GAOA Brainard Lake Recreation Area Deferred Maintenance: requirements and submission rules
45 requirements and 0 submission rules found in the solicitation documents for 1240LT27Q0004. Use them as the start of your compliance matrix.
Submission rules that can disqualify a bid
- None detected automatically: read the instructions to offerors.
Requirements
| ID | Requirement |
|---|---|
| R1 | RSVP for the site visit before COB on 11/16/2026 to kamber.box@usda.gov. ensure the email in your response is a good contact email so you can be notified if there is a cancellation or the pre-bid is moved to a virtual meeting. The site visit is NOT mandatory. |
| R2 | All Contractors shall visit the project sites and acquaint themselves with current conditions prior to submitting a bid for these services. |
| R3 | No work shall happen on weekends or Federally recognized Holidays. Work shall be allowed during daylight hours. |
| R4 | Recreation site will remain open to the public during construction. Contractor shall install and maintain suitable barriers to ensure the protection of the public, employees, and facilities. All signs shall meet MUTCD standards. |
| R5 | Contractor shall be in compliance with current OSHA 1910 and 1926 regulations and requirements. |
| R6 | Any sub-contractors shall be under the superintendence by the Prime. |
| R7 | The contractor is responsible for adhering to the contract specifications and for quality control. |
| R8 | The Contractor shall furnish all management, labor, equipment, supervision, tools, materials, transportation, operating supplies, supervision, workman’s compensation, unemployment insurance and incidentals necessary to perform the work in accordance with the specification and provisions of the contract. |
| R9 | Large boulders or rock material shall remain on-site unless otherwise directed by the Contracting Officer. |
| R10 | The contractor shall be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, County, and Municipal laws, codes, and regulations applicable to the performance of the work. |
| R11 | The contractor shall be responsible for all damages to persons or property, which occur as a result of the Contractor’s performance or negligence. |
| R12 | ALL WORK TO CONFORM TO FOREST SERVICE, STATE, AND COUNTY CODES, LAWS, AND REGULATIONS. |
| R13 | CONTRACTOR SHALL COORDINATE ACTIVITIES WITH AFFECTED UTILITY COMPANIES AND SHALL NOTIFY THE UTILITY NOTIFICATION CENTER (811) AT LEAST 48 HOURS PRIOR TO THE START OF CONSTRUCTION ACTIVITIES. |
| R14 | ALL CONSTRUCTION ACTIVITIES SHALL BE IN COMPLIANCE WITH CURRENT INTERNATIONAL BUILDING CODES AND STATE OF COLORADO ON-SITE WASTEWATER REGULATIONS. |
| R15 | CONTRACTOR IS RESPONSIBLE FOR NOTIFYING CONTRACTING OFFICER (CO) 72 HOURS IN ADVANCE OF ANY POTENTIAL DISRUPTIONS TO UTILITY SERVICES OR PROGRAMMED VISITOR ACTIVITIES. |
