27 requirements and 5 submission rules found in the solicitation documents for 1240BE27Q0001. Use them as the start of your compliance matrix.

Solicitation number
1240BE27Q0001
Agency
AGRICULTURE, DEPARTMENT OF / FOREST SERVICE / WALLOWA WHITMAN NATIONAL FOREST
NAICS
237310
Set-aside
Small Business Set Aside - Total
Responses due
22 October 2026 (closed)
Official notice
View on SAM.gov

Submission rules that can disqualify a bid

  • Questions Questions shall be submitted via email to andrea.pollock@usda.gov and are due no later than October 15, 2026, at 1:00 PM Mountain Time.
  • The quote due date is 10/22/2026 at 1:00 PM MT.
  • ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning O ffers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing The above numbered solicitation is amended as set forth in Item 14.
  • Any taxes or surcharges which the supplier or licensor seeks to pass along to the Government as end user will be governed by the terms of the associated Government contract or order and must be submitted to the Contracting Officer for a determination of applicability prior to invoicing unless specifically agreed otherwise.
  • Some examples of what would be routinely used for simplified acquisitions are: FAR 52.212-1 is amended as follows: Submission Method and Address for Quotations Quotes shall be submitted via email to: Andrea Pollock, Contracting Officer Email: andrea.pollock@usda.gov The solicitation provides no alternate delivery method.

Requirements

IDRequirement
R1OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
R2Therefore, to be considered responsive, contractors must submit pricing for all items.
R3All offerors must provide the following minimum information and documentation with their quotations to be considered responsive and have their offers evaluated: • Equipment suitability & capacity: Demonstration of crusher type(s), capacity (tonnage per hour), and suitability for the specified rock type and desired gradation. • Production quality control: Methods to ensure consistent gradation, cubical shape, removal of fines, and compliance with contract specs. • Operational efficiency: Proposed workflow, sequencing, expected production rates, and strategies for minimizing downtime.
R4The offeror shall provide pricing as requested in the Schedule of Items on page 1 of this Request for Quote. Failure to propose pricing for all individual line items may result in a quotation being excluded from further consideration.
R5Past Performance information provided by the contractor shall only include: • Performance on contracts within the last 3 years involving: Similar rock types (e.g., basalt, limestone), Comparable production volumes and geography, Timely completion and contract adherence. • Client references addressing quality, responsiveness, cost control, and problem resolution.
R6The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer.
R7The Offeror agrees to hold the prices in its offer firm for 90 calendar days from the date specified for receipt of offers.
R8The backhoe and grader shall be priced as firm-fixed-price lump sum items, inclusive of operators, fuel, transportation, maintenance, and all associated costs. The lump sum price shall cover all work described in the PWS. No hourly pricing will be used for these CLINs.
R9All option quantities shall be completed during the same time period as base work. No separate mobilization will be authorized.
R10In accordance with the RFO FAR, it is the contractor's sole responsibility to obtain, maintain, and comply with all permits, licenses, registrations, certifications, and authorizations required to perform the work under this contract, whether federal, state, or local.
R11The Contractor shall furnish all labor, supervision, equipment, transportation, (except those designated as Government-furnished), and incidentals for crushing, stockpiling and site reclamation activities within The scope of this contract.
R12The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with this PWS. The QCP shall be submitted to the COR for acceptance within 14 calendar days of award, (Deliverable 01).
R13The contractor shall submit a work plan for acceptance to the COR within 14 calendar days of award. (Deliverable 02). At a minimum the work plan shall include: 1) Timeline to completion including proposed project acceptance dates. 2) Key Personnel. 3) Traffic Control Plan, 4) Fire Plan. 5) Contractor equipment storage request.
R14Site reclamation shall be completed such that the floor of the pit area drains and the side slopes and headwall are sloped 1.0V:1.5H.
R15Contractor will be responsible for determining the crushed volume by stockpile survey (in place).
R16Work shall comply with The American Association of State Highway and Transportation Officials, AASHTO T 27 T 11, listed in the Quality Assurance Surveillance Program (QASP) at Attachment 2. Aggregate shall conform to FP-24 Section 703, Table 703-1 Target Values for Subbase, Base, and Surface Course Gradation, Grading Designation G.
R17The Contractor shall replace without additional compensation sufficient suitable materials to complete the portion of the work which was originally contemplated to be constructed with such material.
R18The contractor shall submit an equipment and materials storage to the COR for approval within 14 calendar days of contract award. (Deliverable 3)
R19The Contractor shall provide a Contract Manager and designated alternate, as applicable, who has full authority to act for the Contractor on all contract matters relating to this contract. The Contract Manager or alternate shall be available during the Government's regular working hours and shall be available on site within one hour after the Government's regular working hours. The Contractor shall submit the name and contact information of the contract manager in writing to the COR within 7 calendar days of award. (Deliverable 04)
R20The Contractor must submit payment requests electronically using the invoice instructions provided in the contract.
R21By requesting payment under this award, the contractor certifies that, to the best of its knowledge and belief, it does not operate programs promoting diversity, equity, and inclusion that violate any applicable Federal anti-discrimination laws.
R22Place excess material at government-approved agreed to location(s), at no additional cost to government.
R23Submit the following for approval with the quality control plan: (a) Quality control manager (QCM). Furnish a QCM who has experience in construction, inspection, quality control and material testing on construction projects of similar type and scope. (b) Testers. Provide testers with at least 1 years' experience in the type of sampling and testing required, and with one of the following for the type of sampling and testing performed: (1) National Institute for Certification in Engineering Technologies (NICET) Level II certification in construction materials testing for similar material types or equivalent state or industry certification; (2) Certification by a state or regional certification program, such as Western Alliance for Quality Transportation Construction or Northeast Transportation Technician Certification Program; or (3) At least 1 year of employment by an AASHTO accredited laboratory performing equivalent sampling and testing with competence according to AASHTO R 18.
R24Maintain complete testing and inspection records by pay item number and make them accessible to the CO.
R25Build aggregate stockpiles in layers no more than 36 inches in thickness. Make the side slopes of each layer no flatter than 1V:1.5H. Spread aggregates with trucks or other approved pneumatic-tire equipment. Complete each layer before depositing aggregates on the next layer. Do not allow aggregates from the layer being built to run down over lower layers. Do not drop aggregates from a bucket or spout in one location to form a cone-shaped pile. Do not push aggregates into piles. Make the stockpiles neat and regular in shape. Do not track dirt or other foreign matter onto the stockpile material. Space stockpiles far enough apart or install partitions to prevent the mixing of aggregate gradations.
R26If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
R27The contractor or subcontractor is required to furnish all employees with an adequate number of uniforms without cost or to reimburse employees for the actual cost of the uniforms.

