | 4. Automobile Liability. The contractor must have comprehensive automobile liability insurance covering bodily injury and property damage for all vehicles used in the contract. For U.S. operations, the coverage must be at least $200,000 per person, $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage or loss. |
| R16 | 5. Aircraft Public and Passenger Liability. When using aircraft for the contract, the contractor must have aircraft public and passenger liability insurance. Coverage must be at least $200,000 per person, $500,000 per occurrence for bodily injury, excluding passengers. For passenger injury, coverage must be at least $200,000 multiplied by the number of seats or passengers, whichever is greater. |
| R17 | All workers who perform the work for lead paint abatement described herein shall have successfully completed a training course in lead abatement within the previous five (5) years approved by the Federal Occupational Safety and Health (OSHA) regulations.Section C (statement of work) |
| R18 | The Contractor shall provide a Health and Safety Plan for review and acceptance by the Contracting Officer. No work will commence until acceptance of the plan by the Contracting Officer.Section J |
| R19 | Historic Treatment Specialist Qualifications: A firm that employs personnel, including supervisory personnel, experienced and skilled in the processes and operations indicated. Must demonstrate successful rehabilitation of similar projects.Section C (statement of work) |
| R20 | When providing historic preservation or rehabilitation services, the work shall be accomplished by or under the direct supervision of someone meeting the Secretary of the Interior’s Professional Qualification Standards for Historic Architecture.Section C (statement of work) |
| R21 | The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.Section C (statement of work) |
Recent awards in NAICS 237110
The newest federal contract awards in the same industry code from Department of Agriculture, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2027-06-01 | WIGGINS EXCAVATION LLCForest Service · INSTALLING UTILITIES AND TRAILER PADS FOR A FOREST SERVICE BUNKHOUSE FACILITY | $111,330 |
| 2026-11-01 | AMG CONSTRUCTION COMPANY, INCORPORATEDForest Service · DEMOLITION AND REPLACEMENT OF SEWER LINE AND ASSOCIATED APPURTENANCES WITHIN FOREST SERVICE OWNED FACILITY AT THE BIG PINEY DISTRICT RANGER'S OFFICE. | $135,775 |
| 2026-10-26 | EMPIRE PUMP CORPForest Service · DECOMMISSION WELLS PER ADWR AND SEPTIC TANKS PER ADEQ REGULATIONS. | $149,725 |
| 2026-10-05 | VICTORY CONTRACTING LLCForest Service · CONTRACT FOR DEVELOPMENT AND CONSTRUCTION OF A POTABLE WATER WELL AT THE LAKE CONASAUGA CAMPGROUND (GA EPD SYSTEM GA2130026). WORK SHALL BE COMPLETED BY A CONTRACTOR LICENSED IN THE STATE OF GEORGIA. | $93,500 |
| 2026-10-01 | JONES DRILLING CO INCForest Service · LAVA LANDS PUMP REPLACEMENT & WELL SURVEY - DESCHUTES NATIONAL FOREST | $75,000 |
| 2026-10-01 | J & J EXCAVATING AND TRUCKING, INCForest Service · SULA & WEST FORK SEWER CLEANOUTS | $38,407 |
Source: USAspending.gov, retrieved 2026-10-29. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.