| R16 | CONTRACTOR SHALL TAKE ALL NECESSARY PRECAUTIONS TO PROTECT ADJACENT PUBLIC AND PRIVATE LANDS FROM STORMWATER RUN-OFF OR DEBRIS AND EXCESSIVE DUST. |
| R17 | CONTRACTOR SHALL REMOVE ANY MUD OR CONSTRUCTION TRACKED ONTO TRAILS, PARKING LOTS OR ROADWAYS WITHIN 24 HOURS. |
| R18 | LAYOUT AND ALIGNMENT OF ALL PAVING SURFACES TO BE FIELD STAKED BY CONTRACTOR AND APPROVED BY CO PRIOR TO FORM INSTALLATION. |
| R19 | ALL SURFACE CONCRETE SHALL HAVE A MEDIUM BROOM FINISH WITH TOOLED EDGES. |
| R20 | CONTRACTOR TO PROVIDE ALL TEMPORARY BRACING, SUPPORTS, SHORING, ETC. AS NEEDED FOR CONSTRUCTION AND PER ALL LOCAL CODES. |
| R21 | DO NOT SCALE OR DIGITIZE FROM HARD COPY DRAWINGS. |
| R22 | CONTRACTOR TO VERIFY ALL QUANTITIES. |
| R23 | ALL ACCESSIBLE ROUTES SHALL ADHERE TO ALL FEDERAL ACCESSIBILITY GUIDELINES (FSORAG, ABA, ETC.) |
| R24 | CONTRACTOR IS RESPONSIBLE FOR VERIFYING SITE CONDITIONS PRIOR TO COMMENCING DEMOLITION. NOTIFY CONTRACTING OFFICER (CO) IMMEDIATELY OF ANY CONFLICTS OR CONDITIONS THAT VARY FROM THE INFORMATION PROVIDED. |
| R25 | CONTRACTOR SHALL PROTECT ALL EXISTING FEATURES THAT ARE NOT TO BE REMOVED ADJACENT TO THE CONSTRUCTION AREA INCLUDING, BUT NOT LIMITED TO, ADJACENT BUILDINGS, FOUNDATIONS WALLS, CURBS, AND ABOVE AND BELOW GROUND UTILITIES. ANY DAMAGE TO FINISH OR FOOTINGS TO BE REPAIRED BY CONTRACTOR AT CONTRACTOR'S EXPENSE. |
| R26 | TREE PROTECTION MEASURES TO BE IN PLACE PRIOR TO COMMENCING DEMOLITION. |
| R27 | WITHIN THE DRIP LINE OR ZONE OF ANY PROTECTED EXISTING TREE, THERE SHALL BE NO CUT OR FILL OVER FOUR-INCH DEPTH. |
| R28 | NO TREE DAMAGING ATTACHMENTS, WIRES, SIGNS, OR PERMITS MAY BE FASTENED TO ANY PROTECTED TREE. |
| R29 | THE INSTALLATION OF UTILITIES, OR ANY UNDERGROUND FIXTURE REQUIRING EXCAVATION DEEPER THAN SIX (6) INCHES SHALL BE ACCOMPLISHED BY BORING UNDER THE ROOT SYSTEM OR PROTECTED EXISTING TREES AT A MINIMUM DEPTH OF TWENTY-FOUR (24) INCHES. |
| R30 | CONTRACTOR TO FIELD LOCATE PERIMETER FENCING FOR DEMOLITION OPERATIONS FOR CO APPROVAL PRIOR TO COMMENCING DEMOLITION. ANY AREA NEEDED FOR TEMPORARY STOCKPILING OF REMOVED MATERIALS SHALL BE SECURELY FENCED AND AND THE LOCATION APPROVED BY THE CO. |
| R31 | CONTRACTOR IS RESPONSIBLE FOR REMOVAL OF ALL EXCESS MATERIALS. |
| R32 | FOR EXCAVATION/DEMOLITION OCCURRING DIRECTLY ADJACENT TO ANY FOOTINGS, CONTRACTOR TO SHORE OR SECURE FOOTINGS TO PREVENT EROSION OF SUB-GRADE MATERIAL. |
| R33 | UPON REMOVAL OF ALL ITEMS, ALL IMPACTED ARES TO BE FILLED, AMENDED AND COMPACTED AS REQUIRED BY EACH TYPE OF NEW CONSTRUCTION. |
| R34 | TREE REMOVAL TO INCLUDE COMPLETE ROOTBALL REMOVAL AND REMOVAL OF LARGE ROOTS OVER 2-INCHES IN DIAMETER. TREE PITS TO BE BACKFILLED AND RE-COMPACTED TO APPROXIMATE EXISTING GRADE IF CONSTRUCTION OPERATIONS WILL NOT IMMEDIATELY COMMENCE TO ALLOW SETTING AT PROPOSED GRADE. ANY OPEN PITS TO BE FENCED IF BACKFILL CANNOT BE COMPLETED IMMEDIATELY. |