Recent awards in NAICS 237310

The newest federal contract awards in the same industry code from Department of Agriculture, since 1 October 2024. Use them to see who wins this kind of work and at what value.

StartAwardee and buyerAward value
2027-07-15PRICE CONTRACTING INCForest Service · REPLACE AGING TIMBER BRIDGE WITH NEW STEEL BRIDGE WHICH INCLUDES GSR ABUTMENTS.$545,292
2027-07-07YRU CONTRACTING INCForest Service · BORAH TRAILHEAD/CAMPGROUND RENOVATION - SALMON CHALLIS NATIONAL FOREST$332,737
2027-06-01CUTTING EDGE CONTRACTORS INCForest Service · HTNF PAVEMENT AND REPAIR PROJECT$273,075
2027-06-01NORTERRA SERVICES LLCForest Service · SELWAY SUSPENSION BRIDGE RECONSTRUCTION$249,000
2027-06-01PRICE CONTRACTING INCForest Service · PRIEST PASS ROAD RECONSTRUCTION$141,474
2027-06-01GILBERT AND SONS CONSTRUCTION LLCForest Service · NFSR 27 ASPHALT REPAIRS TASK ORDER UNDER WESTERN OREGON ROAD CONSTRUCTION IDIQS$144,305

Source: USAspending.gov, retrieved 2026-10-18. Award value is the obligated amount reported by the agency.

Automated reading of the documents attached to the notice on SAM.gov when it was posted. Amendments may change them. The official notice always takes precedence.

Bidding on this? Before you submit, check that every claim in your draft is backed by your records and every requirement above is answered.

Amendment issued? Compare it with the original to see every changed requirement, date and limit, free.

Get new solicitations that match your business, free

Enter NAICS codes, keywords or both. No email when nothing matches. Unsubscribe in one click.