| R35 | CONTRACTOR IS RESPONSIBLE FOR ANY DAMAGE TO ANY ON-SITE, OFF-SITE, PUBLIC OR PRIVATE FACILITY OR FEATURE AS A RESULT OF THE CONSTRUCTION PROCESS FOR THIS PROJECT. |
| R36 | CONTRACTOR TO PROVIDE PROPOSED TEMPORARY FENCING PLAN TO PROVIDE SUFFICIENT SPACE FOR CONSTRUCTION OPERATIONS WHILE MAINTAINING SAFE ACCESS TO OTHER NATIONAL FOREST USE AREAS. |
| R37 | ALL MATERIALS TO BE REMOVED SHALL BE DISPOSED OF OR RECYCLED AT AN APPROVED FACILITY OFF NATIONAL FOREST SYSTEM LANDS. |
| R38 | CONTRACTOR SHALL FLAG TREES NEEDING TO BE REMOVED AND CONTRACTING OFFICER SHALL APPROVE PRIOR TO REMOVAL. |
| R39 | ALL EXISTING HISTORIC CCC ELEMENTS WILL REMAIN AND MUST BE PROTECTED DURING CONSTRUCTION. |
| R40 | CONTRACTOR SHALL PROTECT EXISTING ASSETS AND INFRASTRUCTURE SET TO REMAIN AND BE PROTECTED. |
| R41 | CONTRACTOR TO STAKE IN FIELD ALL SIGN LOCATIONS AND SHALL BE APPROVED BY CONTRACTING OFFICER BEFORE INSTALLATION. |
| R42 | ALL SIGNS TO BE FURNISHED AND INSTALLED IN ACCORDANCE WITH FOREST SERVICE SIGN & POSTER GUIDELINES (EM-7100) AND MANUAL FOR UNIFORM TRAFFIC CONTROL DEVICES (MUTCD). |
| R43 | CONTRACTOR SHALL FURNISH AND INSTALL ALL NEW SIGNS. SIGN DESIGNS AND LAYOUTS SHALL BE APPROVED BY THE C.O. PRIOR TO SIGN INSTALLATION. |
| R44 | TRAIL ALIGNMENT SHALL BE STAKED IN THE FIELD BY THE CONTRACTOR AND APPROVED BY THE CONTRACTING OFFICER. |
| R45 | BARRIER ROCK LOCATIONS SHALL BE STAKED IN THE FIELD BY THE CONTRACTOR AND APPROVED BY THE CO. |
Recent awards in NAICS 237310
The newest federal contract awards in the same industry code from Department of Agriculture, since 1 October 2024. Use them to see who wins this kind of work and at what value.
| Start | Awardee and buyer | Award value |
|---|---|---|
| 2027-07-15 | PRICE CONTRACTING INCForest Service · REPLACE AGING TIMBER BRIDGE WITH NEW STEEL BRIDGE WHICH INCLUDES GSR ABUTMENTS. | $545,292 |
| 2027-07-07 | YRU CONTRACTING INCForest Service · BORAH TRAILHEAD/CAMPGROUND RENOVATION - SALMON CHALLIS NATIONAL FOREST | $332,737 |
| 2027-06-01 | CUTTING EDGE CONTRACTORS INCForest Service · HTNF PAVEMENT AND REPAIR PROJECT | $273,075 |
| 2027-06-01 | NORTERRA SERVICES LLCForest Service · SELWAY SUSPENSION BRIDGE RECONSTRUCTION | $249,000 |
| 2027-06-01 | PRICE CONTRACTING INCForest Service · PRIEST PASS ROAD RECONSTRUCTION | $141,474 |
| 2027-06-01 | GILBERT AND SONS CONSTRUCTION LLCForest Service · NFSR 27 ASPHALT REPAIRS TASK ORDER UNDER WESTERN OREGON ROAD CONSTRUCTION IDIQS | $144,305 |
Source: USAspending.gov, retrieved 2026-10-28. Award value is the obligated amount reported by the agency.
Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.
Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.
Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.